23.10 Construction Safety and Quality Control

Subject: Civil Engineering Chapter: Estimation & Construction Management Topic: 23.10 Construction Safety and Quality Control

1. Introduction

Construction is one of the most hazardous industries in the world, because the work is carried out at great heights, with heavy machinery, moving loads, electrical installations and freshly placed concrete, and an accident can injure or kill a worker and delay the project. Construction safety is the discipline of preventing such accidents by the provision of safe working conditions, the use of protective equipment, the training of the workers and the enforcement of safety rules on the site. For a candidate in SSC JE, RRB JE and state AE/JE examinations, safety and quality control form a conceptual topic in which questions on the causes of accidents, the safety measures at various operations and the methods of quality control appear regularly.

Quality control is the process of ensuring that the materials used and the work executed conform to the specifications and the standards of the contract. A structure built with poor quality concrete or sub-standard steel may fail under the loads, causing loss of life and property, and therefore the quality of every item of work must be checked at the site. Quality control in construction covers the testing of the materials before use, the supervision of the work during execution and the inspection and testing of the finished work, and it is carried out by the engineer-in-charge with the help of the site laboratory. The quality of the work and the safety of the workers are closely connected, because a badly executed structure is unsafe for the occupants as well as for the workers.

In this chapter we will study the causes of construction accidents, the general safety measures to be adopted at a construction site, and the special safety measures for excavation, scaffolding, concreting, steel erection and electrical work. We will study the meaning and purpose of quality control, the field and laboratory tests on concrete, the concept of the statistical quality control with the control charts, and the methods of quality assurance at the various stages of construction. We will also study the standards and codes such as the IS codes of the Bureau of Indian Standards that govern the quality of materials and the safety of the workers.

2. Causes of Accidents and General Safety Measures

The accidents at a construction site can be traced to a number of causes. The physical causes include the failure of the scaffolding, the collapse of the excavated trenches, the falling of materials and tools from a height, the overturning of the cranes and the contact with live electrical wires. The human causes include the carelessness and fatigue of the workers, the lack of training, the violation of the safety rules, the improper use of the tools and the failure to use the protective equipment. The environmental causes include the bad weather, the poor lighting, the congested site and the slippery floors. Most accidents are preventable, and the first step in prevention is the identification of these causes.

The general safety measures at a construction site begin with the planning of the site itself. The site must be properly fenced, the materials must be stacked in a safe and orderly manner, the walkways and the staircases must be kept clear, and the dangerous places must be indicated by warning signs. Every worker must be provided with the protective equipment such as the safety helmet, the safety shoes and the safety belts, and the workers must be trained in the safe methods of doing their work. The first aid boxes must be available at convenient places, and the telephone numbers of the nearest hospital and the fire brigade must be displayed prominently.

The safety of the workers also requires the regular inspection of the equipment. The scaffolds must be examined periodically, the ropes and the chains of the cranes must be tested, the electrical wiring and the tools must be checked for insulation, and the defective tools must be removed from the site immediately. The lifting of heavy loads must be done by the machines and not by the workers, and the loads must be slung properly so that they do not slip. The workers must not be permitted to work in a congested manner, and the various trades must be so coordinated that no gang works under another gang from which materials might fall.

3. Safety in Special Operations

The excavation of the foundation trenches is a common source of accidents, because the sides of the trenches may collapse and bury the workers. The trenches deeper than 1.5 metres must be shored or sloped according to the nature of the soil, and the excavated soil must be kept at a safe distance from the edge of the trench. The workers must not work in a trench when heavy loads are being moved near the edge, and the ladders must be provided for entering and leaving the deep trenches. In the case of the trenches in loose or waterlogged soil, the sides must be supported by timbering or sheet piling, and the dewatering must be done before the men enter the trench.

The scaffolding and the formwork are another major source of accidents, because the workers and the materials are supported at a height on the platforms. The scaffolding must be erected on firm ground, the standards must be spaced at the correct intervals, the putlogs must be properly fixed and the platforms must be fully boarded and provided with guard rails and toe boards. The formwork for the concrete must be strong enough to carry the weight of the wet concrete and the workers, and it must be struck only after the concrete has gained the required strength. During the concreting operations, the workers on the platforms must use the safety belts, and the concrete must not be dropped from a great height.

The electrical work and the operation of the machines require special care. The electrical wiring must be done by qualified electricians, the connections must be properly insulated, and the earthing of the machines and the tools must be checked. The workers must not touch the live wires, and the temporary wiring on the site must be laid so that it is not damaged by the movement of the vehicles and the materials. The workers operating the machines such as the concrete mixers, the vibrators and the cranes must be trained, and the machines must be operated with the guards in position. The demolition of the old structures is also hazardous, and it must be carried out under the supervision of an experienced engineer, with the surrounding area cordoned off.

4. Quality Control in Construction

Quality control is the systematic checking of the materials and the work against the specifications, and it begins with the approval of the materials. The cement, the steel, the bricks, the sand and the aggregates must be tested before they are used, and the materials that do not conform to the specifications must be rejected. The field tests on the cement include the check of the colour, the lumps and the setting, the field tests on the aggregate include the check of the size, the shape and the cleanliness, and the tests on the steel include the check of the diameter, the weight and the bending. The laboratory tests confirm the quality by the standard methods prescribed in the IS codes.

The quality of the concrete is controlled at every stage from the mixing to the curing. The proportions of the mix must be measured accurately, the water-cement ratio must be kept within the specified limits, and the concrete must be mixed thoroughly and placed within the initial setting time. The workability of the concrete is tested by the slump test, which measures the consistency of the fresh concrete, and the strength of the concrete is tested by making the cubes and testing them in the compression testing machine at 7 days and 28 days. The cube strength at 28 days is the standard criterion, and the concrete must attain the specified characteristic strength. The curing of the concrete must be done properly, because the strength of the concrete develops only in the presence of water.

The statistical quality control uses the control charts to detect whether the process is under control. The mean chart and the range chart are plotted from the samples taken at regular intervals, and the points are compared with the upper and lower control limits. As long as the points lie within the control limits and do not show any systematic trend, the process is said to be under control, but if a point falls outside the control limits, the cause must be investigated and corrected. The control charts are used for the ready-mix concrete plants and for the large projects, where the quality of the large volume of the concrete must be maintained consistently.

4.1 Worked Numerical Examples

Example 1: In a concrete mix, the water-cement ratio is 0.45 and the cement content is 350 kg per cubic metre. Find the quantity of water required per cubic metre of concrete.

Solution: Water required = water-cement ratio x cement content = 0.45 x 350 = 157.5 litres per cubic metre.

Example 2: Concrete cubes from a mix gave 28 day strengths of 26, 28, 30 and 32 N per square millimetre. Find the mean strength of the cubes.

Solution: Mean strength = (26 + 28 + 30 + 32) / 4 = 116 / 4 = 29 N per square millimetre.

Example 3: In a slump test, the height of the concrete after the removal of the cone was 90 millimetres and the height of the cone was 300 millimetres. Find the slump of the concrete.

Solution: Slump = original height - final height = 300 - 90 = 210 millimetres. The concrete has a high slump and is very workable.

Example 4: A control chart has an upper control limit of 32 N per square millimetre and a lower control limit of 24 N per square millimetre. A sample gives a strength of 33 N per square millimetre. State whether the process is in control and the action to be taken.

Solution: Since 33 is above the upper control limit of 32, the point lies outside the control limits and the process is out of control. The cause of the high strength variation must be investigated and corrected.

5. Quick Revision Tables

Table 1: Safety Measures for Common Operations

Operation Main safety measure
Excavation Shoring or sloping of trenches above 1.5 m
Scaffolding Guard rails, toe boards and firm erection
Concreting at height Safety belts for the workers
Electrical work Insulation, earthing and qualified electricians
Crane and machine operation Trained operators and tested ropes
Demolition Supervision and cordoning of the area

Table 2: Quality Control Tests

Material / Concrete Test Purpose
Cement Field test, consistency Check quality and water demand
Aggregates Sieve analysis Check grading
Fresh concrete Slump test Measure workability
Hardened concrete Cube compression test Measure 28 day strength
Steel Bend test Check ductility

6. Mind Map

flowchart TD
    A[Construction Safety and Quality Control] --> B[Safety]
    A --> C[Quality control]
    B --> B1[Causes of accidents]
    B --> B2[General safety measures]
    B --> B3[Special operation safety]
    C --> C1[Material testing]
    C --> C2[Concrete quality control]
    C --> C3[Statistical quality control]
    B1 --> B1a[Physical causes]
    B1 --> B1b[Human causes]
    C2 --> C2a[Slump test]
    C2 --> C2b[Cube compression test]
    C3 --> C3a[Control charts]
    B3 --> B3a[Excavation and scaffolding]
    B3 --> B3b[Electrical and machines]

7. Important Diagrams (SVG)

The following diagrams show the safety measures for a deep trench and the quality control tests for concrete.

Safety Measures for a Deep Trench Sloping and shoring of sides 1.5 m + Trenches deeper than 1.5 metres must be shored or sloped. Excavated soil is kept away from the edge of the trench. Golden Rule Slope or shore every trench deeper than 1.5 metres to prevent collapse.

Quality Control of Concrete Material testing cement, steel, aggregate Fresh concrete slump test for workability Hardened concrete 28 day cube test for strength Curing water for strength development Water-cement ratio 0.45 with 350 kg cement gives 157.5 litres of water. Control charts detect whether the process is under control. Golden Rule Test materials before use, check the slump of fresh concrete and test cubes at 28 days.

8. Common Mistakes

  1. Many students think that the safety measures are needed only during the heavy operations; in fact safety is required at every stage of the work, including the finishing operations.
  2. A common error is to believe that the slump of the concrete is a measure of its strength; the slump measures only the workability of the fresh concrete.
  3. Candidates often forget that the trench deeper than 1.5 metres must be shored or sloped, and they ignore the critical depth for the collapse of the excavation.
  4. Some students confuse the water-cement ratio with the slump; the water-cement ratio controls the strength, while the slump measures the consistency.
  5. A frequent mistake is to test the concrete cubes at 7 days and accept them as the final criterion; the standard criterion is the 28 day cube strength.
  6. Many candidates think that the quality control is the checking of the finished work only; in reality the materials are tested before use and the work is supervised during execution.
  7. Students often forget that a single point outside the control limits is enough to declare the process out of control and to investigate the cause.
  8. Candidates frequently overlook the earthing and the insulation of the electrical equipment, which are among the most important electrical safety measures on the site.

9. Exam Tips

  1. Remember the critical depth of 1.5 metres, above which the excavation trenches must be shored or sloped for safety.
  2. Memorise the fact that the 28 day cube strength is the standard criterion of the quality of the hardened concrete.
  3. Learn that the slump test measures the workability of the fresh concrete, while the cube compression test measures the strength.
  4. Note that the water-cement ratio controls the strength of the concrete, and a lower water-cement ratio gives higher strength.
  5. Remember the standard protective equipment: the safety helmet, the safety shoes and the safety belts for the workers.
  6. Understand that the control charts compare the sample points with the upper and lower control limits, and a point outside the limits means the process is out of control.
  7. Recall that the quality control begins with the testing of the materials and continues through the execution and the finished inspection.
  8. Learn the safety measures for the special operations, because questions on the shoring of the trenches and the guard rails on the scaffolding appear often.

10. Conclusion

Construction safety and quality control together ensure that the project is completed without injury to the workers and with the structure safe and durable for the owners. In this chapter we have studied the causes of construction accidents, the general safety measures of fencing, protective equipment and first aid, and the special safety measures for excavation, scaffolding, concreting, electrical work and machines. We have studied the meaning and the purpose of quality control, the field and laboratory tests on the materials, the quality control of the concrete through the slump test and the 28 day cube test, and the statistical quality control with the control charts. We have also solved numerical examples on the water-cement ratio, the mean strength and the slump. The safety and the quality of the work are the final test of the entire planning and management of the project, because a project that is completed on time and within the budget is of no value if the workers are injured during construction or if the structure fails during its life. A candidate who has studied the safety rules and the quality tests of this topic completes the whole syllabus of estimation and construction management, and he is then prepared to answer the questions of this section of the examination with confidence and to apply the same principles in his professional life.