A total station is a modern electronic surveying instrument that integrates the functions of a theodolite for angle measurement, an electronic distance measurement device for distance measurement, and a microprocessor with data storage capability for computations and recording. In a single compact instrument the surveyor can measure horizontal angles, vertical angles and slope distances, and the built-in microprocessor immediately computes horizontal distances, vertical distances, differences in elevation and coordinates of the observed points. The instrument displays the results on a screen and stores them in its internal memory, from which the data can be downloaded to a computer for further processing in surveying software.
The total station has revolutionised surveying practice because it makes the survey much faster, more accurate and less dependent on manual booking. Traditional surveying required separate instruments for measuring angles and distances, and the calculations were performed by hand with the aid of tables and logarithms, a process that was slow and prone to arithmetic errors. With a total station, the angle and distance measurements are made optically and electronically to high precision, the corrections for curvature and refraction, earth's mean sea level and scale factor can be applied automatically, and the coordinates of hundreds of points can be obtained and stored in a single day's work. For this reason the total station is now the standard instrument for engineering surveys, topographic surveys, setting out works, and monitoring deformation.
In this chapter we will study the construction and working of a total station, its components and their functions, the process of setting up and measuring with the instrument, and the various modes of measurement it offers. We will understand how the instrument computes coordinates, examine the sources of error and the accuracy specifications, and learn about permanent adjustments and the care required for handling the instrument. Since competitive examinations increasingly include questions on modern surveying instruments, the key features, capabilities and applications of the total station are presented in an examination-oriented manner.
The total station consists of three main assemblies: the electronic theodolite, the electronic distance meter, and the microprocessor. The electronic theodolite measures the horizontal and vertical angles by means of rotary encoders, which convert the rotation of the alidade into digital angle readings. Modern total stations use absolute encoders that give an absolute angular position, so no initialisation or reference is required each time the instrument is turned on. The angles are displayed to a least count that may be as small as one second, and the readings are accurate and free from the interpolation errors associated with reading a graduated circle through an eyepiece.
The electronic distance meter (EDM) of the total station measures the slope distance to a prism reflector by transmitting an infrared or laser beam and measuring either the phase difference or the time of travel of the reflected signal. The prism reflector is mounted on a staff and held at the point to be measured. The slope distance measured by the EDM is combined with the vertical angle measured by the theodolite in the microprocessor, which computes the horizontal distance and the vertical difference using the relationships D = L cos theta and V = L sin theta, where L is the slope distance and theta the vertical angle.
The microprocessor performs all the computations and offers several measurement modes. In the coordinate measurement mode, the instrument can be set up over a point of known coordinates and orientation, after which every observed point is expressed directly in terms of its northing, easting and elevation. In the stake-out mode, the instrument guides the surveyor to set out a point of given coordinates by showing the required horizontal angle, horizontal distance and vertical difference. In the traverse mode the instrument automatically computes the next station coordinates from the measured angle and distance, and in the remote elevation mode it can compute the height of an inaccessible point. The measured data and computed results are stored in internal memory or on a data card, and can be transferred to a computer.
Before measurement, the total station must be set up over the survey station using a plumb bob or optical plummet, levelled with the three foot screws, and then the target or prism staff must be held vertically at the point to be observed. The instrument is initialised by switching it on and, if an absolute encoder type, no further setting is required. The surveyor selects the desired measurement mode, sights the prism by coarse pointing followed by fine pointing using the tangent screws or servo motor, and presses the measure key. The instrument then displays the slope distance, horizontal distance, vertical distance, and the vertical and horizontal angles, and stores the reading if required.
For coordinate surveys, the instrument is set up at a point whose coordinates and height are known, and the horizontal circle is oriented by sighting a second known point and setting the bearing to it. Once the orientation is set, every observed point yields its coordinates directly. The accuracy of the final coordinates depends not only on the instrument but also on the correct centring, levelling and orientation, and on the verticality of the prism staff. Prism constants must also be entered correctly, since the prism produces an apparent shortening of the measured distance by an amount equal to the prism constant.
In the stake-out procedure, the coordinates of the point to be set out are entered into the instrument. The instrument computes the horizontal angle and the horizontal distance from the current station to the point, and the surveyor rotates the alidade until the horizontal angle display reads zero for the required direction. The prism is then moved along that direction until the horizontal distance display also reads zero, and the point is marked. This process is repeated for all the points of the layout, making setting out fast, accurate and convenient.
Example 1: A total station measures a slope distance of 125.00 m to a prism with a vertical angle of 15 degrees. Find the horizontal distance and the vertical difference.
Solution: The horizontal distance D = L cos theta = 125 x cos 15 = 125 x 0.9659 = 120.74 m. The vertical difference V = L sin theta = 125 x sin 15 = 125 x 0.2588 = 32.35 m. Hence the horizontal distance is 120.74 m and the vertical difference is 32.35 m.
Example 2: The horizontal circle reading to a reference station is 45 degrees 30 minutes and the required bearing of the next traverse line is 120 degrees. By how much must the alidade be rotated?
Solution: The required change in horizontal circle reading = 120 degrees - 45 degrees 30 minutes = 74 degrees 30 minutes. Hence the alidade must be rotated clockwise through 74 degrees 30 minutes.
Example 3: A total station at station A (northing 1000.00 m, easting 2000.00 m) observes a point B with a horizontal distance of 80.00 m and a bearing of 30 degrees. Find the coordinates of B.
Solution: Delta N = D cos bearing = 80 x cos 30 = 80 x 0.8660 = 69.28 m. Delta E = D sin bearing = 80 x sin 30 = 80 x 0.5 = 40.00 m. Northing of B = 1000 + 69.28 = 1069.28 m. Easting of B = 2000 + 40 = 2040.00 m. Hence B has coordinates (1069.28, 2040.00).
| Component | Function |
|---|---|
| Electronic theodolite | Measures horizontal and vertical angles with rotary encoders |
| EDM unit | Measures slope distance using infrared or laser beam |
| Microprocessor | Computes horizontal distance, vertical difference and coordinates |
| Display and keypad | Shows readings and allows mode selection |
| Internal memory / data card | Stores measured data for download |
| Tribrach and optical plummet | Centring and levelling over the station |
| Feature | Total station | Conventional theodolite |
|---|---|---|
| Angle measurement | Digital electronic encoders | Graduated circle, optical reading |
| Distance measurement | Electronic, automatic | Requires separate tape or EDM |
| Computation | Built-in microprocessor | Manual calculation |
| Data storage | Internal memory and download | Manual booking |
| Accuracy | High, least count up to 1 second | Moderate |
| Setting out | Stake-out mode built in | Manual angle and distance methods |
flowchart TD
A[Total Station] --> B[Electronic theodolite]
A --> C[Electronic distance meter]
A --> D[Microprocessor]
A --> E[Data storage]
B --> B1[Rotary encoders]
B --> B2[Horizontal and vertical angles]
C --> C1[Infrared / laser beam]
C --> C2[Slope distance to prism]
D --> D1[Horizontal distance computation]
D --> D2[Vertical difference computation]
D --> D3[Coordinate computation]
E --> E1[Internal memory]
E --> E2[Data card and download]
A --> F[Modes]
F --> F1[Coordinate measurement]
F --> F2[Stake-out]
F --> F3[Traverse]
The following diagrams show the measurement geometry of the total station and the coordinate computation scheme.
The total station is the modern workhorse of surveying, combining angle measurement, distance measurement and computation in a single instrument. In this chapter we have studied its three main assemblies, the electronic theodolite with rotary encoders, the electronic distance meter using infrared or laser radiation, and the microprocessor that performs the necessary computations. We have understood how slope distance and vertical angle are combined to give the horizontal distance and vertical difference, how coordinates are computed from bearing and distance, and how the instrument is used for both measurement and stake-out. We have also solved numerical examples on slope distance reduction and coordinate computation, and discussed the common errors such as prism constant omission and zenith angle misuse. The total station has made surveying faster and more accurate, and a candidate who understands its working, its modes and its correct handling will be well prepared to answer modern surveying questions in competitive examinations.