Subject: Civil Engineering Chapter: Environmental Engineering Topic: 15.10 Water Supply Systems
A water supply system is the complete arrangement of structures, pipes and equipment by which water is collected from its source, treated to make it safe, and conveyed and distributed to the consumers of a community. Every city and town in the world depends upon such a system, and the environmental engineer is responsible for planning, designing and operating it so that water of adequate quantity and good quality is available at a reasonable cost, day and night, in every part of the town. For a civil engineering candidate, the study of water supply systems ties together all the earlier chapters, because the complete scheme comprises the source, the intake, the conveyance, the treatment, the storage and the distribution, and questions on the components, the classifications and the operation of the scheme appear in the final portion of the environmental engineering paper.
A water supply scheme is divided into distinct stages. The first stage is the collection of water from the source through the intake structure. The second stage is the conveyance of the raw water from the intake to the treatment plant through a system of conduits and pumping stations. The third stage is the treatment of the water to make it safe and pleasant. The fourth stage is the storage of the treated water in a clear water reservoir and the pumping of it into the distribution system. The fifth and final stage is the distribution of the water to the consumers through the network of mains, service reservoirs and house connections studied in the previous chapter.
In this chapter we will study the components and classifications of water supply systems, the conveyance of water by gravity and by pumping, the storage requirements and the overall operation of the scheme, with worked numerical examples on conduit capacity and pumping. The emphasis throughout is on examination-oriented knowledge, so the sequence of the components, the standard values and the numerical procedure are presented in a form that can be memorised easily and applied directly to the final examination questions.
The complete water supply system consists of the following components in their order: the source of water, which may be a river, reservoir or ground water; the intake structure, which withdraws the water from the source; the raw water conveyance, consisting of conduits or pipes with pumping stations; the treatment plant, in which the water is purified; the clear water reservoir, which stores the treated water; the pumping station, which pumps the water into the distribution system; the service reservoirs, which equalise the demand; and the distribution network, which carries the water to the consumers. A well-planned scheme provides for the future growth of the town by allowing for the forecast population and by making provision for the extension of every component.
Water supply systems are classified on the basis of the quantity of water supplied and the population served. A system supplying up to about 2000 litres per minute and serving a small village is called a small or individual water supply system, and it usually consists of a single well or a small spring supply with a small pump and a storage tank. A medium system supplies from 2000 to 10,000 litres per minute and serves a town or a district, while a large or major system supplies more than 10,000 litres per minute and serves a city, often drawing water from a large river or reservoir and treating it in a large plant. Systems may also be classified by the method of operation into continuous systems, which supply water throughout the day, and intermittent systems, which supply water only for fixed hours.
The choice between a continuous and an intermittent system is important. A continuous system is always preferable, because the water is available at all times, the pressure is maintained and the danger of contamination is less, since the pipes are always full of water under pressure. In an intermittent system, the pipes are empty for part of the day, and when the supply is resumed, the air and any contamination in the pipes may be drawn in, which is why intermittent systems are more liable to cause water-borne disease. For this reason the modern practice is to provide a continuous supply wherever possible, and the examination question on this distinction is a favourite.
The raw water is carried from the intake to the treatment plant and the treated water from the plant to the town by a system of conduits. Conduits are of two types: open channels and closed conduits or pipes. An open channel, such as a canal or an aqueduct, is used where the water flows by gravity and the quantity is large, and it is cheap but suffers losses by evaporation and seepage and may be contaminated along its length. A closed conduit, which is a pipe running full under pressure, is used where the water is to be pumped or where it must be protected from contamination; the closed conduit may be made of steel, cast iron, RCC or prestressed concrete, and it is the usual choice for treated water.
The conveyance is arranged either by gravity or by pumping, and this choice governs the cost and the operation of the scheme. In a gravity system, the source and the treatment plant are located at a higher elevation than the town, so that the water flows naturally without any pumping; this is the cheapest arrangement, because the only running cost is that of the treatment plant itself, and it is used wherever the topography permits. In a pumping system, the water has to be pumped from a lower level to a higher level through a pumping station, and the running cost is high because of the continuous consumption of power. Many schemes use a combination, with gravity for part of the way and pumping for the rest.
A worked numerical example will illustrate the design of a rising main. A pumping station is to convey 1200 litres per minute through a rising main of 200 mm diameter. The discharge is 1200 / 60 = 20 litres per second = 0.02 m3/s, and the area of the 200 mm pipe is pi x 0.2^2 / 4 = 0.0314 m2. The velocity of flow is V = Q / A = 0.02 / 0.0314 = 0.637 m/s. If the static head is 30 metres and the friction loss at this discharge is 5 metres, the total head against which the pump works is 35 metres. The power required, with water unit weight 9810 N/m3, is P = w Q H / efficiency = 9810 x 0.02 x 35 / 0.7 = 6867 / 0.7 = 9810 W, or about 9.8 kW, taking the pump efficiency as 70 percent. Solution: The pump must develop a power of about 9.8 kilowatts to raise 1200 litres per minute through a total head of 35 metres at 70 percent efficiency.
A second numerical example shows the computation for a gravity main. If a gravity conduit of 400 mm diameter carries water at a velocity of 1.0 m/s, the discharge is Q = A V = pi x 0.4^2 / 4 x 1.0 = 0.1256 m3/s, or 125.6 litres per second. In a day of 24 hours, this conduit conveys 0.1256 x 24 x 3600 = 10,852 cubic metres, or about 10.85 million litres per day. Solution: The gravity conduit of 400 mm diameter conveys about 10.85 MLD at a velocity of 1 metre per second, which would satisfy the demand of a town of roughly 50,000 people at 200 litres per head per day.
Storage is provided in a water supply system at two points: the clear water reservoir after the treatment plant, and the service reservoirs in the distribution system. The clear water reservoir stores the treated water before it is pumped to the town, and its capacity is determined from the pumping schedule and the demand curve. The service reservoirs equalise the hourly variation of demand, store water for emergencies and fire fighting, and maintain the pressure in the distribution mains. The total storage of the service reservoirs is often taken as about 30 percent of the maximum daily demand, of which about 20 percent is the equalising storage and the remainder is for fire and emergencies.
The operation of a complete water supply scheme is a continuous cycle. The intake draws the raw water, which is carried to the treatment plant; there the water is screened, coagulated, settled, filtered and disinfected, and the treated water is stored in the clear water reservoir. From the clear water reservoir the water is pumped to the service reservoirs at a fairly constant rate throughout the day, and the service reservoirs release the water to the distribution mains according to the hourly demand. Because the demand varies while the pumping is constant, the service reservoir fills during the low-demand night hours and empties during the peak morning and evening hours.
A worked numerical example will illustrate the computation of the fire storage. If a town of 20,000 people requires fire water according to the Kuichling formula Q = 3182 sqrt(P) litres per minute, with the population in thousands, then Q = 3182 x sqrt(20) = 3182 x 4.472 = 14,230 litres per minute. If the fire is to be fought for 4 hours, the fire storage required is 14,230 x 60 x 4 / 1000 = 3415 cubic metres. Solution: About 3415 cubic metres of fire storage are required in the service reservoir, which must be added to the equalising storage to get the total reservoir capacity.
A final numerical example checks the adequacy of the storage. If the total demand of a town is 20 MLD and the service reservoir is to hold 30 percent of the maximum daily demand, the maximum daily demand at 1.8 times the average is 36 MLD, and the reservoir capacity is 0.30 x 36 = 10.8 million litres, or 10,800 cubic metres. Solution: The service reservoir should have a capacity of about 10,800 cubic metres to provide the required equalising, fire and emergency storage for the town.
| Stage | Component | Function |
|---|---|---|
| 1 | Source | River, reservoir or ground water |
| 2 | Intake | Withdraw water from source |
| 3 | Conveyance | Carry raw water to plant |
| 4 | Treatment | Purify the water |
| 5 | Clear water reservoir | Store treated water |
| 6 | Pumping station | Pump to distribution |
| 7 | Service reservoir | Equalise demand and pressure |
| 8 | Distribution mains | Carry water to consumers |
| Item | Value |
|---|---|
| Small system supply | Up to 2000 L/min |
| Medium system supply | 2000 to 10,000 L/min |
| Large system supply | Above 10,000 L/min |
| Service reservoir capacity | About 30 percent of max daily demand |
| Equalising storage | About 20 percent of max daily demand |
| Fire storage basis | Kuichling formula, 4 hours of fire |
| Preferred operation | Continuous supply |
flowchart TD
A[Water Supply Systems] --> B[Components]
A --> C[Classification]
A --> D[Conveyance]
A --> E[Storage]
B --> B1[Source]
B --> B2[Intake]
B --> B3[Conveyance]
B --> B4[Treatment]
B --> B5[Clear water reservoir]
B --> B6[Pumping station]
B --> B7[Service reservoir]
B --> B8[Distribution mains]
C --> C1[Small up to 2000 L/min]
C --> C2[Medium 2000 to 10,000]
C --> C3[Large above 10,000]
C --> C4[Continuous or intermittent]
D --> D1[Gravity system]
D --> D2[Pumping system]
D1 --> F[Cheapest running cost]
D2 --> G[Power for pumping]
E --> E1[Clear water reservoir]
E --> E2[Service reservoir 30 percent]
E2 --> H[Equalising 20 percent]
E2 --> I[Fire and emergency]
C4 --> J[Continuous preferred]
The following diagrams help us visualise the complete layout of a water supply system and the pumping and storage arrangements.
The water supply system is the complete integrated scheme by which a community obtains its water, and it brings together every topic studied in the environmental engineering syllabus. In this chapter we have studied the eight components of the system from the source to the distribution mains, the classification of the systems by their discharge, the difference between the gravity and the pumping methods of conveyance, and the storage provided in the clear water reservoir and the service reservoirs. We have solved worked numerical examples on the rising main, the pump power, the gravity conduit capacity, the fire storage and the reservoir capacity. The quick revision tables summarise the components and the classification, while the diagrams show the complete layout of the system and the two methods of conveyance. With this chapter the study of water supply engineering is complete, and the candidate now has the full picture from the selection of the source to the tap of the consumer. By memorising the sequence of the components, the standard values and the numerical procedures, a candidate can answer the water-supply-system questions with confidence and secure reliable marks in the final portion of the environmental engineering section of the examination.