🏗️ Civil Engineering

Foundation Failure

Start MCQ Practice →

Foundation Failure

Subject: Civil Engineering Chapter: Foundation Engineering Topic: 19.9 Foundation Failure

1. Introduction

A foundation failure is the loss of support to a structure caused by the shear failure, excessive settlement or instability of the soil beneath the foundation, and it is one of the most dangerous events in civil engineering because it affects the entire structure above. Foundation failures occur when the load imposed by the foundation exceeds the bearing capacity of the soil, when excessive settlement causes distortion and cracking, when the foundation is undermined by erosion or scour, when expansive soil swells and shrinks, or when construction defects weaken the foundation. For an examination candidate, the study of foundation failures is important because questions on the modes of failure, the causes of failure and the remedial measures appear regularly, and because an understanding of failures clarifies the purpose of every design check.

The failure of a foundation can occur in the soil, in the foundation material, or in the structure above. Soil failures include general, local and punching shear failure under the footing, consolidation and immediate settlement, and the failure of slopes near the footing. Foundation material failures include the structural cracking of the footing, the bending or buckling of piles, and the tilting of walls. Structural failures caused by the foundation include the cracking of walls due to differential settlement, the tilting of chimneys and towers, and the complete collapse of a building. Many famous failures in civil engineering history have been traced to soil that was weaker than assumed, water that was not accounted for, or settlement that was underestimated.

The prevention of foundation failure depends on a thorough soil investigation, a correct evaluation of the bearing capacity and settlement, a conservative factor of safety, and careful construction. When a failure does occur, the engineer must diagnose the cause, stop the damaging process, and apply remedial measures such as underpinning, grouting, soil improvement or the installation of additional piles. This chapter explains the modes of bearing capacity failure, the common causes of foundation failures, the concept of the critical depth and liquefaction, and worked numerical problems that illustrate how inadequate factors of safety and excessive pressures lead to failure.

2. Bearing Capacity Failure Modes

The most direct cause of foundation failure is the shear failure of the soil under the footing, which occurs when the applied pressure exceeds the ultimate bearing capacity. As explained in earlier chapters, the failure takes one of three forms. General shear failure occurs in dense sand and stiff clay, with a continuous failure surface extending to the ground surface, sudden tilting of the footing and a bulge in the ground around it; it is a catastrophic failure that can collapse a structure without warning. Local shear failure occurs in loose sand and soft clay, with the failure surface confined to the zone beneath the footing and large gradual settlement. Punching shear failure occurs in very loose soil and extremely soft clay, with the footing punching vertically into the ground and almost no disturbance of the surrounding soil.

The factor of safety against bearing capacity failure is the ratio of the ultimate bearing capacity to the actual gross bearing pressure, and a foundation is considered safe when this ratio is at least about 2.5 to 3. A foundation can also fail by the tilting of an eccentrically loaded footing, when the resultant load falls outside the middle third and a portion of the base loses contact with the soil, and by the sliding of a footing subjected to large horizontal forces. In every case the remedy is either to increase the size or depth of the foundation, to improve the soil, or to reduce the applied load.

Worked Example 1

A strip footing rests on a soil whose ultimate bearing capacity is 300 kN/m2. The footing applies a gross bearing pressure of 150 kN/m2. Determine the factor of safety against bearing capacity failure.

Solution:

Factor of safety = ultimate bearing capacity / actual bearing pressure = 300 / 150 = 2.

Since the factor of safety is only 2, which is less than the recommended value of about 3, the footing is not safe against bearing capacity failure.

Worked Example 2

If the ultimate bearing capacity is 450 kN/m2 for the same footing, determine the factor of safety.

Solution:

Factor of safety = 450 / 150 = 3.

With a factor of safety of 3, the footing is safe against bearing capacity failure.

3. Settlement, Scour and Expansive Soil Failures

Excessive settlement is the most common cause of foundation failure, and it acts in two ways. Total settlement, if very large, can submerge the foundation and damage service connections, but the more dangerous effect is differential settlement, in which different parts of the structure settle by different amounts, causing the building to tilt and the walls and frame to crack. Differential settlement is produced by variations in the soil, by unequal column loads, by footings of different sizes on the same soil, and by the consolidation of a compressible clay layer that is thicker under one part of the structure than under another. The angular distortion of a building is limited to values of the order of 1/300 to 1/500, and when this limit is exceeded, the structure begins to suffer visible damage.

Scour failure occurs when flowing water removes the soil from around and below a foundation, most commonly at bridge piers and abutments in rivers. When the scour depth exceeds the depth of the foundation, the foundation is undermined and can tilt or collapse. Expansive soils, such as black cotton soil, swell when they absorb water and shrink when they dry, so a foundation on such soil heaves in the wet season and settles in the dry season, repeatedly damaging the structure; under-reamed piles are used to carry the foundation below the zone of volume change. Liquefaction is another cause of failure, occurring in loose saturated sand when earthquake shaking raises the pore water pressure to the value of the confining pressure, so that the sand loses its strength and behaves like a liquid, and the foundation sinks or floats.

Worked Example 3

The permissible angular distortion for a framed building is 1/500. Two adjacent footings are 5 m apart, and the computed differential settlement is 12 mm. Determine the angular distortion and check whether it is within the limit.

Solution:

Angular distortion = differential settlement / distance = 0.012 / 5 = 0.0024 = 1/417.

Since 1/417 is greater than 1/500, the angular distortion exceeds the permissible limit, and remedial measures are required.

Worked Example 4

If the distance between the footings of Worked Example 3 is increased to 6 m, find the new angular distortion.

Solution:

Angular distortion = 0.012 / 6 = 0.002 = 1/500.

With a spacing of 6 m, the angular distortion exactly equals the permissible limit.

4. Remedial Measures and Prevention

The prevention of foundation failure begins with a proper subsoil investigation, which reveals the nature and strength of the soil at various depths, the position of the water table and the presence of any weak layers. The bearing capacity and the settlement are then computed by the methods studied in earlier chapters, and the foundation is designed with a factor of safety of about 2.5 to 3 against shear failure and with settlements within the permissible limits. The foundations of adjacent structures should be placed at safe distances, and the bottom of a foundation should be placed below the zone of frost action and below the depth of volume change in expansive soils.

When a foundation has already failed, the remedial measures depend on the cause. Underpinning strengthens an existing foundation by extending it down to a firmer stratum; grouting injects cement or chemical grout into the soil to improve its strength; soil improvement methods such as vibro-compaction and stone columns densify loose sand; and the installation of additional piles increases the load capacity of the foundation. The cracked structure is repaired only after the foundation is stabilised, and the performance is monitored to confirm that the settlement has stopped. These remedial techniques convert a failed foundation into a safe one and are common practical topics in professional examinations.

Worked Example 5

A footing designed for a load of 400 kN is found to be undersized, and the safe bearing capacity of the soil is 100 kN/m2. Determine the required base area.

Solution:

Required base area = load / safe bearing capacity = 400 / 100 = 4 m2.

Therefore the footing must be enlarged or underpinned to provide a base area of at least 4 m2.

Worked Example 6

If the existing footing has a base area of only 3 m2, express the deficiency as a percentage.

Solution:

Deficiency = required area - existing area = 4 - 3 = 1 m2.

Percentage deficiency = (1 / 4) x 100 = 25 percent.

Therefore the existing footing is deficient by 25 percent and must be strengthened.

5. Quick Revision Tables

Table 1: Modes and Causes of Foundation Failure

Failure Mode Cause Typical Soil
General shear failure Pressure exceeds bearing capacity Dense sand, stiff clay
Local shear failure Gradual yielding beneath footing Loose sand, soft clay
Punching shear failure Vertical punching into soil Very loose sand
Differential settlement Unequal settlement of footings Variable soil strata
Scour failure Erosion by flowing water Bridge sites in rivers
Expansive soil failure Swelling and shrinking Black cotton soil
Liquefaction Pore pressure rise in earthquake Loose saturated sand

Table 2: Checks and Remedial Measures

Item Value / Method
Minimum factor of safety 2.5 to 3
Permissible angular distortion 1/300 to 1/500
Remedial measure for weak soil Underpinning
Soil improvement method Grouting, stone columns
Foundation for expansive soil Under-reamed piles
Response to liquefaction Deep piles to firm stratum
Required base area Load / safe bearing capacity

6. Mind Map

flowchart TD
    A[Foundation Failure] --> B[Bearing capacity failure]
    A --> C[Settlement failure]
    A --> D[Scour and undermining]
    A --> E[Expansive soil and liquefaction]
    B --> B1[General shear]
    B --> B2[Local shear]
    B --> B3[Punching shear]
    C --> C1[Total settlement]
    C --> C2[Differential settlement]
    C2 --> C3[Angular distortion 1/300 to 1/500]
    D --> D1[Base below maximum scour depth]
    E --> E1[Under-reamed piles]
    E --> E2[Liquefaction in earthquake]
    A --> F[Remedial measures]
    F --> F1[Underpinning, grouting]
    F --> F2[Soil improvement, extra piles]
    B1 --> G[FOS = q ult / q applied]

7. Important Diagrams (SVG)

The following diagrams show the effect of differential settlement and the modes of bearing capacity failure.

Differential Settlement of a Building Ground Left settles more Right settles less Building tilts and walls crack Angular distortion = differential settlement / distance Golden Rule Differential settlement, not total settlement, is the usual cause of damage to structures.

Remedial Measures for Foundation Failure Underpinning Deepen footing Grouting Inject cement or chemical Stone columns Densify loose sand Extra piles Increase capacity Soil replacement Remove weak soil Preload Consolidate soil Prevention: soil investigation, correct bearing capacity, adequate factor of safety, settlement within limits. Golden Rule Diagnose the cause before treating a failure: bearing, settlement, scour or soil behaviour decide the remedy.

8. Common Mistakes

  1. Many students assume that total settlement is the main danger, ignoring that differential settlement is what actually cracks structures.
  2. A frequent error is to check only the bearing capacity and neglect the settlement, which can still cause failure at low pressures.
  3. Some candidates forget that a factor of safety below about 2.5 is insufficient, and they accept FOS equal to 2 as safe.
  4. Students often confuse liquefaction with settlement, forgetting that liquefaction is a sudden loss of strength in saturated sand during earthquakes.
  5. A common mistake is to ignore the water table and scour, which are the leading causes of failure at bridge sites.
  6. Many candidates think expansive soil heaves only, but it also shrinks on drying, causing repeated cycles of damage.
  7. Some students apply underpinning when the problem is scour or liquefaction, instead of choosing the correct remedial measure.
  8. A frequent error is to compute the angular distortion using the total settlement instead of the differential settlement.

9. Exam Tips

  1. Remember the three shear failure modes and the soils in which they occur, because they are asked repeatedly.
  2. Use factor of safety = ultimate capacity / applied pressure to check safety; the minimum acceptable value is about 3.
  3. Memorise the permissible angular distortion range of 1/300 to 1/500 for structures.
  4. Link each failure cause to its remedy: bearing failure to larger footing, weak soil to underpinning, loose sand to stone columns, expansive soil to under-reamed piles.
  5. Recall that scour failure is prevented by placing the base below the maximum scour depth.
  6. Note that differential settlement is reduced by raft foundations and equal footing sizes.
  7. Remember that a soil investigation is the first and most important step in preventing foundation failure.

10. Conclusion

Foundation failure is the practical consequence of every error in bearing capacity, settlement or construction, and this chapter has surveyed its causes, modes and remedies. We have seen that bearing capacity failure takes the forms of general, local and punching shear failure, that excessive differential settlement distorts and cracks structures, that scour undermines foundations at bridge sites, and that expansive soils and liquefaction create special hazards. The worked examples have shown how to compute the factor of safety, how to evaluate the angular distortion against its permissible limit, and how to determine the required base area when a footing is undersized. The prevention of failure rests on soil investigation, correct analysis and conservative factors of safety, while the treatment of failure relies on underpinning, grouting, soil improvement and additional piles. With a complete understanding of how foundations fail, the candidate is finally ready for the concluding topic of foundation design, which combines bearing capacity, settlement and the selection of foundation type into the systematic procedure used to design a real foundation.