Subject: Civil Engineering Chapter: Irrigation Engineering Topic: 14.6 Canals and Canal Classification
A canal is an artificial channel, generally trapezoidal in cross-section, constructed to carry water from a river, reservoir or tank to the fields where it is required. Canals form the backbone of almost every irrigation project, because they distribute the water stored by dams or diverted by weirs over large agricultural areas. A modern canal system consists of a main canal, branch canals, distributaries and minor channels, each of which carries water to progressively smaller areas. For a civil engineer, the classification of canals and the understanding of their cross-sections, beds, banks and water levels is fundamental, because the design of every canal and every canal structure depends on these basic ideas.
Canals can be classified on several bases. Depending on the source of water and the continuity of supply, they are divided into perennial canals, which flow throughout the year, and inundation canals, which carry water only during the flood season. Depending on the alignment, they are classified as contour canals, which follow the contours of the land, ridge or watershed canals, which run along the ridge or watershed line dividing two drainage basins, and side slope canals, which run at right angles to the contours on the side slopes of the valley. Depending on their function and discharge, canals are further divided into main canals, branch canals, distributaries and minors.
In this chapter we will study the different bases of canal classification, the standard canal cross-section and its parts such as the bed, berm, banks and side slopes, the important terms like FSL, bed slope and freeboard, and the way water losses and silting affect canal performance. We will also study the key numerical problem of computing the capacity of a canal from the area to be irrigated and the duty of the crop.
Based on the alignment, canals are of three main types. A contour canal is aligned nearly parallel to the contours of the country, at a suitable gradient, so that it flows along the side of the hill and commands the land on one side only; it is a canal running along the contour and hence cannot command the area on the uphill side. A ridge or watershed canal is aligned along the ridge line, which is the highest line dividing two drainage basins, and it commands land on both sides, giving the most economical layout because water can be taken on both sides. A side slope canal runs more or less at right angles to the contours, on the side slope of the valley, and it commands a narrow strip of land on the lower side while the upper side remains uncommanded.
Based on the supply of water, canals are divided into perennial and inundation canals. A perennial canal is fed by a permanent source such as a storage reservoir or a perennial river, and it flows throughout the year so that irrigation can be done in any season. An inundation canal takes off directly from a river and carries water only during the high flood period, when the river water level rises above the canal bed; such canals do not require a head regulator but they cannot supply water throughout the year. Based on the discharge and the function, the canals are divided into main canals which take off from the head works, branch canals which take off from the main canal, distributaries which take off from the branch canals, and minors or field channels which take off from the distributaries and finally deliver water to the fields.
The standard canal cross-section is trapezoidal in shape, with a flat bed and sloping sides. The principal parts of the cross-section are the bed, the side slopes, the banks, the berms and the water surface. The bed is the bottom surface of the canal over which the water flows, and the bed level is the elevation of the bed. The side slopes are the sloping sides of the canal, expressed as a ratio such as 1 in 1 or 1.5 in 1, meaning the horizontal to the vertical run of the slope. The banks are the embankments built on either side to confine the water, and the top of the bank is kept above the highest water level by an amount called the freeboard to provide a safety margin against waves and surge.
The full supply level, FSL, is the maximum designed water level in the canal at its design discharge, and the difference between the FSL and the bed level at any section is the depth of flow. The freeboard is the vertical distance between the FSL and the top of the bank, and it is usually kept between 0.5 and 1 metre depending upon the discharge. The berm is the horizontal strip of land between the toe of the bank and the top edge of the side slope, which provides stability to the bank, serves as a road for inspection and gives space for the excavated material. The bed slope is the longitudinal slope of the canal bed, which for an earthen canal is kept small to limit the velocity, and the design velocity is fixed so that it neither silts up the canal by being too low nor erodes the bed and sides by being too high.
The water that flows in a canal is subject to losses and gains. The main losses are the seepage of water through the bed and sides of the canal, which is large in porous soils and small when the canal is lined, and the evaporation from the open water surface, which depends on the climate and the width of the canal. The silting of a canal is the deposition of sediment on the bed, which reduces its capacity and may ultimately block it, while scouring is the removal of the bed material by high velocities. A canal is said to be stable when it neither silts nor scours, and the velocity of flow is the main factor controlling this stability.
The capacity of a canal is the discharge that it must carry, and it is determined from the area to be irrigated and the duty of the crop. The design discharge is obtained by dividing the area to be irrigated by the duty, and an allowance for losses is added if the discharge at the head is required. Once the discharge is known, the cross-section of the canal is fixed by choosing a suitable bed width, depth and side slope so that the resulting velocity is within the safe limits.
Worked example: A canal has to irrigate an area of 4000 hectares. The duty of water at the head of the canal is 1500 hectares per cumec and the conveyance efficiency of the canal is 80 percent. Determine the discharge at the head and the field.
Solution: 1. Discharge at the field = area / duty at field. Duty at field = 1500 / 0.80 = 1875 hectares per cumec, so discharge at field = 4000 / 1875 = 2.13 cumec. 2. Discharge at the head = discharge at field / efficiency = 2.13 / 0.80 = 2.67 cumec. 3. Alternatively, discharge at head = 4000 / (1500 x 0.80) = 4000 / 1200 = 3.33 cumec if the duty of 1500 is taken at the field; the correct interpretation must be read carefully from the question.
Worked example: A trapezoidal canal has a bed width of 6 m, a side slope of 1 in 1 and carries a discharge of 12 cumec at a depth of 1.5 m with a velocity of 0.9 m/s. Check the area of flow and discharge.
Solution: 1. Area of flow = (bed width + side slope x depth) x depth = (6 + 1 x 1.5) x 1.5 = 7.5 x 1.5 = 11.25 square metres. 2. Discharge = area x velocity = 11.25 x 0.9 = 10.125 cumec, which is less than the designed 12 cumec, so the velocity or depth must be slightly increased.
| Basis of classification | Types | Feature |
|---|---|---|
| Alignment | Contour, ridge, side slope | Ridge canal commands both sides |
| Supply | Perennial, inundation | Perennial flows all year |
| Function | Main, branch, distributary, minor | Decreasing discharge order |
| Lining | Lined, unlined | Lined has less seepage |
| Part | Definition | Typical value |
|---|---|---|
| Bed | Bottom surface of flow | Bed width 3 to 15 m |
| Side slope | Horizontal to vertical ratio | 1 in 1 to 1.5 in 1 |
| FSL | Full supply level | Max design water level |
| Freeboard | FSL to top of bank | 0.5 to 1 m |
| Berm | Strip between toe and slope | 1 to 3 m wide |
flowchart TD
A[Canals and Canal Classification] --> B[Classification by alignment]
A --> C[Classification by supply]
A --> D[Classification by function]
A --> E[Canal cross-section]
A --> F[Losses and silting]
B --> B1[Contour canal]
B --> B2[Ridge canal]
B --> B3[Side slope canal]
C --> C1[Perennial canal]
C --> C2[Inundation canal]
D --> D1[Main canal]
D --> D2[Branch canal]
D --> D3[Distributary]
D --> D4[Minor or field channel]
E --> E1[Bed, banks, berms]
E --> E2[FSL and freeboard]
E --> E3[Side slopes and bed slope]
F --> F1[Seepage and evaporation]
F --> F2[Silting and scouring]
The following diagrams show the canal alignment types and the canal cross-section.
Canals are the distribution arteries of an irrigation project, and their classification and cross-sectional design form a large part of the irrigation engineering syllabus. In this chapter we have studied the classification of canals by alignment into contour, ridge and side slope canals, by supply into perennial and inundation canals, and by function into main canals, branch canals, distributaries and minors. We have also examined the standard trapezoidal cross-section with its bed, side slopes, banks, berms, full supply level and freeboard, and the problems of seepage, evaporation, silting and scouring that affect canal performance. The capacity of a canal is computed from the area to be irrigated and the duty of the crop, as shown in the worked examples. These ideas lead directly into the next chapter on canal design, where the cross-section is dimensioned so that the canal neither silts nor scours, and they are also used when designing the head works and canal structures of an irrigation project.
Worked example: A distributary has to supply water for 3000 hectares of paddy land with a duty of 1000 hectares per cumec. The length of the distributary is 8 km and the seepage loss is 1 cumec per 1000 hectares of wetted area. Find the discharge at the head of the distributary.
Solution: 1. Discharge required at the tail = 3000 / 1000 = 3 cumec. 2. Wetted area can be approximated from the length and cross-section; taking the total loss as 1 cumec over the full length gives an approximate total loss of 1.2 cumec for the reach, so discharge at head = 3 + 1.2 = 4.2 cumec. In practice the loss is computed from the exact wetted perimeter and length.