15.3 Water Demand and Population Forecasting

Subject: Civil Engineering Chapter: Environmental Engineering Topic: 15.3 Water Demand and Population Forecasting

1. Introduction

Before a water supply scheme can be designed, the engineer must know two fundamental quantities: the population that the scheme is expected to serve at the end of its design period, and the quantity of water that this population will demand. Both quantities are uncertain because they refer to the future, and yet the whole economics of the scheme depends upon them. If the demand is underestimated, the scheme fails during its design life, and if it is overestimated, capital is wasted in constructing oversized mains and treatment units. For a civil engineering candidate, this chapter is extremely important because it is the richest source of numerical problems in environmental engineering, and questions on population forecasting methods and on the various demand rates appear in almost every competitive examination.

The population of a town does not remain constant; it grows at a rate that depends upon births, deaths, migration and the general development of the area. Because the exact future population cannot be known, engineers use statistical methods to forecast it, each method being based on a different assumption about how the population will grow. Similarly, the water demand is not a single fixed quantity, because the demand varies from hour to hour, from day to day and from season to season, and a distinction is made between the average demand, the maximum daily demand, the maximum hourly demand and the fire demand.

In this chapter we will study the various types of water demands, the factors that affect the rate of demand, the standard formulas used to estimate maximum demand, and the common methods of population forecasting with worked numerical examples for each method. The emphasis throughout is on examination-oriented knowledge, so the formulas, the standard values and the step-by-step method of calculation are presented in a form that can be applied directly to numerical problems.

2. Types of Water Demands

The total water demand of a town is made up of several components. The domestic demand is the water used in houses for drinking, cooking, bathing, washing and flushing, and it is the most important component; for Indian conditions the per capita domestic demand is taken as 135 litres per head per day in the design of a water supply scheme. The commercial and industrial demand is the water used by shops, offices, hotels, factories and institutions, and it varies from 20 to 45 percent of the domestic demand. The public demand includes the water used for parks, gardens, street washing, and public buildings, and it is taken as about 5 percent of the total. The fire demand is the water required for extinguishing fires, and because fire fighting requires a large discharge for a short time, the fire demand is added to the peak hourly demand. Finally, the losses and wastage in a water supply system, due to leakage from joints, valves and meters, are taken as about 15 to 20 percent of the total demand.

For the design of different components of the scheme, different rates of demand are used. The average daily demand is the total annual quantity of water supplied divided by the days in the year, and it is used for computing the water stored in the service reservoir and the design of the pumping units. The maximum daily demand, which is the demand on the day of maximum consumption, is used for the design of the treatment plant and the clear water reservoir, because on that day the plant must still deliver the full requirement. The maximum hourly demand is the peak demand within the hour of maximum consumption, and it is used for the design of the distribution system, the pipes and the service reservoirs, because the pipes must be able to pass the peak flow.

The maximum daily demand is usually taken as 1.8 times the average daily demand, and the maximum hourly demand is taken as 1.5 times the maximum daily demand, so that the maximum hourly demand is 1.8 x 1.5 = 2.7 times the average hourly demand. The fire demand is estimated by empirical formulas, of which the most commonly used is the formula of Kuichling, which states that the fire demand Q in litres per minute is given by Q = 3182 sqrt(P), where P is the population in thousands. A worked numerical example will make this clear. For a town with a population of 16,000, the population in thousands is 16, and the fire demand is Q = 3182 x sqrt(16) = 3182 x 4 = 12,728 litres per minute. Solution: The fire demand of the town according to the Kuichling formula is 12,728 litres per minute, which shows the very large discharge required for fire fighting.

3. Factors Affecting the Rate of Demand and Design Period

The rate of water demand is not a fixed quantity; it depends upon several factors that must be considered when fixing the design demand. The size of the community and its standard of living are the most important, because the per capita demand is larger in larger and more prosperous cities where more bathrooms, washing machines and gardens are present. The climatic conditions also matter, because more water is used for bathing and drinking in hot climates. The industrial development of the town increases the demand considerably, and the quality of the water supplied, the pressure in the mains, the metering of supply, the cost of water, and the policy of the water authority all influence the quantity actually consumed. In general, metered supplies reduce consumption while unmetered flat-rate supplies encourage wastage, and a high pressure increases the losses through leaks and misuse.

A related concept is the design period, which is the expected useful life of a component of the water supply scheme. The design period is fixed by taking into account the difficulty of extension, the useful life of the structure, and the cost of carrying the additional capacity. Common design periods are: dams and storage reservoirs 50 to 100 years, intake structures and conveyance mains 30 to 50 years, treatment plants and pumping stations 15 to 30 years, and distribution mains and service reservoirs 20 to 30 years. The water supply scheme is therefore designed for the maximum hourly demand of the population at the end of the design period, so that the component continues to work for the whole period without enlargement.

The design population is the population at the end of the design period, and it is obtained by forecasting the present population by the methods described in the next section. Because different components have different design periods, each component is designed for its own forecast population. For example, if a treatment plant has a design period of 20 years and the present population is 50,000 with an expected growth rate of 3 percent per year, the population after 20 years is computed by the growth formula and then multiplied by the per capita demand to obtain the design capacity. A worked numerical example will be shown under the forecasting methods.

4. Methods of Population Forecasting

Population forecasting is done by several methods, and each method gives a slightly different answer, so the engineer must judge which method is most suitable for the town. The arithmetic increase method assumes that the population increases by a constant amount every decade, so that the growth curve is a straight line; this method gives a low estimate and is used when growth is slow and steady. The formula is Pn = Po + n a, where Pn is the forecast population, Po is the present population, n is the number of decades and a is the average decadal increment. A worked example: if the population of a town was 40,000, 48,000 and 57,000 in three successive censuses, the decadal increments are 8,000 and 9,000, so the average a is 8,500. The forecast population after two decades is P2 = 57,000 + 2 x 8,500 = 74,000. Solution: The population after two decades by the arithmetic increase method is 74,000.

The geometric increase method assumes that the population grows at a constant percentage rate, which is more realistic for a developing town. The formula is Pn = Po (1 + r/100)^n, where r is the average percentage growth rate per decade. For the same town, the percentage increases are 48,000 / 40,000 - 1 = 0.20 and 57,000 / 48,000 - 1 = 0.1875, giving an average r of 19.375 percent. The forecast after two decades is P2 = 57,000 x (1.19375)^2 = 57,000 x 1.42504 = 81,227. Solution: The population after two decades by the geometric increase method is about 81,227, which is higher than the arithmetic estimate.

The incremental increase method combines the two ideas by adding the average increment and the average increment of the increments. The formula is Pn = Po + n a + n(n+1)/2 times the incremental increase. For the town above, a = 8,500 and the increments are 8,000 and 9,000, so the incremental increase is 9,000 - 8,000 = 1,000. The forecast after two decades is P2 = 57,000 + 2 x 8,500 + 2 x 3 / 2 x 1,000 = 57,000 + 17,000 + 3,000 = 77,000. Solution: The population after two decades by the incremental increase method is 77,000, which lies between the arithmetic and geometric estimates.

The logistic curve method assumes that population growth follows an S-shaped curve, rising slowly at first, rapidly in the middle and slowly again as the saturation limit is approached; this method gives good results for large cities. The decreasing rate of growth method assumes that the rate of increase decreases with time and is useful when the population is approaching saturation. In addition, the graphical extension method and the ratio method, which relates the population of the town to that of a larger area, are sometimes used. A worked numerical example for the per capita demand and total demand: if the forecast population at the end of the design period is 100,000 and the per capita demand is 200 litres per head per day, the average daily demand is 100,000 x 200 / 10,000,000 = 20 million litres per day, and the maximum daily demand at 1.8 times is 36 million litres per day. Solution: The average daily demand is 20 MLD and the maximum daily demand is 36 MLD, which would govern the design of the treatment plant.

5. Quick Revision Tables

Table 1: Types of Water Demand and Typical Values

Type of Demand Basis Typical Value
Domestic demand Per capita 135 L/head/day
Industrial demand Percent of domestic 20 to 45 percent
Public demand Percent of total About 5 percent
Fire demand Kuichling formula Q = 3182 sqrt(P) L/min
Losses and wastage Percent of total 15 to 20 percent
Maximum daily demand Times average 1.8 times average
Maximum hourly demand Times average 2.7 times average

Table 2: Population Forecasting Methods

Method Formula Assumption Typical Result
Arithmetic increase Pn = Po + n a Constant increment Low estimate
Geometric increase Pn = Po (1 + r/100)^n Constant percent growth High estimate
Incremental increase Pn = Po + n a + n(n+1)/2 x i Varying increments Intermediate
Logistic curve S-shaped growth Approaching saturation Good for large cities
Decreasing rate Decreasing percentage Near saturation For matured cities

6. Mind Map

flowchart TD
    A[Water Demand and Population Forecasting] --> B[Types of Water Demand]
    A --> C[Factors Affecting Demand]
    A --> D[Population Forecasting]
    A --> E[Design Period]
    B --> B1[Domestic 135 L/h/d]
    B --> B2[Industrial and commercial]
    B --> B3[Public demand]
    B --> B4[Fire demand]
    B --> B5[Losses 15 to 20 percent]
    B1 --> F[Average daily demand]
    B1 --> G[Maximum daily 1.8 times]
    B1 --> H[Maximum hourly 2.7 times]
    B4 --> I[Q = 3182 sqrt(P)]
    D --> D1[Arithmetic increase]
    D --> D2[Geometric increase]
    D --> D3[Incremental increase]
    D --> D4[Logistic curve]
    D --> D5[Decreasing rate]
    D1 --> J[Pn = Po + n a]
    D2 --> K[Pn = Po (1 + r/100)^n]
    D3 --> L[Add incremental increase]
    E --> M[Reservoirs 50 to 100 years]
    E --> N[Treatment plant 15 to 30 years]
    E --> O[Distribution 20 to 30 years]

7. Important Diagrams (SVG)

The following diagrams help us visualise the variation of water demand through the day and the growth curves of the population forecasting methods.

Variation of Water Demand During the Day 0 6 AM 12 noon 6 PM 12 midnight Time of day Average demand Peak hourly demand in evening Demand is minimum during night hours Golden Rule Maximum daily demand is 1.8 times average; maximum hourly demand is 2.7 times average.

Growth Curves of Population Forecasting Methods 0 1 decade 2 decades 3 decades 4 decades Time (years) Geometric (curved, rising fast) Incremental (between) Arithmetic (straight line) Logistic (S-shaped, approaches saturation) Arithmetic gives lowest, geometric gives high estimate Golden Rule Use arithmetic for steady towns, geometric for developing towns, logistic for large cities.

8. Common Mistakes

  1. Many students use the maximum hourly demand for the design of the treatment plant; the treatment plant is designed for the maximum daily demand, not the hourly peak.
  2. A frequent error is to apply the fire demand formula with population in persons instead of thousands; the population P in Q = 3182 sqrt(P) is in thousands.
  3. Some candidates forget to add the losses and wastage of 15 to 20 percent to the total demand while computing the design capacity.
  4. Students often use the arithmetic method where the geometric method is required; the geometric method is appropriate for a developing town with a growing percentage rate.
  5. A common mistake is to take the per capita demand of 135 L/head/day as the total demand; it is only the domestic component, and industrial, public and fire demands must be added.
  6. Many candidates forget the units of the final answer and leave the population or the demand without the correct units such as thousands or MLD.
  7. Students frequently average the decadal increments incorrectly by dividing by the wrong number of intervals; the average increment is the sum of increments divided by the number of increments.

9. Exam Tips

  1. Memorise the standard per capita domestic demand of 135 L/head/day and the factor of 1.8 and 2.7 for maximum daily and maximum hourly demand.
  2. Remember the Kuichling formula Q = 3182 sqrt(P) litres per minute with P in thousands; this is the most frequently asked fire demand formula.
  3. For forecasting numericals, first compute the average decadal increment or the average growth rate from the given census data, and then apply the appropriate formula.
  4. Learn the standard design periods: dams 50 to 100 years, intake and conveyance 30 to 50 years, treatment plants 15 to 30 years, and distribution mains 20 to 30 years.
  5. Remember that the distribution system and service reservoir are designed for the maximum hourly demand while the treatment plant is designed for the maximum daily demand.
  6. Practise the incremental increase method formula Pn = Po + n a + n(n+1)/2 x i, because it is the one candidates most often forget.
  7. Always state the final answer with the correct unit, whether it is MLD, litres per minute or population in thousands.

10. Conclusion

Water demand and population forecasting together determine the size of every component of a water supply scheme, and this chapter is therefore the numerical heart of environmental engineering. We have studied the components of water demand, the standard factors by which the maximum daily and maximum hourly demands are computed, the fire demand formulas, the factors that affect the rate of demand, and the standard design periods of the various components. We have also studied the five methods of population forecasting, namely arithmetic increase, geometric increase, incremental increase, logistic curve and decreasing rate of growth, and we have solved worked numerical examples for each important method. The quick revision tables give the standard values and formulas in a compact form, while the mind map and the diagrams show the demand variation and the growth curves visually. Mastery of these formulas is essential because the subsequent chapters on intake structures, treatment and distribution all use the design flows computed here. By memorising the standard values and practising the numericals, a candidate can secure the easiest and most reliable marks in the environmental engineering section of the examination.