Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.8 Construction Scheduling
Construction scheduling is the process of assigning a definite time and date to every activity of the project, so that the construction work is carried out in a planned sequence and the project is completed by its target date. While planning decides what work has to be done and in what order, scheduling decides when each activity will start and finish, how long it will take and what resources will be needed at each stage. A schedule is therefore the time-table of the project, and it forms the document against which the actual progress is measured. For a candidate in SSC JE, RRB JE and state AE/JE examinations, construction scheduling is a conceptual and numerical topic in which questions on the bar chart, the network schedule and the resource levelling appear regularly.
The need for scheduling arises because the resources of a project, namely labour, materials, machinery and money, are limited. If all the activities are started at once, the site will be congested, the machinery will be insufficient and the labour will be over-stretched. Scheduling spreads the activities over the available time and matches them with the available resources, so that every gang has work every day and every machine is kept usefully occupied. The schedule also tells the procurement department when each material must reach the site, and it tells the finance department when the money will be required, so that the cash flow of the project can be planned.
In this chapter we will study the methods of scheduling, including the bar chart or Gantt chart, the milestone chart and the network-based schedule from CPM and PERT. We will study the concepts of resource scheduling, including resource levelling and resource allocation, and the different patterns of scheduling such as the sequential, parallel and balanced patterns. We will also study the concept of time-cost optimisation and crashing, in which the duration of the project is reduced by shortening the critical activities at an extra cost, and we will solve worked numerical examples on the total float and the project duration.
The bar chart, also called the Gantt chart, is the oldest and simplest method of scheduling. In the bar chart, every activity of the project is listed one below the other on the left hand side, and the time scale of the project is marked horizontally across the top. Each activity is then represented by a horizontal bar, drawn between the starting date and the finishing date of the activity. The length of the bar is proportional to the duration of the activity, and by reading the bar chart one can see at a glance when every activity starts, when it finishes and how it overlaps with the other activities.
The bar chart is very easy to prepare and to understand, and it can be understood by the site staff without any special training. However, it has serious limitations. The bar chart does not show the interdependence of the activities, so it cannot show which activities depend on the completion of others. It cannot show the critical activities, because it has no concept of the critical path, and therefore the delay of a non-critical activity can cause the project to be delayed without the planner noticing it. It also cannot show the progress of the work in detail, and when the activities are many, the chart becomes crowded and confusing.
To overcome some of these limitations, the Gantt chart with progress marking is used, in which each bar is shaded in proportion to the work actually completed. A comparison of the shaded portion with the full bar shows at once whether the activity is on time, ahead of time or behind time. The milestone chart is a further refinement, in which only the important events of the project, called milestones, such as the completion of the foundation, the completion of the roof and the completion of the finishing, are shown as special marks on the time scale, so that the top management can check the progress of the project by verifying a few key points instead of every activity.
The network techniques of CPM and PERT provide a much more powerful basis for scheduling than the bar chart. From the network, the earliest start time and the latest start time of every activity are known, and the schedule can be drawn either as an earliest start schedule, in which every activity starts as early as possible, or as a latest start schedule, in which every activity starts as late as possible without delaying the project. The choice between the two depends on the availability of resources; the latest start schedule delays the spending of money and the use of resources, but it leaves very little margin for delay.
The resources of the project are usually limited, and the schedule must be adjusted so that the peak requirement of any resource does not exceed its availability. Resource levelling is the process of smoothing the resource requirement of the project over its duration, so that the peaks and valleys of the resource histogram are reduced. This is done by shifting the non-critical activities, which have float, away from the periods of peak demand and into the periods of low demand, without changing the total duration of the project. Resource allocation is the adjustment of the schedule when the available resource is less than the requirement, so that some activities are stretched over a longer time, which may increase the project duration.
The scheduling of the activities can follow different patterns. In the sequential pattern, the activities are done one after another, which requires little labour and machinery but takes a long time. In the parallel pattern, many activities are done simultaneously, which reduces the time but requires a large amount of labour and machinery and causes congestion. The balanced pattern falls between the two, combining the advantage of a reasonable time with an economical use of resources, and it is the pattern recommended for most construction projects.
In many projects, the owner is prepared to pay an extra cost to complete the project earlier, and the reduction of the project duration by the deliberate shortening of the activities is called crashing. The relationship between time and cost for an activity is such that the normal duration corresponds to the normal cost, and the crash duration corresponds to the crash cost, which is higher. The cost slope of an activity is the extra cost required to reduce the duration of the activity by one unit of time, and it is computed by the formula that the cost slope equals the crash cost minus the normal cost divided by the normal duration minus the crash duration.
The crashing of a project is done only on the critical activities, because the reduction of a non-critical activity does not reduce the project duration. Among the critical activities, the one with the smallest cost slope is crashed first, because it gives the cheapest reduction in the project time. As the crashing proceeds, the critical path may change, and the crashing must be continued on the new critical activities, so that the project duration is progressively reduced at the minimum total cost. The process continues until no further economical crashing is possible or until the desired project duration is reached.
The time-cost optimisation problem aims to find the project duration that gives the minimum total cost, where the total cost is the sum of the direct cost of the activities, which increases with crashing, and the indirect cost of the project, which decreases with the reduction of the project duration because the overheads such as supervision, site office and interest are saved. The optimum project duration is the point at which the sum of the direct and indirect costs is minimum, and this point is found by crashing the project step by step.
Example 1: A project has an activity with normal duration 10 days and normal cost Rs. 20,000, and crash duration 6 days with crash cost Rs. 32,000. Find the cost slope of the activity.
Solution: Cost slope = (Crash cost - Normal cost) / (Normal duration - Crash duration) = (32000 - 20000) / (10 - 6) = 12000 / 4 = Rs. 3000 per day.
Example 2: An activity with normal duration of 8 days and crash duration of 5 days has a cost slope of Rs. 2000 per day. Find the crash cost if the normal cost is Rs. 15,000.
Solution: Reduction in duration = 8 - 5 = 3 days. Extra cost = 3 x 2000 = Rs. 6000. Crash cost = 15,000 + 6000 = Rs. 21,000.
Example 3: Two critical activities A and B form the critical path with durations of 6 and 4 days. If activity A can be crashed to 4 days at a cost slope of Rs. 500 per day and activity B can be crashed to 2 days at Rs. 400 per day, find the minimum project duration after crashing and the total crashing cost.
Solution: Crash B by 2 days first at 400 per day, cost = 2 x 400 = Rs. 800. The path duration becomes 6 + 2 = 8 days. Now crash A by 2 days at 500 per day, cost = 2 x 500 = Rs. 1000. Final project duration = 4 + 2 = 6 days, and total crashing cost = 800 + 1000 = Rs. 1800.
| Method | Basis | Advantage | Limitation |
|---|---|---|---|
| Bar / Gantt chart | Time scale with bars | Simple to prepare | No interdependence |
| Milestone chart | Key events on time scale | Good for top management | Few details |
| CPM network | Critical path | Shows critical activities | Needs training |
| PERT network | Probabilistic times | Handles uncertainty | Needs three estimates |
| Concept | Meaning |
|---|---|
| Resource levelling | Smoothing the resource histogram using float |
| Resource allocation | Adjusting schedule to limited resources |
| Cost slope | Extra cost per unit time reduction |
| Normal duration | Duration at minimum direct cost |
| Crash duration | Minimum possible duration |
| Optimum duration | Minimum total cost duration |
flowchart TD
A[Construction Scheduling] --> B[Bar chart]
A --> C[Network schedule]
A --> D[Resource scheduling]
A --> E[Time-cost optimisation]
B --> B1[Simple and easy]
B --> B2[No critical path shown]
C --> C1[Earliest start schedule]
C --> C2[Latest start schedule]
D --> D1[Resource levelling]
D --> D2[Resource allocation]
E --> E1[Crashing critical activities]
E --> E2[Cost slope formula]
E --> E3[Optimum project duration]
E1 --> E1a[Smallest cost slope first]
The following diagrams show a Gantt or bar chart and the relationship of time and cost in crashing.
Construction scheduling converts the plan of the project into a time-table of execution, because it fixes the start and finish dates of every activity and matches the activities with the available resources. In this chapter we have studied the methods of scheduling, from the simple bar chart and the milestone chart to the network-based schedules of CPM and PERT, and we have seen the limitations of each method. We have studied the resource aspects of scheduling, including resource levelling, which smooths the peaks of the resource demand using the float of the non-critical activities, and resource allocation, which adjusts the schedule to the available resources. We have also studied time-cost optimisation, in which the critical activities are crashed at the minimum extra cost to shorten the project, and we have solved numerical examples on the cost slope and the crashing sequence. The schedule is the document against which the progress of the project is measured, and the concepts of this chapter complete the study of the planning and scheduling tools. A candidate who has mastered the bar chart, the network schedule and the crashing calculations will find the questions of construction management easy to answer, and the same tools are used in the field by the project engineer to control the progress of real construction works.