🏗️ Civil Engineering

20.5 Leveling

Start MCQ Practice →

20.5 Leveling

Subject: Civil Engineering Chapter: Surveying Topic: 20.5 Leveling

1. Introduction

Leveling is that branch of surveying which deals with the determination of the relative heights or elevations of points on the earth's surface, and with the establishment of points at given heights. While other surveys determine the horizontal positions of points, leveling determines their vertical position, so that a complete three-dimensional picture of the ground is obtained. Leveling is the most important surveying operation for civil engineers because the design of roads, railways, canals, dams, buildings and drainage schemes all depend on the elevations of the ground and the gradients to be adopted. For a competitive examination candidate, leveling is a high-yield topic because questions on the height of instrument, reduced level, bench marks, rise and fall methods, and the types of leveling instruments appear frequently in every paper.

The basic principle of leveling is to establish a horizontal line of sight and to measure the vertical distances from this line to the points whose elevations are required. A level, which gives a horizontal line of sight through its telescope, is set up on a tripod, and readings are taken on vertical staffs held at the points. The vertical distance from the line of sight to a point on the ground is the staff reading, and by adding or subtracting these readings the elevations of the points are computed. The reference surface to which all elevations are referred is called the datum, and in India this is mean sea level at Karachi, as adopted by the Survey of India; the reduced level of a point is its height above this datum.

The difference of level between two points is the vertical distance between the horizontal planes through the two points. If the reduced level of one point is known and the difference of level to a second point is measured, the reduced level of the second point is obtained. Leveling is therefore a straightforward extension of the principle of a horizontal line of sight, and the accuracy of the result depends on the instrument, the staff, the care in reading, and the method of booking. In this chapter we will study the level, the staff, the terms used in leveling, the methods of computing reduced levels, the types of leveling, the sources of error, and the numerical problems that appear in examinations.

2. Instruments and Terms Used in Leveling

The level is the fundamental instrument of leveling, and the dumpy level is the most common type. It consists of a telescope with a level tube attached, mounted on a tripod through a vertical spindle, and it can be levelled with foot screws. The telescope contains an eyepiece, an objective, a diaphragm with cross hairs, and internal focusing; the line of collimation is the imaginary line joining the intersection of the cross hairs and the optical centre of the objective, and it is the line of sight of the level. The dumpy level is so named because it is short and robust, and its line of collimation remains fixed when the telescope is rotated. The wye or Y level carries the telescope in two y-shaped supports, while the tilting level has a screw to tilt the telescope slightly for accurate setting.

The leveling staff is a rectangular wooden or aluminium rod, about 3 to 4 metres long, graduated in metres, decimetres and centimetres, with alternate sections in black and white or red and white, and read directly against the horizontal cross hair. The staff may be self-reading, in which the surveyor reads the graduated staff directly through the telescope, or target staff, in which a movable target is fixed by the staffman at the position indicated by the surveyor. The staff is held vertically by the staffman, resting on a peg or on the ground, and its zero reading corresponds to the point on which it rests. The staff reading is the vertical distance from the ground point to the line of sight.

The important terms of leveling are the bench mark, the datum, the reduced level, the height of instrument, the back sight, the fore sight, and the intermediate sight. A bench mark is a fixed point of known reduced level, established by the Survey of India or by the engineer, and it is used as the starting point of a leveling operation; the Great Trigonometrical Survey bench marks are the highest grade, followed by permanent bench marks and temporary bench marks. The height of instrument or height of the plane of collimation is the reduced level of the line of sight. The back sight is the first staff reading taken at a known point after setting up the level, the fore sight is the last reading taken at a point of unknown elevation before moving the level, and the intermediate sight is any reading taken between the back sight and the fore sight.

3. Methods of Computing Reduced Levels

There are two methods of computing the reduced levels of points: the height of instrument method and the rise and fall method. In the height of instrument method, also called the collimation method, the reduced level of the line of sight is first found by adding the back sight reading to the reduced level of the bench mark. The reduced level of any point is then obtained by subtracting its staff reading from the height of instrument. When the level is shifted, a new height of instrument is computed from the last fore sight, which is then treated as a back sight on a point of known reduced level. This method is quick and is used when many intermediate sights are taken from one setting.

In the rise and fall method, the difference between successive staff readings is computed, and the difference is entered as a rise if the following reading is less than the preceding one, or as a fall if the following reading is greater. The reduced level of each point is then found by adding the rise to, or subtracting the fall from, the reduced level of the preceding point. The rise and fall method is more accurate and self-checking, because the sum of the back sights minus the sum of the fore sights must equal the sum of the rises minus the sum of the falls, and also must equal the difference between the first and the last reduced levels. This check catches arithmetical mistakes immediately.

A simple example of the height of instrument method: The reduced level of a bench mark is 100.000 m, and the back sight on it is 1.250 m, so the height of instrument is 100.000 + 1.250 = 101.250 m. If an intermediate staff reading of 2.000 m is taken on a point A, the reduced level of A is 101.250 - 2.000 = 99.250 m. If a fore sight of 0.750 m is then taken on point B and the level is moved, the new height of instrument after a back sight of 1.500 m on B is computed as the reduced level of B, which is 101.250 - 0.750 = 100.500 m, plus 1.500, giving 102.000 m.

Worked example: The following readings were taken with a dumpy level: back sight on a bench mark of reduced level 100.000 m is 1.500 m, intermediate sight on point A is 2.200 m, fore sight on point B is 0.800 m. Compute the reduced levels of A and B.

Solution: Height of instrument = 100.000 + 1.500 = 101.500 m. Reduced level of A = 101.500 - 2.200 = 99.300 m. Reduced level of B = 101.500 - 0.800 = 100.700 m. The check is that the difference of level between A and B is 100.700 - 99.300 = 1.400 m, which equals the difference in the readings 2.200 - 0.800 = 1.400 m.

4. Types of Leveling, Contouring and Errors

Leveling is classified according to the purpose and the method of observation. Simple leveling is the operation of determining the difference of level between two points when the level is set up once. Differential leveling is used when the points are far apart and many settings of the level are required, with a series of back sights and fore sights. Profile leveling is used to determine the elevations of points along a line, such as the centre line of a road, and it is accompanied by cross leveling to determine the elevations across the line. Reciprocal leveling is used to find the difference of level across a wide river or deep valley, where the level is set up on both banks in turn and readings are taken both ways to eliminate the errors of curvature and refraction.

Fly leveling is the operation of checking a series of bench marks by running a level line of quick survey between them, without taking intermediate sights. Check leveling is the leveling carried out to verify a previously done leveling, and it is always run in the opposite direction to the original work. Precise leveling is used for the highest accuracy in geodetic work, using precise instruments and special methods. Trigonometric leveling determines the difference of level by measuring the vertical angle and the distance, instead of by direct staff readings. The purpose of classification is to select the correct procedure and the expected accuracy for each kind of work.

The errors in leveling arise from the instrument, the staff, the observer and the earth's curvature and refraction. The instrumental errors include the collimation error, in which the line of sight is not truly horizontal, the imperfect adjustment of the bubble, and the wrong focusing of the telescope. The personal errors include the incorrect holding of the staff, the careless reading of the staff, and the wrong booking of the readings. The natural errors include the effects of curvature of the earth and atmospheric refraction, which are eliminated in reciprocal leveling, and the settling of the instrument or the staff. The correct length of sight, the careful adjustment of the instrument, and the repetition of readings with the staff held on a peg all reduce these errors.

Worked example: In reciprocal leveling across a river, the staff readings from level set up on bank A were 1.100 m on A and 2.400 m on B, and from bank B the readings were 1.050 m on A and 2.350 m on B. Find the true difference of level between A and B.

Solution: From bank A, the difference is 2.400 - 1.100 = 1.300 m. From bank B, the difference is 2.350 - 1.050 = 1.300 m. Since both readings give the same value, the curvature and refraction errors have been eliminated, and the true difference of level between A and B is 1.300 m.

5. Quick Revision Tables

Table 1: Terms Used in Leveling

Term Meaning
Datum Reference surface for elevations, mean sea level
Bench mark Fixed point of known reduced level
Reduced level Height of point above datum
Height of instrument Reduced level of line of sight
Back sight First reading on a known point
Fore sight Last reading before moving the level
Intermediate sight Reading between back sight and fore sight

Table 2: Leveling Methods and Errors

Item Details
Height of instrument method Add BS to RL, subtract staff reading
Rise and fall method Compare successive readings, self-checking
Differential leveling Multiple settings for distant points
Reciprocal leveling Across rivers, eliminates curvature and refraction
Curvature error Line of sight falls below true horizontal
Refraction error Bends the line of sight, opposite to curvature
Collimation error Line of sight not truly horizontal

6. Mind Map

flowchart TD
    A[Leveling] --> B[Principle - horizontal line of sight]
    A --> C[Instruments]
    A --> D[Terms]
    A --> E[Methods]
    A --> F[Types]
    A --> G[Errors]
    C --> C1[Dumpy level]
    C --> C2[Staff]
    D --> D1[Bench mark]
    D --> D2[Reduced level]
    D --> D3[Height of instrument]
    E --> E1[Height of instrument method]
    E --> E2[Rise and fall method]
    F --> F1[Differential leveling]
    F --> F2[Reciprocal leveling]
    F --> F3[Profile leveling]
    G --> G1[Collimation error]
    G --> G2[Curvature and refraction]

7. Important Diagrams (SVG)

The following diagrams show the principle of leveling with the height of instrument and the method of reciprocal leveling across a river.

Principle of Leveling - Height of Instrument Horizontal line of sight Level Staff reading 2.000 m Ground BS 1.250 m Datum (mean sea level) BM RL 100.000 m Golden Rule Reduced level = height of instrument minus staff reading, where HI = BM + back sight.

Reciprocal Leveling Across a River River Wide water body Level on bank A Sight to B 2.400 m Sight to A 1.100 m level of line of sight Bank A staff Bank B staff Sights taken from both banks eliminate curvature and refraction errors. Golden Rule Use reciprocal leveling across rivers so that curvature and refraction errors cancel out.

8. Common Mistakes

  1. Many students subtract the back sight instead of adding it; the height of instrument is the bench mark reduced level plus the back sight reading.
  2. A frequent error is to add the fore sight to find the reduced level; the reduced level of a point is the height of instrument minus its staff reading.
  3. Some candidates forget to check the arithmetic in the rise and fall method; the sum of rises minus the sum of falls must equal the last reduced level minus the first.
  4. Students often hold the staff in a tilted position; the staff must be held perfectly vertical, otherwise the reading is too large.
  5. A common mistake is to neglect the correction for curvature and refraction in long sights; these errors become significant beyond about 100 metres.
  6. Many candidates move the level before recording the fore sight; the fore sight must be taken on the last point before the instrument is shifted.
  7. Students confuse the intermediate sight with the fore sight; the intermediate sight is taken at a point of unknown elevation between the back sight and the fore sight.
  8. Some candidates use an ordinary level for precise geodetic work; precise leveling requires precise instruments and special procedures.

9. Exam Tips

  1. Master the height of instrument method first, because it is the quickest for multiple intermediate sights and is the most commonly tested.
  2. Remember the arithmetic check of the rise and fall method: sum of back sights minus sum of fore sights equals sum of rises minus sum of falls equals the difference of the first and last reduced levels.
  3. Know the meaning of bench mark types: Great Trigonometrical Survey bench marks, permanent bench marks and temporary bench marks.
  4. Remember that reciprocal leveling is used across wide rivers to eliminate curvature and refraction errors.
  5. Note that the staff reading is smaller at a higher point and larger at a lower point, so a rise corresponds to a smaller following reading.
  6. Learn that the datum in India is mean sea level at Karachi, which is a frequently asked fact.
  7. Remember the order of readings at a shifting level: back sight, intermediate sights, fore sight, then move and take a new back sight.

10. Conclusion

Leveling is the vertical counterpart of all horizontal surveying, and it supplies the elevations without which no civil engineering structure can be designed or constructed. In this chapter we have studied the level and the staff, the terms of leveling such as bench mark, datum, reduced level, height of instrument, back sight, fore sight and intermediate sight, and the two standard methods of computing reduced levels, namely the height of instrument method and the rise and fall method. We have examined the different types of leveling, including simple, differential, profile, cross, fly and reciprocal leveling, and the errors that arise from the instrument, the observer, and the curvature and refraction of the earth. We have also solved worked examples on computing reduced levels and on reciprocal leveling across a river. These methods and their checks are examined repeatedly in competitive papers, and they are the direct basis of contouring, which is the next topic. By practising the booking and the arithmetic checks, a candidate gains the accuracy and speed needed to score well in leveling questions.