Subject: Civil Engineering Chapter: Geotechnical Engineering Topic: 17.10 Ground Improvement
Very often the soil available at a construction site is not strong enough or stiff enough to support the proposed structure, and the engineer must choose between three broad courses of action: design a deep foundation that transfers the load to a deeper strong stratum, remove and replace the weak soil, or improve the weak soil itself so that it becomes capable of carrying the load. The third course of action is called ground improvement or soil improvement, and it covers a wide range of techniques by which the engineering properties of the soil, its strength, stiffness, permeability and drainage, are deliberately changed to make it suitable for construction. Ground improvement is frequently the most economical solution, because it uses the material already present at the site.
Ground improvement methods work by one or more of four basic mechanisms: densification, in which the soil is compacted to reduce its void ratio; drainage and consolidation, in which the pore water is removed so that the effective stress increases; reinforcement, in which strong materials such as stone, geosynthetics or piles are introduced into the soil; and stabilisation, in which cement, lime or other additives change the properties of the soil itself. The choice of method depends on the type of soil, the depth of the weak material, the availability of plant and materials, and the cost. A technique that works well for a granular fill may be useless for a soft clay, and vice versa.
In this chapter we will study the compaction of soils, which is the densification of cohesionless soils and fills by mechanical energy, including the compaction tests and the compaction curve. We will study the consolidation and drainage methods such as preloading and sand drains or vertical drains for soft clays, and the methods of vibro-compaction, vibro-replacement and stone columns for granular soils. We will study the stabilisation of soils with lime, cement and other admixtures, and the use of geosynthetics for reinforcement, drainage and filtration. Numerical examples will show the computation of the degree of compaction and the required surcharge, because quantitative problems on compaction and preloading are common in examinations.
Compaction is the process of densifying a soil by applying mechanical energy, which expels the air from the voids and brings the soil particles closer together. Compaction increases the dry density of the soil, which in turn increases the strength, reduces the settlement and reduces the permeability of the soil. It is achieved in the field by rollers such as the smooth wheel roller, the sheep foot roller and the vibratory roller, and the choice of the roller depends on the type of soil. The laboratory test used to control field compaction is the Proctor compaction test, in which the soil is compacted in a standard mould with a standard rammer, and the test is carried out at different water contents to find the optimum water content and the maximum dry density.
The compaction curve is the graph of the dry density against the water content, and it is a characteristic inverted U-shaped curve. As the water content increases from a low value, the water lubricates the particles and the dry density increases, until a maximum is reached at the optimum moisture content; beyond the optimum water content, the excess water occupies the voids and the dry density decreases. The Proctor test is performed in two standard versions: the standard Proctor test, in which a 2.5 kg rammer falls 300 mm in a mould of volume 1000 cm3, and the modified Proctor test, in which a 4.5 kg rammer falls 450 mm, so the modified test imparts more energy and gives a higher maximum dry density at a lower optimum water content. The dry density achieved in the field is expressed as a percentage of the maximum dry density and is called the relative compaction.
Worked Example 1: In a standard Proctor test, the soil compacted in a 1000 cm3 mould with a soil mass of 1.8 kg has a water content of 12 per cent. Determine the bulk density and the dry density. Solution: Bulk density rho = mass/volume = 1.8/0.001 = 1800 kg/m3. Dry density rho d = rho/(1 + w/100) = 1800/1.12 = 1607.14 kg/m3. Hence the bulk density is 1800 kg/m3 and the dry density is about 1607 kg/m3 at a water content of 12 per cent.
Soft clay deposits are weak and highly compressible, and they cannot be compacted because the pore water cannot escape quickly from the fine pores. For such soils, the improvement is achieved by consolidation, in which the load is applied gradually and the pore water is allowed to escape, so that the effective stress increases and the soil becomes stronger and less compressible. The most direct method is preloading, in which a surcharge load, often the sand fill or the embankment material, is placed on the site before the construction, and the soil is allowed to consolidate under this load. The soil is thus compressed before the structure is built, so that the subsequent settlement of the structure is small.
The time required for consolidation depends on the drainage path, and it can be reduced dramatically by installing vertical drains, also called sand drains or prefabricated vertical drains, which are columns of sand or drainage strips installed in the clay. The vertical drains provide short horizontal drainage paths, so that the pore water has to travel only a short distance to reach the drain instead of a long distance to reach the top or bottom boundary. By the theory of consolidation, the time of consolidation is proportional to the square of the drainage path, so reducing the drainage path from, say, 10 m to 1 m reduces the consolidation time by a factor of about 100. The combination of a surcharge and vertical drains is one of the most effective and economical methods of improving thick soft clay deposits.
Worked Example 2: A soft clay layer of 8 m thickness drains on one side only. If the time required for 90 per cent consolidation is estimated at 2 years for this drainage condition, determine the time required if vertical drains reduce the effective drainage path to 1 m. Solution: The time of consolidation is proportional to the square of the drainage path. With one-way drainage the drainage path is 8 m, and the new drainage path is 1 m. Hence the new time t2 = t1 x (H2/H1)2 = 2 x (1/8)2 = 2/64 = 0.03125 years, that is, about 11.4 days. Hence the vertical drains reduce the consolidation time from 2 years to about 11 days.
For loose granular soils, the most effective improvement is vibro-compaction, in which a powerful vibrator, called a vibroflot, is inserted into the ground and the sand is densified by the vibration. The vibrator is lowered to the required depth, the sand around it is compacted by the vibrations, and the process is repeated over a grid pattern, so that the whole deposit becomes dense and its bearing capacity and resistance to liquefaction are greatly increased. In the presence of cohesive fines, the vibrator cannot compact the soil alone, and stone columns are formed instead; in the vibro-replacement method, the vibrator creates a hole, which is filled with stone in successive lifts and compacted, so that a column of dense stone is formed. The stone columns act as a composite material with the soil, carry a part of the load, and provide drainage that accelerates the consolidation of the surrounding clay.
Soil stabilisation is the improvement of the soil by mixing it with additives that change its properties. Lime stabilisation is used for clayey soils, in which the lime reacts with the clay minerals to reduce the plasticity and the swell and to increase the strength; it is effective for clays with a plasticity index greater than about 15. Cement stabilisation is used for a wide range of soils, in which the cement sets and binds the soil particles together, producing a strong and durable material; the cement content is usually between 5 and 10 per cent for most soils. Bituminous stabilisation, fly ash stabilisation and chemical stabilisation are used for particular applications such as roads and industrial fills. The stabilised soil is mixed in place by a stabiliser machine or mixed in a plant and then compacted.
The use of geosynthetics, which include geotextiles, geogrids, geomembranes and geocomposites, is a modern and growing method of ground improvement. Geotextiles separate the layers, filter the soil and drain the water; geogrids reinforce the soil by their tensile strength and interlock with the particles; and geomembranes provide an impermeable barrier. Geosynthetics are widely used in the construction of reinforced embankments, retaining walls, roads and landfills, and they have made possible the construction of structures on very weak soils that were earlier considered impossible. The selection of the ground improvement method is made after a careful study of the soil conditions, the structure, the cost and the environmental requirements.
Worked Example 3: A foundation on a loose sand deposit must have a minimum relative compaction of 95 per cent. If the maximum dry density from the modified Proctor test is 18 kN/m3, determine the minimum dry density that must be achieved in the field. Solution: Relative compaction = (field dry density / maximum dry density) x 100. Hence field dry density = 0.95 x 18 = 17.1 kN/m3. Hence the contractor must achieve a dry density of at least 17.1 kN/m3 in the field.
| Method | Mechanism | Suitable soil |
|---|---|---|
| Compaction | Densification by mechanical energy | Cohesionless soils and fills |
| Preloading | Consolidation under surcharge | Soft clays |
| Vertical drains | Shortened drainage path | Thick soft clay deposits |
| Vibro-compaction | Densification by vibration | Loose granular soils |
| Stone columns | Reinforcement and drainage | Mixed or clayey soils |
| Lime and cement stabilisation | Chemical change of soil | Clays and wide range of soils |
| Test | Rammer mass | Drop height | Mould volume | Energy |
|---|---|---|---|---|
| Standard Proctor | 2.5 kg | 300 mm | 1000 cm3 | Lower |
| Modified Proctor | 4.5 kg | 450 mm | 1000 cm3 | Higher |
| Result | Higher OMC and lower MDD for standard | |||
| Relative compaction | Field dry density / maximum dry density |
flowchart TD
A[Ground Improvement] --> B[Mechanisms]
A --> C[Compaction]
A --> D[Consolidation methods]
A --> E[Vibro methods]
A --> F[Stabilisation]
A --> G[Geosynthetics]
B --> B1[Densification]
B --> B2[Drainage and consolidation]
B --> B3[Reinforcement]
B --> B4[Chemical stabilisation]
C --> C1[Proctor test]
C --> C2[Optimum moisture content]
C --> C3[Maximum dry density]
C --> C4[Field rollers]
D --> D1[Preloading with surcharge]
D --> D2[Vertical drains - sand drains]
D --> D3[Time proportional to H squared]
E --> E1[Vibro-compaction for sands]
E --> E2[Vibro-replacement and stone columns]
F --> F1[Lime stabilisation for clays]
F --> F2[Cement stabilisation]
F --> F3[Bituminous and fly ash]
G --> G1[Geotextiles - separation, filtration]
G --> G2[Geogrids - reinforcement]
G --> G3[Geomembranes - impermeable barrier]
The following diagrams show the compaction curve and the arrangement of vertical drains for the improvement of a soft clay deposit.
Ground improvement transforms weak and unsuitable soils into materials that can safely support the structures of modern engineering, and it often does so more economically than deep foundations or soil replacement. In this chapter we have studied the four mechanisms of improvement, densification, drainage and consolidation, reinforcement and stabilisation, and the techniques that apply them. We have studied the compaction of cohesionless soils and fills with the Proctor tests, the compaction curve, the optimum moisture content and the relative compaction, and the consolidation of soft clays by preloading and vertical drains, with the square law that governs the time of consolidation. We have studied vibro-compaction and stone columns for granular and mixed soils, lime and cement stabilisation, and the modern use of geosynthetics. The worked examples have demonstrated the computation of dry density, the reduction in consolidation time and the required field dry density. With this final chapter, the entire arc of the unit, from the introduction to soil, through formation, phase relationships, index properties, classification, permeability, seepage, effective stress and exploration, to the improvement of the ground, is complete, and the candidate is equipped to answer a wide range of questions in geotechnical engineering.