Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.9 Contracts and Tendering
A contract is a legally binding agreement between two or more parties, by which one party undertakes to do some work and the other party agrees to pay for it. In civil engineering, the work of construction is almost always executed through a contract, because the owner, whether a government department, a corporation or a private individual, seldom possesses the machinery, the labour and the skill required to construct large works himself. The contractor, who is the other party, undertakes to complete the work as per the drawings, specifications and the conditions of the contract, in return for the agreed payment. For a candidate in SSC JE, RRB JE and state AE/JE examinations, contracts and tendering form a highly scoring conceptual topic, because questions on the types of contracts, the tender procedure and the important clauses of the contract appear frequently.
The process by which the contractor is selected is called tendering. In the case of public works, the owner cannot simply choose a contractor at his will, because the money belongs to the public and the selection must be open and fair. The owner therefore invites tenders, in which the intending contractors submit their offers or bids for doing the work, and the work is awarded to the contractor whose tender is the most advantageous, which in the usual case is the one with the lowest price, provided he is technically capable and financially sound. The whole process, from the invitation of the tender to the signing of the agreement, is governed by the rules of the department and the law of contract.
In this chapter we will study the essential elements of a valid contract, the different types of contracts such as the lump sum contract, the item rate contract, the percentage rate contract, the cost plus contract and the labour contract, and the advantages and disadvantages of each. We will study the tender procedure, the conditions of the contract, the meaning of the earnest money and the security deposit, and the stages from the issue of the tender to the acceptance and the signing of the agreement. We will also study the important documents that make up the contract, such as the notice inviting tender, the tender form, the specifications, the conditions of contract and the bill of quantities.
For a contract to be legally enforceable, certain essentials must be present. There must be an offer by one party and an acceptance of that offer by the other party, and both must be genuine and communicated. There must be a lawful consideration, which is the price or the value for which the work is done, and both the offer and the consideration must be lawful, that is, they must not be against the law or public policy. The parties must be competent to contract, meaning that they are of sound mind, have attained the age of majority and are not disqualified by law. The consent of the parties must be free, without coercion, undue influence, fraud or misrepresentation, and the object of the contract must be lawful.
The contract must also comply with the formalities required by law. A contract relating to an amount exceeding a certain limit, such as one hundred rupees, must be in writing and registered, and in the case of public works the contract is executed on a printed form in duplicate, stamped according to the law. The contract must contain clear terms describing the work, the time of completion, the price, the mode of payment, the provisions for extra work, the penalties for delay, and the procedure for the settlement of disputes. A contract that is vague, incomplete or unlawful is void, and no court will enforce it.
The relationship between the owner and the contractor is governed by the Indian Contract Act, and a breach of the contract by either party gives the other party the right to claim damages. If the contractor fails to complete the work in time or does the work badly, the owner can withhold payment, recover damages, or even terminate the contract and get the work done by another contractor at the risk and cost of the defaulting contractor. Similarly, if the owner fails to pay the contractor's bills, the contractor can claim the amount with interest and damages. The conditions of the contract lay down the exact rights and obligations of both parties in such situations.
The contracts used in construction can be classified on different bases, and each type has its own advantages and disadvantages. In the lump sum contract, the contractor agrees to complete the whole work for a fixed sum of money, and the amount is not changed even if the actual cost of the work differs from the estimate. The lump sum contract is suitable when the drawings and specifications are complete and the work is well defined, and its advantage is that the owner knows his total liability in advance. However, any change in the design costs the owner extra, and the contractor may economise on quality to protect his profit.
In the item rate contract, the contractor quotes a rate for each item of work in the schedule, and the payment is made on the actual measured quantities multiplied by the agreed rates. The item rate contract is the most common type for public works, because it is fair to both parties, since the owner pays only for the work actually done and the contractor is paid for every unit executed. In the percentage rate contract, the contractor quotes a percentage above or below the departmental rate schedule, and the rates of all the items are taken as that percentage of the schedule rates. This contract is simple, because only one figure has to be quoted, but the advantage of competitive tendering on individual items is lost.
In the cost plus contract, the contractor is paid the actual cost of the work plus a certain percentage of the cost as his profit, and this type is used when the work is not well defined, such as in emergency repair work or in research work. The advantage of the cost plus contract is that the quality of the work is not sacrificed, but its disadvantage is that the owner has no certainty about the total cost and the contractor has no incentive to economise. The labour contract is one in which the owner supplies the materials and the contractor provides only the labour, and it is used for small works where the materials are of special quality. The turnkey contract is one in which the contractor designs, constructs and hands over the complete project, and it is used for large industrial projects.
The tender procedure begins with the preparation of the notice inviting tenders, which announces the work, its estimated cost, the date and time of receipt and opening of the tenders, the amount of the earnest money and the conditions under which the tender is to be submitted. The notice is published in the newspapers and on the website of the department, so that all eligible contractors have an equal opportunity to bid. The intending contractor obtains the tender documents, which consist of the tender form, the drawings, the specifications, the conditions of the contract, the schedule of quantities and the bill of quantities, on payment of the cost of the documents.
The contractor fills up the tender form, quoting his rates or his percentage, and submits it along with the earnest money, which is a small percentage of the estimated cost, usually two percent, deposited as a guarantee that the contractor will not withdraw his offer after it is submitted. The tenders are opened in the presence of the contractors or their representatives at the stated time, and the tenders below the estimated cost are examined. The lowest acceptable tender is normally accepted, subject to the technical and financial capability of the contractor, and a letter of acceptance is issued to him. Before the work is started, the contractor deposits the security deposit, which is a larger percentage of the contract value, usually ten percent, in the form of cash or bank guarantee, and the agreement is executed on stamped paper.
The contract document is a comprehensive record of all the terms of the work, and it includes the articles of agreement, the conditions of the contract, the specifications, the bill of quantities, the drawings and the schedule of rates. The conditions of the contract describe the time of completion, the power of the engineer to order extra work, the procedure for payment of the running and final bills, the provisions for the compensation for delay, and the method of settlement of disputes by arbitration. The contractor is bound by all these conditions, and the engineer-in-charge is the representative of the owner for the supervision and measurement of the work.
Example 1: The estimated cost of a work is Rs. 10,00,000 and the earnest money is 2 percent of the estimate. Find the amount of the earnest money to be deposited with the tender.
Solution: Earnest money = 2 percent of 10,00,000 = 0.02 x 10,00,000 = Rs. 20,000.
Example 2: The contract value of a work is Rs. 25,00,000 and the security deposit is 10 percent of the contract value. Find the amount of the security deposit.
Solution: Security deposit = 10 percent of 25,00,000 = 0.10 x 25,00,000 = Rs. 2,50,000.
Example 3: In a percentage rate contract, the departmental rate for brickwork is Rs. 800 per cubic metre and the contractor quotes a rate of 10 percent above the schedule. Find the contract rate of brickwork.
Solution: Contract rate = 800 x (1 + 0.10) = 800 x 1.10 = Rs. 880 per cubic metre.
| Type of contract | Basis of payment | Main use |
|---|---|---|
| Lump sum | Fixed total amount | Well-defined works |
| Item rate | Actual quantity x item rate | Most public works |
| Percentage rate | Percent of schedule rates | Simple tendering |
| Cost plus | Actual cost + percentage profit | Emergency and new works |
| Labour contract | Owner supplies materials | Small special works |
| Turnkey | Design, construct and hand over | Large industrial projects |
| Item | Typical percentage |
|---|---|
| Earnest money | 2 percent of estimated cost |
| Security deposit | 10 percent of contract value |
| Retention money | 10 percent of each running bill |
| Compensation for delay | 0.5 percent per week, maximum 10 percent |
flowchart TD
A[Contracts and Tendering] --> B[Essentials of contract]
A --> C[Types of contracts]
A --> D[Tender procedure]
A --> E[Contract documents]
B --> B1[Offer and acceptance]
B --> B2[Lawful consideration]
B --> B3[Competent parties]
C --> C1[Lump sum]
C --> C2[Item rate]
C --> C3[Percentage rate]
C --> C4[Cost plus]
D --> D1[Notice inviting tender]
D --> D2[Submission with earnest money]
D --> D3[Opening and acceptance]
D --> D4[Security deposit and agreement]
E --> E1[Conditions of contract]
E --> E2[Specifications]
E --> E3[Bill of quantities]
The following diagrams show the classification of contracts and the sequence of the tender procedure.
Contracts and tendering form the legal and administrative framework within which all construction work is executed, because they fix the rights and obligations of the owner and the contractor and the manner in which the work is awarded. In this chapter we have studied the essentials of a valid contract, including offer, acceptance, consideration, competent parties and free consent, and the different types of contracts, from the lump sum and the item rate contracts to the percentage rate, cost plus, labour and turnkey contracts, with the suitability of each. We have studied the complete tender procedure, from the notice inviting tender and the submission with the earnest money to the opening, acceptance, deposit of the security and the signing of the agreement, and the documents that make up the contract. We have also solved numerical examples on the earnest money, the security deposit and the percentage rate contract. The understanding of contracts is essential for the engineer, because the entire execution of the work, the measurement of the quantities and the payment of the bills are governed by the conditions of the contract, and a candidate who has mastered this topic can answer a large number of conceptual questions in the examination. This knowledge of contracts completes the commercial side of the estimation and construction management syllabus, and it is closely linked to the final topic of construction safety and quality control, where the actual standards of work executed under the contract are inspected and maintained.