🏗️ Civil Engineering

23.2 Detailed Estimation

Start MCQ Practice →

23.2 Detailed Estimation

Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.2 Detailed Estimation

1. Introduction

A detailed estimate is the complete and accurate statement of the cost of a project, prepared by working out the exact quantity of every item of work from the detailed drawings and specifications and multiplying each quantity by its market rate. Unlike the approximate estimate, which gives a quick rough figure, the detailed estimate requires every dimension to be measured from the plans and sections, every item to be listed separately, and every rate to be justified. For the engineer, the detailed estimate is the document that receives administrative and technical sanction, forms the basis for inviting tenders and controls the expenditure of the project during execution, and for the examination candidate it is the source of a large number of conceptual questions on methods of measurement and the arrangement of the estimate.

A detailed estimate is divided into three distinct parts: the measurements, the abstract and the lead statement. In the measurement part, each item is written in the measurement sheet with its length, breadth and height or thickness, and the quantity is calculated in the units in which the item is paid for. In the abstract part, the quantities of all items are collected, multiplied by their rates and totalled to obtain the cost of the work. The lead statement records the distances over which materials have to be transported from the source to the site, because the cost of carriage forms a separate item in the estimate. These three parts together give the estimator complete control over both quantities and rates.

In this chapter we will study the essentials of a good estimate, the rules for taking out measurements, the standard units in which common items are measured, the items that make up a building estimate and the manner of filling up the measurement and abstract sheets. We will also solve a numerical example of computing the quantities of excavation, concrete, brickwork and plastering from a simple room, so that the candidate sees exactly how a measurement sheet is prepared and how the abstract is built from it.

2. Essentials and Steps of Detailed Estimation

A good detailed estimate must satisfy certain essentials. It must be based on complete, accurate and up-to-date drawings, including the plan, sections, elevations and details of the work. It must be accompanied by a specification for every item, because the rate of an item depends on the quality of the material and the method of construction. It must be prepared in a systematic form so that every quantity can be checked easily, and it must be realistic, neither too low nor too high, so that the sanctioned amount is sufficient to complete the work. Finally, the estimate must be within the competence of a trained estimator, who should be familiar with local rates of material and labour and with the wastage factors that are allowed for in different items.

The preparation of a detailed estimate proceeds through definite steps. First, the complete set of drawings is studied and the area of each item is visualised. Second, the schedule of quantities, also called the bill of quantities, is prepared by measuring the lengths, breadths and heights of all items from the drawings and entering them in the measurement sheet. Third, the quantities of all items are totalled in the abstract sheet. Fourth, each quantity is multiplied by its rate, taken from the current rate schedule or market rates, and the cost of each item is obtained. Fifth, the total of all items is added to the contingencies, work-charge establishment, tools and plants, and the cost of supervision to arrive at the final cost of the work.

The quantity of an item is obtained by the fundamental relation that volume equals length multiplied by breadth multiplied by height, and area equals length multiplied by breadth. For items measured by volume, such as earthwork, concrete and brickwork, three dimensions are used, while for items measured by area, such as plastering, flooring and roofing, two dimensions are used, and for items measured by length, such as handrails, copings and skirting, only one dimension is used. The accuracy of the whole estimate depends on these measurements, and the estimator must therefore check every dimension against the drawing and clearly note the deductions to be made for openings, doors and windows.

3. Units of Measurement and Modes of Measurement

In detailed estimation, every item is measured and paid in a standard unit, and the rules laid down in the specifications of the Public Works Department are followed. Items like earthwork, concrete, brickwork, masonry, plastering in thick form, and excavation are measured in cubic metres, because they are three-dimensional. Items like flooring, plastering, pointing, roofing, whitewashing, distempering, painting and damp proofing are measured in square metres, because they are two-dimensional. Items like steel reinforcement, pipes, wiring, handrails and skirting are measured in running metres, while items such as doors, windows, ventilators, cupboards and fans are counted in numbers or numbers with the size stated.

Certain items have special modes of measurement that are frequently tested. Steel reinforcement is measured by weight in quintals or kilograms, and the weight is computed from the length of the bars using the formula that the weight of a bar in kilograms equals the diameter squared in millimetres divided by 162, multiplied by the length in metres. This standard relation comes from the fact that one square millimetre area of steel weighs about 7.85 grams per metre per square millimetre, giving the factor d squared divided by 162. Similarly, the number of bricks per cubic metre of brickwork is roughly 500, allowing for the mortar joints, and the number of cement bags per cubic metre of concrete is obtained by dividing the cement required in kilograms by 50, the weight of one bag.

While taking out the quantities, the estimator must deduct the openings from masonry and plastering, but add back the sides of openings for jambs and reveals, as specified in the relevant rules. Painting and whitewashing are measured over the actual surface, and deductions are not made for small openings but are made for large openings. The estimate is finally summarised in the abstract form, where the cost of each item is entered against its quantity, and the sum total is rounded off and presented with contingencies at about three to five percent and work-charge establishment at about one and a half to two percent of the total cost.

4. Worked Numerical Example on Building Items

Example: A room has an internal size of 5 metres by 4 metres, with walls 0.3 metres thick. Compute the quantity of earthwork in excavation for the foundation if the trench is dug all round, 0.5 metres wide and 1 metre deep, and find the quantity of brickwork in the foundation and superstructure if the plinth wall is 0.5 metres high and the superstructure wall is 3 metres high above plinth, both of 0.3 metre thickness.

Solution: Centre to centre length = 5 + 0.3 = 5.3 m, centre to centre breadth = 4 + 0.3 = 4.3 m. Perimeter of trench centre line = 2 x (5.3 + 4.3) = 2 x 9.6 = 19.2 m. Earthwork in excavation = perimeter x width x depth = 19.2 x 0.5 x 1.0 = 9.6 cubic metres.

Brickwork in foundation and plinth: the volume of brickwork is obtained by the perimeter multiplied by the wall thickness multiplied by the height. Total height of brickwork = 0.5 + 3.0 = 3.5 m. Quantity of brickwork = 19.2 x 0.3 x 3.5 = 20.16 cubic metres.

Example 2: A wall 20 metres long, 3 metres high and 0.3 metres thick has a door opening of 2.1 metres by 1.2 metres. Find the net quantity of brickwork and the quantity of plastering on one face of the wall, deducting the opening.

Solution: Gross brickwork = 20 x 3 x 0.3 = 18 cubic metres. Door opening volume = 2.1 x 1.2 x 0.3 = 0.756 cubic metres. Net brickwork = 18 - 0.756 = 17.244 cubic metres. Plastering area on one face = 20 x 3 - 2.1 x 1.2 = 60 - 2.52 = 57.48 square metres.

Example 3: Find the weight of steel required for a beam having four bars of 12 millimetre diameter, each 6 metres long, using the formula weight = d squared divided by 162.

Solution: Weight per metre of 12 mm bar = 12 x 12 / 162 = 144 / 162 = 0.889 kg per metre. Length of all four bars = 4 x 6 = 24 metres. Total weight = 24 x 0.889 = 21.33 kilograms. The steel required is about 21.33 kilograms.

Example 4: Estimate the number of bricks required for 10 cubic metres of brickwork, assuming 500 bricks per cubic metre and adding 5 percent for wastage.

Solution: Bricks required = 10 x 500 = 5000 bricks. Adding 5 percent wastage = 5000 x 0.05 = 250 bricks. Total bricks required = 5000 + 250 = 5250 bricks.

5. Quick Revision Tables

Table 1: Units of Measurement of Common Items

Item Unit of measurement
Earthwork in excavation Cubic metre
Concrete Cubic metre
Brickwork in foundation and superstructure Cubic metre
Steel reinforcement Kilogram / quintal
Plastering, pointing, flooring, painting Square metre
Pipes, wiring, handrails, skirting Running metre
Doors, windows, ventilators, fans Number
Damp proof course Square metre

Table 2: Key Conversion Factors

Item Standard value
Bricks per cubic metre of brickwork About 500
Cement bag weight 50 kg
Weight of 12 mm steel bar 0.889 kg per metre
Weight formula d x d / 162 kg per metre
Contingencies allowance 3 to 5 percent
Work-charge establishment 1.5 to 2 percent

6. Mind Map

flowchart TD
    A[Detailed Estimation] --> B[Essentials]
    A --> C[Measurement Sheet]
    A --> D[Abstract Sheet]
    A --> E[Lead Statement]
    B --> B1[Complete drawings]
    B --> B2[Specifications]
    B --> B3[Realistic rates]
    C --> C1[Length x breadth x height]
    C --> C2[Deductions for openings]
    D --> D1[Quantity x rate]
    D --> D2[Add contingencies]
    E --> E1[Distance of material travel]
    C1 --> C1a[Cubic metre items]
    C1 --> C1b[Square metre items]
    C1 --> C1c[Running metre items]
    C1 --> C1d[Number items]

7. Important Diagrams (SVG)

The following diagrams show the arrangement of a building estimate and the measurement of quantities from a simple room plan.

Parts of a Detailed Estimate DETAILED ESTIMATE Measurement Sheet L, B, H of every item Abstract Sheet Quantity x rate = cost Lead Statement Transport distances Total cost of items, plus contingencies and work-charge establishment, gives the final sanctioned cost of the project. Golden Rule Measure in the units of payment: m3 for solids, m2 for surfaces, metres for lines.

Measurement from Room Plan for Brickwork ROOM 5m x 4m Internal size Perimeter of centre line = 2(L + B) centre to centre Centre line L = 5 + 0.3 = 5.3 m, B = 4 + 0.3 = 4.3 m Perimeter = 2 x 9.6 = 19.2 m, brickwork = 19.2 x 0.3 x height Golden Rule For wall quantities use centre line perimeter, not internal dimensions.

8. Common Mistakes

  1. Many students take the internal dimensions for wall quantities; the correct practice is to measure along the centre line of the walls.
  2. A common error is to forget the deduction for door and window openings while computing brickwork and plastering quantities.
  3. Candidates frequently use the formula d squared divided by 162 for the wrong diameter, mixing up 12 mm and 16 mm bars, which changes the weight completely.
  4. Some students measure plastering in cubic metres; plastering is a surface finish and is always measured in square metres.
  5. A frequent mistake is to forget that steel reinforcement is paid by weight in kilograms or quintals, not by running metre.
  6. Many candidates forget to add contingencies and work-charge establishment in the abstract, leaving the estimate short of the actual sanctioned cost.
  7. In the measurement sheet, students often fail to state whether the dimensions are taken in metres or centimetres, causing an error of a hundred times in the quantity.
  8. Candidates often forget the wastage allowance for bricks and cement, so the quantity of materials purchased is insufficient for the actual work.

9. Exam Tips

  1. Remember the golden rule that volume items are measured in cubic metres, surface items in square metres, and linear items in running metres.
  2. Learn the standard values by heart: 500 bricks per cubic metre, 50 kg per bag of cement, and weight of steel equal to d squared divided by 162 kilograms per metre.
  3. For brickwork questions, always use the centre line perimeter computed from the centre to centre dimensions of the room.
  4. Practise the deduction rule: openings are deducted from masonry and plastering, and the sides of openings are added back where specified.
  5. Remember the allowances: contingencies 3 to 5 percent and work-charge establishment 1.5 to 2 percent of the total cost.
  6. In the abstract sheet, quantities are collected from the measurement sheet and multiplied by rates taken from the current rate schedule.
  7. Note that the detailed estimate is the only estimate that can be used for inviting tenders and for obtaining financial sanction of the project.
  8. Always state units clearly in the measurement sheet, because a mistake between metres and centimetres changes the quantity by a factor of one hundred.

10. Conclusion

Detailed estimation converts the drawings of a project into a precise financial statement, because it is here that every length, breadth and height is measured, every quantity is computed and every rate is applied. In this chapter we have studied the essentials of a good estimate, namely complete drawings, clear specifications and realistic rates, and the three parts of the estimate, namely the measurement sheet, the abstract sheet and the lead statement. We have learned the units in which common items are measured, the standard conversion factors such as 500 bricks per cubic metre and the weight formula for steel, and we have solved numerical examples on excavation, brickwork, plastering and steel weight. The skill of taking out quantities accurately is the heart of the estimator's work, and it is also the basis of the next topic of quantity estimation, where the measurement of individual items such as earthwork, concrete and masonry is taken up in full detail. A candidate who masters the measurement sheet and the abstract sheet will find both the concept questions and the numerical questions of estimation easy to handle in the examination.