Subject: Civil Engineering Chapter: Public Health Engineering Topic: 16.2 Sewerage Systems
A sewerage system is the entire network of pipes, channels and appurtenances by which the waste water of a town is collected, carried and finally disposed of after suitable treatment. While a sewer is only the individual pipe or conduit that carries the waste water, sewerage is the complete system that includes house drains, lateral sewers, branch sewers, mains, pumping stations and the treatment plant at the end. For a civil engineering candidate appearing in competitive examinations, sewerage systems are a high-yield topic, because questions on the types of sewers, the types of sewerage systems, the shapes of sewers and the sections of a conventional sewer are asked repeatedly.
A sewerage system must be designed with two separate kinds of flow in mind: the dry weather flow, which is the waste water produced by the population during normal dry periods, and the storm water flow, which is the rain water that runs off the streets, roofs and open ground. The fundamental decision in planning is whether these two flows should be carried in one common sewer or in two separate sewers, and this decision leads directly to the classification of sewerage systems into the combined system, the separate system and the partially separate system.
In this chapter we will study the types of sewerage systems and their merits and demerits, the types and shapes of sewers commonly used, the important terms such as dry weather flow, storm water flow and time of concentration, and the estimation of sewage quantity by rational and empirical methods. Numerical problems on the computation of peak sewage flow and on the rational formula for storm water are an important part of this topic, and they are presented with fully worked solutions.
The separate system is the system in which two sets of pipes are laid: one set, called the sanitary sewers, carries the sanitary sewage consisting of excreta and sullage, and the other set, called the storm water drains, carries the storm water. The sanitary sewers are designed for the dry weather flow only and are laid with proper slopes to keep the velocity self-cleansing, while the storm water drains are larger and carry only rain water. The separate system is preferred in modern towns because the sanitary sewage, which requires costly treatment, is not diluted by storm water, so the treatment plant can be small, and the storm water, which is comparatively clean, can be discharged directly into natural streams without treatment.
The combined system is the system in which a single sewer carries both the sanitary sewage and the storm water in the same pipe. Its chief advantage is economy, because only one sewer is laid in each street, and it is convenient for towns where the rainfall is heavy and where the streets are narrow. Its chief disadvantage is that a large quantity of storm water must be treated at the plant during rains, which makes the treatment plant large and costly, and if the treatment plant is overloaded, untreated sewage may have to be bypassed into the stream. The partially separate system is a compromise in which the storm water from roofs and paved areas is admitted into the sanitary sewer while the storm water from the unpaved ground is carried in separate open drains.
The selection of a system depends on local conditions. Where rainfall is light, where the water table is high, where land is costly and where roads are narrow, the separate system is generally preferred. The separate system also allows the sewers to be laid at smaller sizes because the flow is smaller, and it avoids the problem of treating huge volumes of storm water. In India the separate system is normally adopted, and the sewage is treated at a treatment plant before disposal, while storm water is led to the nearest stream or storm water drain.
Sewers are made of many materials. Stoneware or vitrified clay sewers are used for small sizes up to about 450 mm diameter, because they are resistant to the corrosive action of sewage and are cheap, but they are brittle. Cast iron sewers are used for pumping mains and for large-size sewers under heavy traffic and pressure, because they are strong and can withstand internal pressure, though they are costly. Steel sewers are used for large crossing of rivers and for force mains, while asbestos cement and reinforced concrete sewers are used for large diameters, with reinforced concrete being the most common material for big sewers in India. The most important requirement of a sewer material is that it must be resistant to corrosion and to the abrasive action of the sewage, because sewage is often acidic and carries grit and sand.
The shape of the sewer is governed by the hydraulic requirement that it should carry the designed flow at the designed velocity and by the structural requirement that it should be able to resist the load of the earth above it. The circular section is the most common shape because, for a given area, the circular section has the maximum hydraulic mean depth and the minimum wetted perimeter, and it is structurally the strongest shape against external loads. Egg-shaped or oval sewers are used for combined sewers where the flow varies widely, because at low flow the narrow bottom part maintains a good depth and self-cleansing velocity. Rectangular and horse-shoe sections are used for large sewers and culverts, and the parabolic and semi-elliptical sections are sometimes used for large storm water drains.
Every sewer in a separate system must be capable of carrying the dry weather flow and also the peak flow. The dry weather flow is the sewage that flows in the sewer during dry periods, and it is estimated as about 80 percent of the water supplied, because the remaining 20 percent is consumed, evaporated or lost in leakage. In designing a sewer, the maximum discharge for which the sewer is designed is obtained by applying the peak factor, which is the ratio of the maximum flow to the average flow; this peak factor decreases as the size of the sewer increases, and it is usually taken as 2 for large sewers, 2.5 for medium sewers and 3 for small laterals.
The quantity of storm water reaching a sewer is estimated by the rational formula, which is one of the most important formulas of this chapter. The rational formula is:
Q = C x I x A
where Q is the peak rate of runoff in cubic metres per second, C is the coefficient of runoff, I is the intensity of rainfall in metres per hour and A is the catchment area in square metres.
Problem: A catchment area of 20 hectares has a runoff coefficient of 0.6. If the intensity of rainfall for the time of concentration is 40 mm per hour, find the peak storm water runoff in cubic metres per second.
Solution: A = 20 hectares = 20 x 10,000 = 200,000 square metres. I = 40 mm/hour = 0.04 m/hour. Q = C x I x A = 0.6 x 0.04 x 200,000 = 4800 cubic metres per hour = 4800/3600 = 1.33 cubic metres per second.
Answer: The peak runoff is 1.33 cubic metres per second.
The time of concentration is the time required for the rain water from the farthest point of the catchment to reach the sewer outlet, and it is made up of the inlet time, which is the time for overland flow to reach the sewer, and the time of flow in the sewer. The intensity of rainfall for use in the rational formula must be taken for a duration equal to the time of concentration, because a storm of short duration on a small catchment produces a higher rate of runoff per unit area.
For the design of a sanitary sewer, the maximum discharge is computed as the product of the average flow, the peak factor and the allowance for infiltration of ground water. For example, if the average sewage flow of a small town is 100 litres per second and the peak factor is 3, the design discharge becomes 300 litres per second, to which a small allowance for infiltration is added. The sewer is then sized so that it flows partly full at the average flow and nearly full at the peak flow, and so that the velocity remains between the minimum self-cleansing velocity and the maximum limiting velocity.
| Feature | Separate system | Combined system | Partially separate |
|---|---|---|---|
| Number of sewers | Two | One | Two, partly combined |
| Treatment plant size | Small | Large | Medium |
| Storm water treated | No | Yes | Partly |
| Cost | High | Low | Moderate |
| Suitability | Modern towns | Narrow streets, heavy rain | Compromise scheme |
| Material | Size range | Main property | Use |
|---|---|---|---|
| Stoneware / vitrified clay | Up to 450 mm | Resists corrosion | Small house and lateral sewers |
| Cast iron | Medium to large | Strong, resists pressure | Pumping mains, under pressure |
| Steel | Large | Very strong | Force mains, river crossings |
| RCC | Large | Strong in compression | Large municipal sewers |
| Asbestos cement | Small to medium | Light, smooth | Drainage pipes |
flowchart TD
A[Sewerage Systems] --> B[Types of systems]
A --> C[Types of sewers]
A --> D[Shapes of sewers]
A --> E[Design flow estimation]
B --> B1[Separate system]
B --> B2[Combined system]
B --> B3[Partially separate system]
C --> C1[Stoneware and RCC]
C --> C2[Cast iron and steel]
C --> C3[Asbestos cement]
D --> D1[Circular - most common]
D --> D2[Egg shaped for combined]
D --> D3[Rectangular and horse shoe]
E --> E1[Dry weather flow]
E --> E2[Peak factor]
E --> E3[Rational formula Q = C I A]
B1 --> F[Two sewers, small plant]
B2 --> G[One sewer, large plant]
E3 --> H[Time of concentration]
The following diagrams show the layout of the separate sewerage system and the cross-sections of the common sewer shapes.
Sewerage systems provide the physical means by which the sanitary goals of the previous chapter are achieved, because no town can be kept clean without a properly planned network of pipes. In this chapter we have studied the three types of sewerage systems, the separate, the combined and the partially separate systems, together with their relative merits, and we have seen why the separate system is generally adopted in modern Indian towns. We have examined the materials and shapes of sewers, with particular attention to the circular section which dominates sewer design, and we have learned to estimate storm water runoff by the rational formula and sewage flow by the dry weather flow and peak factor approach. Numerical examples on both runoff and peak flow computation have been worked out, so that the candidate can solve the quantitative questions of this topic without hesitation. With these foundations in place, the next logical step is the detailed hydraulic design of the sewer itself, which is taken up in the following chapter on sewer design.