1. Introduction

Site selection is the first and most decisive step in the entire process of building construction, because every later decision, from the type of foundation to the cost of the project, depends on the land chosen for the structure. A building is designed to serve its occupants for fifty years or more, and no amount of good structural design can compensate for a site that is waterlogged, unstable, poorly accessible or located far from essential services. In competitive examinations such as SSC JE, RRB JE and state AE/JE papers, questions on site selection appear in the building construction section with great regularity, because the topic tests whether a candidate understands the practical, economic and environmental considerations that a site engineer must weigh before the first brick is laid.

Site selection is governed by two broad sets of factors: the requirements of the owner and the inherent characteristics of the land. The owner's requirements include the purpose of the building, the number of floors, the plot area and the budget. The characteristics of the land include its soil conditions, water table, orientation with respect to the sun and wind, proximity to roads and public utilities, neighbourhood environment and the legal status of the land. A good site is one where the soil is firm, the water table is low, the surroundings are clean and the plot is legally clear of disputes, so that construction can proceed without interruption and the building can serve safely for its full design life.

In this chapter we will study the criteria that make a site suitable for building construction, the classification of soils that affect foundation selection, the importance of orientation in relation to sun and wind, and the requirements of a building site such as water supply, drainage and power. We will also understand why orientation is critical in tropical countries like India, where the sun's path and the monsoon winds decide how hot a building becomes in summer and how well it dries after rain. This knowledge is fundamental because it links the practical art of the site engineer with the scientific design of buildings.

2. Factors Governing Selection of Site

The selection of a building site is based on a number of inter-related factors, and the site engineer must assign proper weight to each of them before finalising the plot. The first and most obvious factor is the purpose of the building. A school, a hospital, a factory, a residential apartment and a cinema hall all have different site requirements. A hospital requires a quiet, dust-free locality with easy access for ambulances, whereas a factory requires a large level plot near a highway or railway line so that raw material and finished goods can be moved economically. A school must be located away from heavy traffic and noise, preferably in a residential locality where children can walk safely.

The second factor is the size and shape of the plot. The plot must be sufficiently large to accommodate the building, the mandatory open spaces for light and ventilation, the set-backs required by municipal byelaws and future expansion. The shape should preferably be regular, because irregular plots cause a waste of space in the corners and make orientation difficult. The third factor is the physical features of the site. The site should be level or gently sloping, because excessive cutting and filling to make it level adds to the cost. A slope that drains rainwater away from the building is an advantage, whereas a low-lying hollow that collects water after rain must be avoided.

The fourth factor is the nature of the soil. The soil must be able to carry the load of the foundation without excessive settlement. Firm soils such as gravel, sand and stiff clay are preferred, whereas black cotton soil, which swells when wet and shrinks when dry, is very undesirable because it causes severe cracking of foundations and walls. The fifth factor is the water table. A high water table creates difficulty in excavating the foundation, increases the cost of damp proofing, and may cause the basement to flood. The sixth factor is the availability of public services such as water supply, sewerage, electricity, telephone and gas lines, because connecting these services over long distances adds substantially to the project cost.

3. Soil Investigation and Bearing Capacity

Before foundations are designed, the soil at the site must be investigated to determine its bearing capacity, which is the safe pressure that the soil can carry per unit area without shear failure or excessive settlement. Soil investigation is usually done by digging trial pits or by boring boreholes at the proposed locations of the columns. The number of trial pits depends on the size of the site; for a small building one or two pits may suffice, while for a large multi-storey building several boreholes are drilled. Samples are taken from each stratum and tested in the laboratory for their strength, compressibility and moisture content.

The bearing capacity of common soils in tonnes per square metre is a favourite examination value. Hard rock has a safe bearing capacity of about 330 t/m2, soft rock about 45 t/m2, gravel or shingle about 40 t/m2, compact sand about 30 t/m2, loose sand about 10 t/m2, compact clay about 10 t/m2, soft clay about 5 t/m2, and black cotton soil or made-up soil only about 2 t/m2. These values show why rock and compact gravel are the best foundation beds, and why black cotton soil must either be avoided or replaced by lime or sand stabilisation before any structure is built on it.

The water table is determined from the trial pits and boreholes by measuring the depth at which water stands. If the water table is high, the foundation must be placed deeper or the pit must be dewatered during construction, and damp proofing measures must be strengthened. The presence of underground streams, springs or old wells on the site is dangerous, because they cause unequal settlement. Similarly, an old rubbish dump or made-up ground is never fit for direct foundation, and any loose or organic material must be excavated and replaced with compacted sand or gravel in layers.

4. Building Orientation and Its Requirements

Orientation is the positioning of the building on its site with respect to the directions of the compass, done in such a way that the building receives maximum comfort with minimum cost. In India, the sun rises in the east, reaches its maximum height over the south in the northern hemisphere and sets in the west, while the prevailing summer winds are from the south-west. Good orientation therefore means placing the longer axis of the building along the east-west direction, so that the largest exposed wall faces south. The south-facing wall receives the afternoon sun in winter when it is welcome, while the small east and west walls reduce the intense heat of the morning and evening sun in summer.

For a building in the tropics, the north face is the coolest because it never receives direct sunlight, and the south face is the next best. The east face receives the morning sun which is mild, and the west face receives the hot afternoon sun which should be avoided as far as possible. Windows and verandahs should therefore be provided on the north and south sides, while the east and west walls should have fewer openings. Since the summer winds in India blow from the south-west, the main windows should face the south-west to catch the breeze, while in winter the winds from the north should be excluded by keeping the north side relatively closed.

The orientation must also satisfy the rules of maximum daylight, because a room lit from the south receives uniform light throughout the day. In the planning of the rooms, the living rooms, study and kitchen should be on the east and south to get light and warmth, while the bedrooms can be on the west and the store and staircase can occupy the north side. Modern practice also considers the solar angle at the winter solstice and summer solstice, so that verandahs and chajjas are designed to admit the low winter sun and shade the high summer sun. A building correctly oriented uses less energy for cooling and heating and is more comfortable throughout the year.

5. Quick Revision Tables

Table 1: Safe Bearing Capacity of Common Soils

Type of soil Safe bearing capacity (t/m2) Suitability
Hard rock 330 Excellent
Soft rock 45 Excellent
Gravel / shingle 40 Very good
Compact sand 30 Good
Loose sand 10 Requires compaction
Compact clay 10 Fair
Soft clay 5 Poor
Black cotton soil 2 Unsuitable, must be replaced

Table 2: Sun Effects and Orientation of Building Faces

Face of building Sun effect Recommended use
North No direct sun, coolest Stores, stairs, bathrooms
South Winter sun welcome, summer sun high Living rooms, large windows
East Mild morning sun Bedrooms, kitchen
West Hot afternoon sun, to be avoided Minimum openings, sun shades

6. Mind Map

flowchart TD
    A[Site Selection and Orientation] --> B[Site selection factors]
    A --> C[Soil investigation]
    A --> D[Orientation]
    B --> B1[Purpose of building]
    B --> B2[Size and shape of plot]
    B --> B3[Physical features]
    B --> B4[Soil and water table]
    B --> B5[Public services]
    C --> C1[Trial pits and boreholes]
    C --> C2[Bearing capacity]
    C --> C3[Water table]
    C --> C4[Black cotton soil]
    D --> D1[Longer axis east-west]
    D --> D2[South and north walls large]
    D --> D3[Windows south-west]
    D --> D4[East and west minimum openings]
    B1 --> B1a[Hospital, school, factory differ]
    C2 --> C2a[Rock 330 t/m2 best]
    C2 --> C2b[Black cotton 2 t/m2 worst]

7. Important Diagrams (SVG)

The following diagrams show the suitability of a site from the point of view of soil and water table, and the correct orientation of a building with respect to the sun.

Choice of Site - Soil and Water Table GOOD SITE Compact sand / gravel High bearing capacity Low water table Level, well drained Near road and services BAD SITE Black cotton soil Swelling and shrinking High water table Low-lying water logging Old well / made-up ground Test soil by trial pits and boreholes before design. Rock 330 t/m2, gravel 40, compact sand 30, black cotton 2 t/m2. Golden Rule Select a firm, well-drained site with low water table; bearing capacity decides the foundation.

Correct Orientation of a Building BUILDING Longer axis E-W North and south walls large WEST Hot afternoon sun Minimum openings EAST Mild morning sun Kitchen, bedrooms NORTH (coolest) SOUTH (winter sun) Summer winds from south-west, so place windows on the south-west face. South and north walls receive the most light; east and west should have chajjas. Golden Rule Keep the longer axis east-west so the largest walls face north and south for comfort.

8. Common Mistakes

  1. Many students think that the south face is always the hottest; actually in the northern hemisphere the west face receives the hottest afternoon sun, while the north face is the coolest.
  2. A common error is to recommend a low-lying plot because it is cheap; water logging after rain makes such a site unfit for construction.
  3. Some candidates forget that black cotton soil swells on wetting and shrinks on drying; it causes severe cracking and must never be used without treatment.
  4. Students frequently confuse safe bearing capacity values, especially mixing up gravel (40 t/m2) with loose sand (10 t/m2); the compactness decides the capacity.
  5. A frequent mistake is to ignore the purpose of the building while selecting the site; a hospital and a factory need completely different localities.
  6. Many candidates believe that the water table is unimportant once the foundation is deep; a rising water table causes dampness, basement flooding and uplift on the footing.
  7. Another common error is to orient the longer axis north-south; the correct practice in India is to place the longer axis east-west for maximum comfort.
  8. Students often forget that made-up or rubbish-filled ground must be excavated and replaced; building directly on old fill causes unequal settlement and cracks.

9. Exam Tips

  1. Memorise the safe bearing capacities in t/m2: rock 330, soft rock 45, gravel 40, compact sand 30, compact clay 10, black cotton 2.
  2. Remember that trial pits and boreholes are the field methods of soil investigation, while the bearing capacity is obtained by plate load test or standard penetration test.
  3. In an orientation question, first note the hemisphere; in India the longest wall should face south, and the north side is the coolest.
  4. Learn that a high water table raises the cost of dewatering and damp proofing; a good site has a low water table and firm subsoil.
  5. For the plan layout, place living rooms and study on the east-south side, bedrooms and verandahs appropriately, and stores and stairs on the north.
  6. Remember that the south-west face catches the summer monsoon breeze, so the main openings are provided there in Indian conditions.
  7. Recall that the minimum distance from a public road and the municipal set-backs are decided by local building byelaws, not by the designer alone.
  8. Practise one-line answers on which soil is best (rock) and which is worst (black cotton soil), because direct questions appear in CBT papers.

10. Conclusion

Site selection and building orientation form the foundation of the entire building construction process, because they decide the safety, comfort and economy of the structure before even the first drawing is made. In this chapter we have studied the factors that govern the choice of a site, namely the purpose of the building, the size and shape of the plot, the soil conditions, the water table and the availability of public services. We have learned the safe bearing capacities of common soils and understood why rock and compact gravel make the best foundations while black cotton soil must be avoided or treated. We have also studied the principles of orientation, which require the longer axis of the building to be placed east-west so that the largest walls face north and south, capturing the winter sun and the summer breeze while rejecting the heat of the east and west. A candidate who can quickly judge the merits of a site and correctly orient a building will answer a whole family of building construction questions with confidence, and this practical judgment is equally valuable in the field where the site engineer works.