Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.2 Detailed Estimation
A detailed estimate is the complete and accurate statement of the cost of a project, prepared by working out the exact quantity of every item of work from the detailed drawings and specifications and multiplying each quantity by its market rate. Unlike the approximate estimate, which gives a quick rough figure, the detailed estimate requires every dimension to be measured from the plans and sections, every item to be listed separately, and every rate to be justified. For the engineer, the detailed estimate is the document that receives administrative and technical sanction, forms the basis for inviting tenders and controls the expenditure of the project during execution, and for the examination candidate it is the source of a large number of conceptual questions on methods of measurement and the arrangement of the estimate.
A detailed estimate is divided into three distinct parts: the measurements, the abstract and the lead statement. In the measurement part, each item is written in the measurement sheet with its length, breadth and height or thickness, and the quantity is calculated in the units in which the item is paid for. In the abstract part, the quantities of all items are collected, multiplied by their rates and totalled to obtain the cost of the work. The lead statement records the distances over which materials have to be transported from the source to the site, because the cost of carriage forms a separate item in the estimate. These three parts together give the estimator complete control over both quantities and rates.
In this chapter we will study the essentials of a good estimate, the rules for taking out measurements, the standard units in which common items are measured, the items that make up a building estimate and the manner of filling up the measurement and abstract sheets. We will also solve a numerical example of computing the quantities of excavation, concrete, brickwork and plastering from a simple room, so that the candidate sees exactly how a measurement sheet is prepared and how the abstract is built from it.
A good detailed estimate must satisfy certain essentials. It must be based on complete, accurate and up-to-date drawings, including the plan, sections, elevations and details of the work. It must be accompanied by a specification for every item, because the rate of an item depends on the quality of the material and the method of construction. It must be prepared in a systematic form so that every quantity can be checked easily, and it must be realistic, neither too low nor too high, so that the sanctioned amount is sufficient to complete the work. Finally, the estimate must be within the competence of a trained estimator, who should be familiar with local rates of material and labour and with the wastage factors that are allowed for in different items.
The preparation of a detailed estimate proceeds through definite steps. First, the complete set of drawings is studied and the area of each item is visualised. Second, the schedule of quantities, also called the bill of quantities, is prepared by measuring the lengths, breadths and heights of all items from the drawings and entering them in the measurement sheet. Third, the quantities of all items are totalled in the abstract sheet. Fourth, each quantity is multiplied by its rate, taken from the current rate schedule or market rates, and the cost of each item is obtained. Fifth, the total of all items is added to the contingencies, work-charge establishment, tools and plants, and the cost of supervision to arrive at the final cost of the work.
The quantity of an item is obtained by the fundamental relation that volume equals length multiplied by breadth multiplied by height, and area equals length multiplied by breadth. For items measured by volume, such as earthwork, concrete and brickwork, three dimensions are used, while for items measured by area, such as plastering, flooring and roofing, two dimensions are used, and for items measured by length, such as handrails, copings and skirting, only one dimension is used. The accuracy of the whole estimate depends on these measurements, and the estimator must therefore check every dimension against the drawing and clearly note the deductions to be made for openings, doors and windows.
In detailed estimation, every item is measured and paid in a standard unit, and the rules laid down in the specifications of the Public Works Department are followed. Items like earthwork, concrete, brickwork, masonry, plastering in thick form, and excavation are measured in cubic metres, because they are three-dimensional. Items like flooring, plastering, pointing, roofing, whitewashing, distempering, painting and damp proofing are measured in square metres, because they are two-dimensional. Items like steel reinforcement, pipes, wiring, handrails and skirting are measured in running metres, while items such as doors, windows, ventilators, cupboards and fans are counted in numbers or numbers with the size stated.
Certain items have special modes of measurement that are frequently tested. Steel reinforcement is measured by weight in quintals or kilograms, and the weight is computed from the length of the bars using the formula that the weight of a bar in kilograms equals the diameter squared in millimetres divided by 162, multiplied by the length in metres. This standard relation comes from the fact that one square millimetre area of steel weighs about 7.85 grams per metre per square millimetre, giving the factor d squared divided by 162. Similarly, the number of bricks per cubic metre of brickwork is roughly 500, allowing for the mortar joints, and the number of cement bags per cubic metre of concrete is obtained by dividing the cement required in kilograms by 50, the weight of one bag.
While taking out the quantities, the estimator must deduct the openings from masonry and plastering, but add back the sides of openings for jambs and reveals, as specified in the relevant rules. Painting and whitewashing are measured over the actual surface, and deductions are not made for small openings but are made for large openings. The estimate is finally summarised in the abstract form, where the cost of each item is entered against its quantity, and the sum total is rounded off and presented with contingencies at about three to five percent and work-charge establishment at about one and a half to two percent of the total cost.
Example: A room has an internal size of 5 metres by 4 metres, with walls 0.3 metres thick. Compute the quantity of earthwork in excavation for the foundation if the trench is dug all round, 0.5 metres wide and 1 metre deep, and find the quantity of brickwork in the foundation and superstructure if the plinth wall is 0.5 metres high and the superstructure wall is 3 metres high above plinth, both of 0.3 metre thickness.
Solution: Centre to centre length = 5 + 0.3 = 5.3 m, centre to centre breadth = 4 + 0.3 = 4.3 m. Perimeter of trench centre line = 2 x (5.3 + 4.3) = 2 x 9.6 = 19.2 m. Earthwork in excavation = perimeter x width x depth = 19.2 x 0.5 x 1.0 = 9.6 cubic metres.
Brickwork in foundation and plinth: the volume of brickwork is obtained by the perimeter multiplied by the wall thickness multiplied by the height. Total height of brickwork = 0.5 + 3.0 = 3.5 m. Quantity of brickwork = 19.2 x 0.3 x 3.5 = 20.16 cubic metres.
Example 2: A wall 20 metres long, 3 metres high and 0.3 metres thick has a door opening of 2.1 metres by 1.2 metres. Find the net quantity of brickwork and the quantity of plastering on one face of the wall, deducting the opening.
Solution: Gross brickwork = 20 x 3 x 0.3 = 18 cubic metres. Door opening volume = 2.1 x 1.2 x 0.3 = 0.756 cubic metres. Net brickwork = 18 - 0.756 = 17.244 cubic metres. Plastering area on one face = 20 x 3 - 2.1 x 1.2 = 60 - 2.52 = 57.48 square metres.
Example 3: Find the weight of steel required for a beam having four bars of 12 millimetre diameter, each 6 metres long, using the formula weight = d squared divided by 162.
Solution: Weight per metre of 12 mm bar = 12 x 12 / 162 = 144 / 162 = 0.889 kg per metre. Length of all four bars = 4 x 6 = 24 metres. Total weight = 24 x 0.889 = 21.33 kilograms. The steel required is about 21.33 kilograms.
Example 4: Estimate the number of bricks required for 10 cubic metres of brickwork, assuming 500 bricks per cubic metre and adding 5 percent for wastage.
Solution: Bricks required = 10 x 500 = 5000 bricks. Adding 5 percent wastage = 5000 x 0.05 = 250 bricks. Total bricks required = 5000 + 250 = 5250 bricks.
| Item | Unit of measurement |
|---|---|
| Earthwork in excavation | Cubic metre |
| Concrete | Cubic metre |
| Brickwork in foundation and superstructure | Cubic metre |
| Steel reinforcement | Kilogram / quintal |
| Plastering, pointing, flooring, painting | Square metre |
| Pipes, wiring, handrails, skirting | Running metre |
| Doors, windows, ventilators, fans | Number |
| Damp proof course | Square metre |
| Item | Standard value |
|---|---|
| Bricks per cubic metre of brickwork | About 500 |
| Cement bag weight | 50 kg |
| Weight of 12 mm steel bar | 0.889 kg per metre |
| Weight formula | d x d / 162 kg per metre |
| Contingencies allowance | 3 to 5 percent |
| Work-charge establishment | 1.5 to 2 percent |
flowchart TD
A[Detailed Estimation] --> B[Essentials]
A --> C[Measurement Sheet]
A --> D[Abstract Sheet]
A --> E[Lead Statement]
B --> B1[Complete drawings]
B --> B2[Specifications]
B --> B3[Realistic rates]
C --> C1[Length x breadth x height]
C --> C2[Deductions for openings]
D --> D1[Quantity x rate]
D --> D2[Add contingencies]
E --> E1[Distance of material travel]
C1 --> C1a[Cubic metre items]
C1 --> C1b[Square metre items]
C1 --> C1c[Running metre items]
C1 --> C1d[Number items]
The following diagrams show the arrangement of a building estimate and the measurement of quantities from a simple room plan.
Detailed estimation converts the drawings of a project into a precise financial statement, because it is here that every length, breadth and height is measured, every quantity is computed and every rate is applied. In this chapter we have studied the essentials of a good estimate, namely complete drawings, clear specifications and realistic rates, and the three parts of the estimate, namely the measurement sheet, the abstract sheet and the lead statement. We have learned the units in which common items are measured, the standard conversion factors such as 500 bricks per cubic metre and the weight formula for steel, and we have solved numerical examples on excavation, brickwork, plastering and steel weight. The skill of taking out quantities accurately is the heart of the estimator's work, and it is also the basis of the next topic of quantity estimation, where the measurement of individual items such as earthwork, concrete and masonry is taken up in full detail. A candidate who masters the measurement sheet and the abstract sheet will find both the concept questions and the numerical questions of estimation easy to handle in the examination.