Subject: Civil Engineering Chapter: Transportation Engineering Topic: 22.2 Highway Alignment
The alignment of a highway is the position or course of the centre line of the road on the ground, defined in both the horizontal and vertical planes. The horizontal alignment consists of the straight portions and the horizontal curves of the road, while the vertical alignment consists of the gradients and the vertical curves. Choosing the correct alignment is one of the most important decisions in highway engineering, because once the alignment is fixed, its correction at a later stage becomes extremely difficult and costly, and the alignment determines the construction cost, the maintenance cost, the vehicle operating cost and the safety of the entire project.
A good alignment is judged against four broad requirements: it must be short, easy, safe and economical. A short alignment minimises the length of the road and hence the cost of construction, but the shortest alignment on paper may not be the most economical when terrain, land value and cost of structures are considered. An easy alignment means that the road should have easy grades and gentle curves so that vehicles can travel at high speeds with comfort and safety. A safe alignment avoids areas prone to flooding, land slides and excessive gradients, and an economical alignment balances the initial cost, the annual maintenance cost and the operating cost so that the total cost over the life of the road is a minimum.
In this chapter we will study the requirements of an ideal alignment, the factors that control the selection of alignment, the procedure adopted for fixing the alignment of a new highway, and the special considerations for hill roads. The emphasis is on examination-oriented facts and the application of gradient standards to numerical problems.
The ideal alignment must be short, easy, safe and economical. Shortness means that the distance between the terminal points should be as small as possible, which reduces the length of the road, the time of travel and the cost of construction. Easiness means that the gradients should be within the permissible limits and the curves should have adequate radii, so that drivers can maintain reasonable speeds without strain. Safety requires that the alignment should avoid steep hills, waterlogged areas, flood-prone zones and unstable soil, and should provide good sight distance. Economy means that the total cost, comprising the cost of construction, the cost of maintenance and the cost of vehicle operation, should be the minimum; it is not enough that only the initial construction cost is low.
The selection of alignment is controlled by several factors, the first of which is the obligatory points through which the alignment must pass or which it must avoid. Obligatory points are of two types: points that control the alignment, such as intermediate towns, bridges across rivers, the crossing of railway lines and mountain passes, and points that must be avoided, such as religious structures, graves, costly agricultural land, waterlogged areas and unstable slopes. The shorter and more direct alignment between two fixed obligatory points is generally preferred unless it is too costly.
The next group of factors includes the traffic flow and the geometric design requirements, the economy of construction and maintenance, and the environment. The alignment should be chosen so that the road serves the maximum population with the minimum length, and the geometric standards such as design speed, ruling gradient, radius of horizontal curves and sight distance govern the geometric feasibility of an alignment. The cost of land, earthwork, bridges and drainage works determines the economic feasibility, and in hill areas the stability of slopes, the possibility of land slides and the climate also influence the choice of the alignment.
The vertical alignment of a highway consists of gradients and vertical curves. The gradient is the rate of rise or fall of the road surface along its length, expressed as a ratio such as 1 in 30, which means that the road rises by 1 unit for every 30 units of horizontal distance. The controlling gradient is the ruling gradient, which is the maximum gradient that is normally permitted in a design so that heavy vehicles can climb the grade at a reasonable speed. For plain and rolling terrain the ruling gradient is 1 in 30, while for mountainous terrain it is 1 in 20.
The limiting gradient is a steeper gradient that may be adopted in exceptional situations where the ruling gradient would make the construction very costly, but it should be avoided as far as possible. The limiting gradient is 1 in 20 in plain terrain and 1 in 16.7 in mountainous terrain. The exceptional gradient is an even steeper gradient allowed only over short stretches, of about 100 metres, and it is 1 in 15 in plain terrain and 1 in 12.5 in mountainous terrain. The minimum gradient is adopted for drainage in flat terrain; a minimum gradient of about 1 in 500 is generally provided on flat ground so that water can drain off the road surface and side drains.
Solved Problem 1: A hill road rises from a chainage where the elevation is 820 m to a point 2.0 km away where the elevation is 880 m. Determine the gradient. Solution: Rise = 880 - 820 = 60 m, horizontal distance = 2000 m. Gradient = 60/2000 = 1 in 33.3. Since this is flatter than the ruling gradient of 1 in 20 for mountainous terrain, it is acceptable.
Solved Problem 2: The ruling gradient of a road in plain terrain is 1 in 30. A vertical curve of 120 m length connects a grade of 1 in 30 rising to a grade of 1 in 40 falling. Find the difference of grade. Solution: Grade change = (1/30) - (-1/40) = 1/30 + 1/40 = (4 + 3)/120 = 7/120 = 0.0583, which is 5.83 percent. The total grade change is 5.83 percent over the 120 m vertical curve.
The alignment of a new highway is fixed through a systematic procedure consisting of map study, reconnaissance survey, preliminary survey and detailed survey. The first step is the study of the available maps, such as the survey of India toposheets, to decide the possible routes between the terminal points and to identify the obligatory points, the terrain and the natural obstacles along each route. The next step is the reconnaissance survey, in which the possible routes are examined on the ground or from the air to reject those that are obviously unsuitable and to select a few feasible routes for detailed investigation.
The preliminary survey is carried out with instruments to study the selected routes in detail; its purpose is to collect the topographical data and to compare the routes with respect to length, alignment, gradients, earthwork, drainage, bridges and cost so that the best route can be chosen. The final step is the detailed survey, also called the location survey, in which the centre line of the finally selected route is set out on the ground, levels are taken along it, cross-sections are recorded, and all the details required for preparing the drawings and estimates are collected. Bench marks and reference points are established so that the alignment can be reproduced at the time of construction.
For hill roads, alignment is usually kept along the ridge or along the valley, avoiding unstable slopes and land-slide zones, and the alignment is so chosen that the gradients do not exceed the permissible values. For roads in waterlogged areas, the alignment is taken along the highest ground available, and in snow-bound areas the sunny side of the slope is preferred. The final alignment represents a compromise between the straight-line distance, the obligatory points, the geometric standards, the cost and the safety, and no single factor alone decides the route.
| Type of gradient | Plain and rolling terrain | Mountainous terrain |
|---|---|---|
| Ruling gradient | 1 in 30 | 1 in 20 |
| Limiting gradient | 1 in 20 | 1 in 16.7 |
| Exceptional gradient | 1 in 15 | 1 in 12.5 |
| Minimum gradient | 1 in 500 (for drainage) | depends on terrain |
| Step | Name | Purpose |
|---|---|---|
| 1 | Map study | Identify possible routes and obligatory points |
| 2 | Reconnaissance survey | Examine routes on the ground, reject unsuitable ones |
| 3 | Preliminary survey | Compare routes by length, cost and gradient |
| 4 | Detailed survey | Set out centre line, collect data for design |
flowchart TD
A[Highway Alignment] --> B[Horizontal alignment]
A --> C[Vertical alignment]
A --> D[Controlling factors]
A --> E[Survey procedure]
B --> B1[Straights]
B --> B2[Horizontal curves]
C --> C1[Gradients]
C --> C2[Vertical curves]
D --> D1[Obligatory points]
D --> D2[Traffic and geometric design]
D --> D3[Economy]
D --> D4[Environment]
E --> E1[Map study]
E --> E2[Reconnaissance]
E --> E3[Preliminary survey]
E --> E4[Detailed survey]
C1 --> F[Ruling gradient 1 in 30]
C1 --> G[Limiting gradient 1 in 20]
C1 --> H[Exceptional gradient 1 in 15]
F --> I[Heavy vehicles can climb at reasonable speed]
The following diagrams show the relationship between the gradients used in vertical alignment and the sequence of surveys followed in fixing the alignment of a new road.
The alignment of a highway is the single most important decision in the planning of a road project because it fixes the length, the cost and the safety of the road for its entire life. In this chapter we have studied the four requirements of an ideal alignment, namely that it must be short, easy, safe and economical, and we have examined the factors that control the selection of alignment, particularly the obligatory points, the traffic and geometric requirements, the economy and the environment. The vertical alignment has been described through the ruling, limiting, exceptional and minimum gradients, and the numerical examples have shown how the gradient is computed and checked against the standards. The systematic procedure of map study, reconnaissance, preliminary survey and detailed survey has been explained, along with the special considerations for hill roads and waterlogged areas. Since the alignment fixes the geometric design parameters, this knowledge forms the natural bridge to the next chapter, in which the width, superelevation, sight distance and curves of the highway are designed.
(End of file - total 165 lines)