🏗️ Civil Engineering

23.4 Rate Analysis

Start MCQ Practice →

23.4 Rate Analysis

Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.4 Rate Analysis

1. Introduction

Rate analysis is the process of determining the cost of one unit of an item of work, such as one cubic metre of concrete, one cubic metre of brickwork or one square metre of plastering, by adding together the cost of the materials, the cost of the labour and the charges for tools and plants used in its execution. No item of the estimate can be priced without rate analysis, because the rates in the schedule are all built up from the actual costs of cement, sand, aggregates, bricks, steel and the wages of the workmen. For a candidate in SSC JE, RRB JE and state AE/JE examinations, rate analysis is a highly scoring topic, because questions that give the mix proportion and the rates of materials and ask for the cost per cubic metre of concrete appear regularly in the numerical portion of the paper.

The total rate of an item is made up of several distinct components. The cost of materials includes the market price of every material entering the item, together with the cost of carriage to the site and the wastage allowed during handling and use. The cost of labour is the sum of the wages of the different categories of workmen, such as the mason, the beldar, the bhisti or waterman, the carpenter and the bar bender, each multiplied by the time they spend on one unit of the item. To this are added the cost of tools and plants, usually taken as a small percentage of the labour cost, the cost of water for curing and mixing, and a percentage for the contractor's profit and overheads, so that the rate reflects the true market price of the finished work.

In this chapter we will study the components that make up a rate, the process of rate analysis from the quantity of materials to the final rate, the standard assumptions used in the analysis of concrete and brickwork items, and the effect of the lead and lift on the cost of materials. We will also solve worked numerical examples of the rate analysis of cement concrete and brickwork, which are the two most commonly examined items, so that the candidate can reproduce the complete calculation in the examination.

2. Components and Process of Rate Analysis

The rate analysis of any item is carried out through a definite sequence. First, the quantity of the item for which the rate is required is fixed at one unit, such as one cubic metre. Second, the quantity of each material required for that unit is computed from the mix proportion, using the dry volume factors and the wastage percentages. Third, the cost of each material is obtained by multiplying its quantity by its market rate including carriage. Fourth, the labour required for the item is worked out in terms of the number of days of each category of workman, and the labour cost is found by multiplying the days by the daily wages. Finally, the costs of materials and labour are added to the charges for tools and plants, water, and the contractor's overheads and profit, to obtain the rate of the item.

The cost of materials is affected by the lead and the lift, which are the horizontal distance and the vertical height over which the material has to be transported from its source to the site. The cost of carriage increases with the lead, and the specification prescribes that a certain quantity of material can be carted free of cost up to a basic lead, and extra cost is charged for additional lead beyond it. Similarly, the lift is the vertical rise over which the material is carried, and the cost of lifting the material above a certain height is added to the rate. The estimator must therefore know the lead and lift of every material, because they form a substantial part of the delivered cost of materials like sand and stone aggregates.

The labour cost is determined from the standard output of a workman, which is the amount of work a workman of a given category can do in one day. For example, one mason with the help of one beldar and one bhisti can complete about one cubic metre of brickwork in one day, while the number of masons and labourers required for one cubic metre of concrete depends on the mix and the method of mixing. The standard data for the output of workmen are taken from the Public Works Department schedule of rates, and the candidate must remember the commonly quoted figures such as the number of beldars required per cubic metre of different items.

3. Rate Analysis of Concrete and Brickwork

The rate analysis of cement concrete is the most frequently examined item, and it illustrates the complete procedure. For a mix of 1:2:4, the dry volume of concrete is obtained by multiplying the wet volume by 1.54, and the quantities of cement, sand and aggregate are found from the proportion. The cost of these materials at their market rates, including carriage and wastage, gives the material cost. The labour for one cubic metre of concrete includes the mason for laying and finishing, the beldars for mixing and carrying, the bhisti for adding water and curing, and sometimes the machine for mixing, and the labour cost is obtained from the number of days multiplied by the wages. To this are added the cost of tools and plants, water, and the contractor's overheads and profit, and the sum gives the rate of one cubic metre of concrete.

The rate analysis of brickwork follows a similar procedure. For one cubic metre of brickwork, the number of bricks is taken as 500, and the quantity of mortar is taken as one third of the volume, that is 0.33 cubic metres for 1:6 mortar. The mortar itself is analysed from the quantity of cement and sand, the quantity of cement being computed from the mix with the dry volume factor of 1.33. The cost of bricks and the cost of the mortar are added to the labour cost, which includes the mason, the beldar and the bhisti, and then the tools and plants, water, overheads and profit are added to obtain the rate of brickwork per cubic metre.

In both analyses, the wastage and the extra charges must be carefully stated. Materials like cement are bought in bags and the wastage in handling is allowed at a small percentage, while bricks are allowed wastage of about 2.5 percent. The contractor's profit is usually taken between 10 and 20 percent of the total cost, and the overhead charges cover supervision, establishment and site office expenses. The rate analysis therefore expresses in numbers the practical fact that the cost of a unit of work is the sum of material cost, labour cost, plant charges and profit.

4. Worked Numerical Examples

Example 1: Determine the quantity of cement required for one cubic metre of concrete of mix 1:2:4, taking the dry volume as 1.54 times the wet volume.

Solution: Dry volume = 1 x 1.54 = 1.54 cubic metres. Sum of proportions = 1 + 2 + 4 = 7. Volume of cement = 1.54 x (1/7) = 0.22 cubic metres. Weight of cement = 0.22 x 1440 = 316.8 kg. Number of bags = 316.8 / 50 = 6.34, that is about 6.5 bags of cement.

Example 2: For the above concrete, the rates are cement Rs. 400 per bag, sand Rs. 1500 per cubic metre and aggregate Rs. 1800 per cubic metre. Compute the material cost for one cubic metre of 1:2:4 concrete.

Solution: Volume of cement = 0.22 m3, weight = 316.8 kg, bags = 6.34, cost of cement = 6.34 x 400 = Rs. 2536. Volume of sand = 1.54 x (2/7) = 0.44 m3, cost of sand = 0.44 x 1500 = Rs. 660. Volume of aggregate = 1.54 x (4/7) = 0.88 m3, cost of aggregate = 0.88 x 1800 = Rs. 1584. Total material cost = 2536 + 660 + 1584 = Rs. 4780.

Example 3: The labour for one cubic metre of the above concrete is 2 masons at Rs. 700 per day and 4 beldars at Rs. 450 per day. Find the labour cost and the total rate after adding 10 percent tools and plants, water charge of Rs. 20 and 15 percent profit.

Solution: Mason cost = 2 x 700 = Rs. 1400. Beldar cost = 4 x 450 = Rs. 1800. Total labour cost = 1400 + 1800 = Rs. 3200. Cost of tools and plants at 10 percent = 3200 x 0.10 = Rs. 320. Total cost before profit = 4780 + 3200 + 320 + 20 = Rs. 8320. Profit at 15 percent = 8320 x 0.15 = Rs. 1248. Rate of concrete = 8320 + 1248 = Rs. 9568 per cubic metre.

Example 4: Estimate the quantity of cement and sand for 1 cubic metre of brickwork in 1:6 mortar, assuming 500 bricks and 0.33 cubic metres of mortar per cubic metre of brickwork, with dry volume factor 1.33 for mortar.

Solution: Dry volume of mortar = 0.33 x 1.33 = 0.439 cubic metres. Sum of proportions = 1 + 6 = 7. Volume of cement = 0.439 x (1/7) = 0.063 cubic metres. Weight of cement = 0.063 x 1440 = 90.4 kg, that is 1.81 bags. Volume of sand = 0.439 x (6/7) = 0.376 cubic metres. The brickwork requires about 1.8 bags of cement and 0.376 cubic metres of sand per cubic metre.

5. Quick Revision Tables

Table 1: Components of a Rate

Component What it includes
Material cost Market price, carriage, wastage
Labour cost Wages of all workmen for the unit
Tools and plants About 10 percent of labour cost
Water Mixing and curing charge
Overheads and profit Contractor's profit 10 to 20 percent
Lead and lift Transport cost of materials

Table 2: Cement Content for Common Mixes

Mix Cement per m3 of concrete Bags per m3
1:1.5:3 0.28 m3 8 bags
1:2:4 0.22 m3 6.5 bags
1:3:6 0.154 m3 4.4 bags
1:4:8 0.118 m3 3.4 bags

6. Mind Map

flowchart TD
    A[Rate Analysis] --> B[Material cost]
    A --> C[Labour cost]
    A --> D[Tools and plants]
    A --> E[Overheads and profit]
    B --> B1[Quantity from mix]
    B --> B2[Market rate plus carriage]
    B --> B3[Wastage allowance]
    C --> C1[Mason days]
    C --> C2[Beldar days]
    C --> C3[Bhisti days]
    D --> D1[10 percent of labour]
    E --> E1[Profit 10 to 20 percent]
    B1 --> B1a[Dry volume 1.54]
    B1 --> B1b[1:2:4 gives 6.5 bags]

7. Important Diagrams (SVG)

The following diagrams show the components of a rate and the steps of analysing the cost of one cubic metre of concrete.

Components of a Rate RATE OF ITEM Material cost Quantity x rate Labour Days x wages Tools and plants 10 percent of labour Water and overheads Contractor's profit 10-20 percent Sum of all components gives the rate of one unit of the item. Golden Rule Rate = material cost + labour cost + plant charges + overheads + profit.

Rate Analysis of 1 m3 Concrete 1:2:4 Cement = 0.22 m3 = 6.5 bags Sand = 0.44 m3 Aggregate = 0.88 m3 Labour = masons + beldars Dry volume = 1.54 m3, sum = 7 Cement = 1.54/7 = 0.22 m3 Material cost = Rs. 4780 Labour cost = Rs. 3200 Tools 320 + water 20 = Rs. 340 Profit 15 percent = Rs. 1248 Total rate = Rs. 9568 per m3 Golden Rule Always multiply the wet volume by 1.54 before working out mix quantities.

8. Common Mistakes

  1. Many students forget to apply the dry volume factor of 1.54 and use the wet volume in the mix, which gives an unrealistically low material cost.
  2. A common error is to take the cement quantity directly from the volume of wet concrete without converting it into bags by dividing the weight by 50.
  3. Candidates often omit the cost of carriage of materials, forgetting that the delivered rate at site is higher than the market rate at the source.
  4. Some students forget to add tools and plants and water charges, leaving the computed rate short of the actual cost of the item.
  5. A frequent mistake is to apply profit on the material cost only; the correct practice is to add profit on the total cost of the item.
  6. Many candidates use the wrong sum of proportions, confusing 1:2:4 with 1:1.5:3, which changes the number of cement bags and hence the rate.
  7. In brickwork analysis, students often forget the 1.33 dry volume factor for mortar and compute the cement from the wet volume of mortar.
  8. Candidates frequently omit the lead and lift charges for materials, underestimating the delivered cost of sand, aggregate and bricks.

9. Exam Tips

  1. Memorise the cement bags per cubic metre for common mixes: 1:1.5:3 about 8 bags, 1:2:4 about 6.5 bags, 1:3:6 about 4.4 bags.
  2. Always state the dry volume factor clearly: 1.54 for concrete and 1.33 for mortar, because this is a favourite examination point.
  3. Remember that tools and plants are taken as about 10 percent of the labour cost, and profit as 10 to 20 percent of the total cost.
  4. In rate analysis numericals, compute the material cost, then the labour cost, then add plant charges, water and profit, in that order.
  5. Learn the standard output figures, such as 500 bricks per cubic metre and one third of the volume as mortar for brickwork.
  6. Note that the cost of carriage depends on the lead and the lift, and a free haul distance is allowed up to a basic lead.
  7. Practise the full analysis of one cubic metre of 1:2:4 concrete once with numbers, because the same pattern is repeated with changed rates.
  8. Remember that wastage of materials is included in the material cost, so the purchased quantity is slightly higher than the theoretical quantity.

10. Conclusion

Rate analysis is the process that turns the quantities of the estimate into money, because it determines the cost of one unit of every item of work from the prices of materials and the wages of labour. In this chapter we have studied the components of a rate, namely the material cost with carriage and wastage, the labour cost from the days and wages of the workmen, the tools and plants charges, water, overheads and the contractor's profit. We have learned the standard assumptions of the dry volume factors for concrete and mortar, the cement content of the common mixes, and the effect of lead and lift on the cost of materials, and we have solved worked numerical examples of the rate analysis of concrete and brickwork. The rate of an item is the link between quantity estimation and the final abstract of the estimate, and a candidate who can analyse rates correctly can answer a whole family of numerical questions in the estimation and costing paper. This understanding of how costs are built up also prepares the candidate for the management topics that follow, where the control of cost and time during construction is studied.