23.1 Types of Estimates

Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.1 Types of Estimates

1. Introduction

An estimate is a carefully computed statement of the probable cost of a proposed engineering work, prepared before the actual construction begins. In civil engineering, no project, whether it is a small school building or a large irrigation dam, can be sanctioned or financed without a realistic estimate of its cost, because the estimate determines the budget that must be allocated, the materials that must be procured and the period over which funds will be released. For a candidate preparing for SSC JE, RRB JE and state AE/JE examinations, the topic of estimates is a rich source of one-mark questions, because it tests whether the aspirant knows which type of estimate is used at which stage of a project, the differences between accurate and approximate methods, and the standard rules used to arrive at quantities.

The purpose of an estimate goes far beyond merely fixing a price. An estimate is used to obtain administrative approval from the sanctioning authority, to invite tenders from contractors, to arrange finance and loans, to control expenditure during construction, and to compare the cost of different schemes so that the most economical one is adopted. Since the whole financial planning of a project is based on the estimate, an estimate that is too low leads to shortage of funds and stoppage of work, while an estimate that is too high may cause the project to be rejected as uneconomical. A good estimator therefore combines technical knowledge with practical judgment about rates, wastage and site conditions.

In this chapter we will study the classification of estimates into detailed estimates and approximate or preliminary estimates, the various sub-types under each class such as revised, supplementary, annual repair and extension estimates, and the principal methods of preparing approximate estimates, namely the plinth area method, the cubical contents method, the unit base method and the bay method. We will also work out a numerical example of the plinth area method, which is the most frequently examined approximate method, so that the concepts are converted into problem-solving skill.

2. Detailed and Approximate Estimates

Estimates are broadly divided into two main classes on the basis of the accuracy desired. The detailed estimate is the most accurate form of estimate, prepared by working out the actual quantities of every item of work from the detailed drawings and specifications, and then multiplying each quantity by its rate. The detailed estimate includes the quantity of earthwork, concrete, brickwork, steel, flooring, plastering, painting and every other item, so that the sum of all items, together with contingencies, work charge establishment and other charges, gives the total cost of the work. The detailed estimate forms the basis for inviting tenders and is prepared only when the drawings and specifications are complete.

The approximate estimate, also called the preliminary or abstract estimate, is a rough calculation made in the early stage when only outline requirements are known, to obtain an idea of the probable cost so that the project can be judged for feasibility and funds can be earmarked. Approximate estimates are prepared using past experience and average rates, and are accurate to within about ten to fifteen percent. They are used for preparing feasibility reports, for obtaining administrative approval in principle, and for deciding whether the project should be examined further at all. Approximate estimates are always cheaper and quicker to prepare than detailed estimates, but they can never be used for inviting tenders or for controlling expenditure.

Under the broad class of detailed estimates, we meet several special types. A revised estimate is prepared when the sanctioned estimate is exceeded by more than five percent, due to changes in rates, quantities or design after sanction. A supplementary estimate is prepared when new or additional work is added after the original estimate has been sanctioned. An annual repair or maintenance estimate is prepared every year for the upkeep of a building, covering small repairs to walls, roofs, floors and services. An extension estimate is prepared for the cost of adding new rooms or floors to an existing building, and a special repair estimate covers repairs to an old or damaged structure whose condition has become unsafe.

3. Methods of Approximate Estimates

Several methods are available for preparing an approximate estimate, and the choice of method depends on the type of structure and the amount of information available. The plinth area method is the most common and is based on the plinth area of the building, which is the covered area measured at the floor level, including the thickness of external walls but excluding cantilever projections. The cost is obtained by multiplying the plinth area by the plinth area rate, which is the average cost per square metre of similar buildings in the locality. The plinth area rate includes the cost of the building with its services but excludes the cost of land, and for a multi-storey building the plinth area of each floor is used.

The cubical contents method gives a slightly more accurate result by multiplying the cubic content of the building, which is the plinth area multiplied by the height of the building measured from the foundation to the roof, by the rate per cubic metre. This method is useful where the height of the building varies, but it has the disadvantage that the volume of the walls below plinth and the roof thickness are sometimes not allowed for correctly. The unit base method is used for certain structures whose cost can be expressed per unit of capacity or output, such as cost per running metre for roads, railways and pipelines, cost per room or per bed for hospitals, and cost per student for schools. The bay method is used for buildings such as godowns, factories and sheds that consist of a number of similar bays, where the cost of one typical bay is worked out and multiplied by the total number of bays.

For special structures, other methods are used. The cost per litre or per gallon method is used for overhead water tanks and reservoirs, the cost per hectare is used for agricultural or landscaping works, and the cost per kilometre is used for roads and canals. In every approximate method, the rates are taken from the prevailing market schedule or from the cost of recently completed similar works, and suitable allowances are added for services such as water supply, electrification and sanitation. The plinth area rate is adjusted for the difference in plinth heights, finishing, locality and the number of floors, so that the resulting figure is realistic.

4. Worked Numerical Examples

Example 1: A residential building has a plinth area of 180 square metres and the plinth area rate for similar buildings in the locality is Rs. 12,500 per square metre. Determine the approximate cost of the building.

Solution: Approximate cost = plinth area x plinth area rate = 180 x 12,500 = Rs. 22,50,000. The approximate cost of the building is Rs. 22,50,000.

Example 2: A two-storey building has a plinth area of 120 square metres per floor. The plinth area rate is Rs. 10,000 per square metre for the ground floor and Rs. 9,500 per square metre for the first floor. Estimate the total cost.

Solution: Total plinth area = 120 + 120 = 240 square metres. Cost of ground floor = 120 x 10,000 = Rs. 12,00,000. Cost of first floor = 120 x 9,500 = Rs. 11,40,000. Total approximate cost = 12,00,000 + 11,40,000 = Rs. 23,40,000.

Example 3: A godown has plinth area of 200 square metres and an average height of 6 metres. If the rate per cubic metre is Rs. 4,500, find the approximate cost by the cubical contents method.

Solution: Cubical contents = plinth area x height = 200 x 6 = 1200 cubic metres. Approximate cost = 1200 x 4,500 = Rs. 54,00,000. The approximate cost of the godown is Rs. 54,00,000.

Example 4: A hospital building with 150 beds has an estimated cost per bed of Rs. 2,00,000. Find the approximate cost of the hospital.

Solution: Approximate cost = number of beds x cost per bed = 150 x 2,00,000 = Rs. 3,00,00,000. The approximate cost of the hospital is Rs. 3 crores.

5. Quick Revision Tables

Table 1: Types of Estimates and Their Use

Type of estimate Basis of preparation Stage of use
Approximate estimate Plinth area, cubical contents, unit base Early planning and feasibility
Detailed estimate Actual quantities from drawings Inviting tenders, financial sanction
Revised estimate Original estimate exceeded by more than 5 percent After sanction, due to rate/quantity change
Supplementary estimate Additional work added later During construction
Annual repair estimate Routine maintenance items Every year for upkeep
Extension estimate Cost of new rooms or floors When building is extended

Table 2: Approximate Estimate Methods

Method Basis Best suited for
Plinth area method Plinth area x rate per m2 Residential and public buildings
Cubical contents method Volume x rate per m3 Buildings with varying height
Unit base method Cost per unit of capacity Roads, pipelines, hospitals
Bay method Cost per bay x number of bays Godowns, factories, sheds
Cost per litre method Capacity x rate per litre Water tanks, reservoirs

6. Mind Map

flowchart TD
    A[Types of Estimates] --> B[Detailed Estimate]
    A --> C[Approximate Estimate]
    B --> B1[Revised estimate]
    B --> B2[Supplementary estimate]
    B --> B3[Annual repair estimate]
    B --> B4[Extension estimate]
    C --> C1[Plinth area method]
    C --> C2[Cubical contents method]
    C --> C3[Unit base method]
    C --> C4[Bay method]
    C1 --> C1a[Area x rate per m2]
    C2 --> C2a[Volume x rate per m3]
    C3 --> C3a[Per bed, per km, per room]
    C4 --> C4a[One bay cost x bays]
    B1 --> B1a[When cost exceeds by 5 percent]
    B2 --> B2a[For additional work]

7. Important Diagrams (SVG)

The following diagrams show how estimates are classified and how the plinth area of a building is measured.

Classification of Estimates ESTIMATES Detailed Estimate Approximate Estimate Revised Supplementary Annual Repair Extension Plinth Area Cubical Contents Unit Base Golden Rule Detailed estimates invite tenders; approximate estimates only judge feasibility early.

Measurement of Plinth Area ROOM 1 Floor area included Wall thickness Wall thickness Plinth area = area at floor level including external wall thickness. Balconies and cantilever projections are excluded from plinth area. Mezzanine floor area, porches and verandahs are included as per rules. Golden Rule Cost by plinth area method = plinth area in m2 x plinth area rate in Rs/m2.

8. Common Mistakes

  1. Many students think a revised estimate is prepared for additional new work; actually a supplementary estimate serves that purpose, while the revised estimate replaces an old estimate whose cost has risen.
  2. A common error is to include the cost of land in the plinth area rate; the plinth area rate covers only the building construction cost, and the cost of land is added separately.
  3. Candidates frequently confuse the bay method with the unit base method; the bay method counts similar bays while the unit base method uses cost per bed, per room or per kilometre.
  4. Some students believe that the approximate estimate can be used to invite tenders; in practice tenders can only be called on the basis of the detailed estimate.
  5. A frequent mistake is to ignore the external wall thickness while computing plinth area, which underestimates the covered area and hence the cost.
  6. Many candidates forget that the revised estimate becomes necessary only when the sanctioned estimate is exceeded by more than five percent, and a small excess below this does not require a revised estimate.
  7. In the cubical contents method, students often take only the height of the rooms and forget the height from foundation to roof, which is the correct height for the cubical contents.
  8. Candidates often forget that cantilever projections and balconies are excluded from plinth area, and wrongly add them while measuring the covered area.

9. Exam Tips

  1. Memorise the classification: detailed estimate for tenders and finance, approximate estimate for feasibility and administrative sanction in principle.
  2. Remember the key values, such as the revised estimate rule of five percent excess, because these figures are directly asked in one-mark questions.
  3. For the plinth area method, practise the direct formula: cost = plinth area x plinth area rate, and remember the plinth area rate excludes the cost of land.
  4. Learn which method suits which structure: bay method for godowns and factories, unit base method for roads and hospitals, cubical contents method for buildings with varying height.
  5. Remember that the cubical contents method is considered slightly more accurate than the plinth area method because it accounts for the height of the building.
  6. Keep in mind that the abstract estimate is another name for the approximate estimate and is prepared from rough sketch without detailed quantities.
  7. Note the distinction that the annual repair estimate is prepared every year, while a special repair estimate is prepared for an old structure that has become unsafe.
  8. Practise short numericals on plinth area and cubical contents so that the multiplication and rate application become automatic in the examination.

10. Conclusion

The types of estimates form the starting point of the entire discipline of estimation and costing, because every financial decision about a project flows from the estimate prepared at its beginning. In this chapter we have studied the two broad classes of estimates, the detailed estimate which is accurate enough to invite tenders and obtain sanction, and the approximate estimate which gives a quick preliminary idea of the cost. We have examined the special types such as the revised estimate, the supplementary estimate, the annual repair estimate and the extension estimate, each with its own stage and purpose, and we have studied the principal approximate methods, namely the plinth area method, the cubical contents method, the unit base method and the bay method, along with worked numerical examples. The distinction between these methods and the correct application of the plinth area rule are repeatedly tested in competitive examinations, and a candidate who has mastered the classification and the methods can answer a large family of questions on this topic with speed and accuracy. This foundation in estimating prepares the student for the later topics of quantity estimation, rate analysis and contract management, where the numbers introduced here are refined into the exact quantities and rates that govern real construction projects.