Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.6 Construction Planning
Construction planning is the process of deciding in advance what work has to be done, in what order it will be done, by whom it will be done and with what resources, so that the project is completed within the stipulated time and budget. A construction project involves a large number of interrelated activities, from site preparation and foundation work to superstructure, services and finishing, and unless these activities are planned carefully, the work becomes disordered, resources stand idle, delays occur and costs rise. For a candidate in SSC JE, RRB JE and state AE/JE examinations, construction planning is a conceptual topic that tests the understanding of the principles of management, the stages of a project and the tools used to represent and control the plan.
The need for planning arises from the very nature of construction. A building project ties up large sums of money in materials, machinery and labour, and every day of delay costs money in interest, overheads and idle resources. Planning ensures that the sequence of activities is logical, that the required materials arrive at the site exactly when they are needed, that the machines and men are kept fully employed, and that the bottlenecks in the programme are identified before they cause trouble. Planning is therefore not an optional academic exercise but a practical necessity for the survival of the construction firm.
In this chapter we will study the objectives and advantages of construction planning, the various stages through which a construction project passes from conception to completion, the principles of project management such as planning, scheduling and controlling, and the organisation structures used in the construction industry. We will also study the types of construction such as residential, commercial, industrial and infrastructure works and the special planning needs of each, along with the factors that make construction planning complex, such as weather, site conditions and the availability of resources.
The primary objective of construction planning is to complete the project within the specified time, cost and quality. Time planning fixes the dates for the start and completion of each activity, cost planning sets the budget and the cash flow, and quality planning specifies the standards of work and the methods of inspection. A secondary objective is the optimum use of resources, so that labour, materials, machines and money are neither over-utilised nor left idle. The plan also aims at safety, because a well-planned site with orderly movement of men and materials is a safer site, and at the coordination of the many agencies, such as the client, the architect, the consultant, the contractor and the subcontractors, who are all involved in the project.
The advantages of proper planning are numerous. Planning reduces the total time of the project because activities are carried out in a logical order without idle waiting. Planning reduces the cost of the project by avoiding overtime, by ordering materials in economical quantities, and by keeping the machinery fully occupied. Planning improves the quality of work because every activity is checked against the specification at the correct stage. Planning provides a clear basis for monitoring and control, because the actual progress can be compared with the planned progress and corrective action can be taken wherever the work is lagging. Finally, planning helps in the settlement of claims and disputes, because the plan forms the documented programme to which the contractor and the owner have agreed.
The planning of a project must be carried out at different levels. The long range planning is done by the top management of the firm, deciding the overall programme of work over several years. The short range planning is done for each project, covering the complete schedule of activities of that project. The day-to-day planning is done by the site engineer, fixing the tasks of each gang for the coming days. All the levels must be consistent, so that the daily plan supports the project plan, which in turn supports the corporate plan.
A construction project passes through a definite sequence of stages from its conception to its completion. The first stage is the inception or the recognition of the need, when the owner decides that a building or a structure is required, whether for residence, industry, education or public service. The second stage is the feasibility study, when the site is examined, the approximate cost is estimated, the availability of funds is checked and the technical possibilities are reviewed, so that the decision to proceed can be taken on sound grounds. The third stage is the design stage, when the architect and the engineer prepare the plans, sections, elevations and structural drawings, and the specifications and the detailed estimate are prepared.
The fourth stage is the tender and award of contract, when the contractor is selected through open or limited tendering and the contract document is signed. The fifth stage is the construction stage, when the actual work is executed according to the programme, with the site engineer directing the labour and material, and with regular inspections ensuring quality. The sixth stage is the commissioning or handing over, when the completed work is tested, the defects are rectified, the final bill is prepared and the building is handed over to the owner. The final stage is the maintenance period, during which the contractor is responsible for rectifying defects that appear in the guarantee period.
Each of these stages requires its own planning. In the design stage, planning decides the layout of the building and the structural system. In the tender stage, planning decides the contract type and the form of the tender document. In the construction stage, planning decides the sequence of operations, the deployment of labour and machinery and the procurement of materials. The success of the whole project depends on the completeness of the planning done before construction begins, because changes made after the work has started are expensive and disruptive.
The management of any construction project rests on three fundamental functions: planning, scheduling and controlling. Planning is the selection of the activities and their logical order; scheduling is the assignment of time, dates and resources to each activity; and controlling is the comparison of the actual progress with the schedule and the taking of corrective action. These three functions are performed repeatedly throughout the life of the project, because the plan is not a fixed document but a living programme that is updated as the work proceeds.
The tools used to represent a construction plan are the bar chart, the Gantt chart and the network techniques such as CPM and PERT. The bar chart is the simplest tool, in which each activity is represented by a horizontal bar drawn against a time scale, showing the start and finish of the activity. The Gantt chart is a refined bar chart that can also show the progress of each activity by shading the bar in proportion to the work done. The network techniques represent the activities as a diagram of arrows and nodes, showing the logical interdependence of the activities and enabling the critical path to be found. The critical path is the longest sequence of dependent activities in the network, and it decides the total duration of the project.
The organisation of the construction project is also a part of planning. The line organisation places each workman under one supervisor only, so that orders flow in a clear line from the project manager to the site engineer to the foreman and to the gang. The functional organisation places specialists in charge of particular functions such as materials, machinery and finance. The project organisation combines the two, with a project manager responsible for the whole project and functional experts assisting him. In construction practice, the line organisation with a project manager is the most common, because it gives clear responsibility and quick decisions at the site.
Example 1: A project consists of three activities A, B and C, where B and C can start only after A is complete. Activity A takes 5 days, B takes 6 days and C takes 4 days. If B and C are done in parallel, find the minimum total duration of the project.
Solution: The project has two paths: A-B of 5 + 6 = 11 days, and A-C of 5 + 4 = 9 days. The project duration is decided by the longest path, so the minimum total duration = 11 days.
Example 2: A job requires 4 labourers working 8 hours per day for 10 days. If the number of labourers is increased to 5, find the number of days required, assuming the productivity per labourer per day remains the same.
Solution: Total man-days = 4 x 10 = 40 man-days. With 5 labourers, days = 40 / 5 = 8 days. The job will be completed in 8 days.
Example 3: A contractor is to complete a work in 12 days with an output of 2 cubic metres of brickwork per day. Find the total quantity of brickwork and the number of bricklayers required if each mason completes 0.5 cubic metre per day.
Solution: Total brickwork = 12 x 2 = 24 cubic metres. Number of masons = 24 / (12 x 0.5) = 24 / 6 = 4 masons. Four masons are required.
| Stage | Main activity |
|---|---|
| Inception | Recognition of the need |
| Feasibility study | Site, cost, funds and technical review |
| Design | Drawings, specifications and estimate |
| Tender and award | Selection of contractor, contract signing |
| Construction | Execution of work at site |
| Commissioning | Testing and handing over |
| Maintenance | Rectification during guarantee period |
| Function | Purpose | Tool |
|---|---|---|
| Planning | Decide activities and order | Bar chart, network |
| Scheduling | Fix time and resources | Gantt chart |
| Controlling | Compare and correct | Progress reports, CPM |
| Organising | Fix authority and responsibility | Organisation chart |
flowchart TD
A[Construction Planning] --> B[Objectives]
A --> C[Stages of project]
A --> D[Management functions]
A --> E[Planning tools]
B --> B1[Time control]
B --> B2[Cost control]
B --> B3[Quality control]
C --> C1[Inception]
C --> C2[Feasibility]
C --> C3[Design]
C --> C4[Tender]
C --> C5[Construction]
C --> C6[Handing over]
D --> D1[Planning]
D --> D2[Scheduling]
D --> D3[Controlling]
E --> E1[Bar chart]
E --> E2[Gantt chart]
E --> E3[CPM and PERT]
The following diagrams show the stages of a construction project and the organisation structure used at the site.
Construction planning is the discipline that brings order to the chaos of a building site, because it decides beforehand what is to be done, in what sequence, by whom and with what resources. In this chapter we have studied the objectives of planning, namely completion within time, cost and quality, and the advantages that flow from it, such as lower cost, higher quality and better control. We have traced the stages of a construction project from inception and feasibility study through design, tender, construction and handing over, and we have studied the management functions of planning, scheduling and controlling and the tools used for them, such as the bar chart, the Gantt chart and the network techniques. We have also solved simple numerical examples on the project duration and the deployment of labour. The concepts of this chapter form the foundation for the next two topics, where the network techniques of CPM and PERT and the scheduling of construction are studied in full detail. A candidate who understands the principles of planning will find those techniques easy to master, because the critical path and the schedule are simply the tools by which the plan is drawn and controlled.