1. Introduction

Before any traffic facility can be planned, designed or improved, reliable data about the existing traffic must be collected, and this is the purpose of traffic studies and surveys. A traffic study is the systematic collection, analysis and interpretation of data relating to the movement of vehicles and pedestrians on a road network, and it forms the factual basis for geometric design, capacity analysis, signal design, road improvement and accident prevention. Every recommendation in traffic engineering is only as good as the traffic data on which it is based, so the methods and interpretation of traffic studies are given great importance in examinations.

The main studies are the volume studies, which count how many vehicles use a road; the speed studies, which measure how fast they travel; the speed and delay studies, which measure the journey time and the delays; the origin and destination studies, which find where the traffic comes from and where it is going; the parking studies, which measure the demand for parking; and the accident studies, which analyse the causes and patterns of road accidents. Each study has a definite objective and a set of standard techniques of measurement and analysis.

In this chapter we will study the objectives, methods and applications of the most important traffic studies, and we will learn the computations that convert the raw counts into usable quantities such as the average annual daily traffic, the peak hour factor, the average spot speed and the accident rate. Numerical problems on these computations are very common in competitive examinations, so each calculation is illustrated with a worked example.

2. Traffic Volume Studies

Traffic volume is the number of vehicles passing a given point of a road in unit time, and the volume study is the most fundamental of all traffic studies. The volume data are required for the design of pavement thickness, the design of intersections, the justification of traffic signals, the planning of one-way systems, and the computation of the capacity of a road. The counting may be done manually by observers using tally sheets, or mechanically by automatic counters such as the pneumatic tube counter, the loop detector and the video camera; manual counting gives the classified count with the vehicle types, while automatic counting gives the total volume continuously.

The volume at a point varies with the time of day, the day of the week and the season, so a single hour count is not representative. The average annual daily traffic is the total volume passing a point in a whole year divided by 365, and it is used for pavement design and economic analysis. The average daily traffic is the volume in a specified day, the average weekday traffic and average weekend traffic are computed separately for design, and the design hourly volume is the hourly volume used for design, commonly the 30th highest hourly volume of the year. The directional distribution and the temporal distribution of volume are shown by volume diagrams and by the percentage of vehicles in the peak hour.

The peak hour factor is the ratio of the peak hour volume to four times the peak fifteen-minute volume within that hour, and it is a measure of how concentrated the traffic is within the peak hour. A peak hour factor close to 1.0 means that the flow is uniform through the hour, while a low value means that the traffic is concentrated in a short period. The results of the volume study are presented as traffic volume maps, intersection flow diagrams and time flow charts, which give the designer a complete picture of the traffic demand.

Solved Problem 1: The traffic counts on a road over four representative days of a year are 9500, 8200, 8600 and 8900 vehicles. If the four-day average is raised by an expansion factor of 1.20 to give the average daily traffic, find the ADT and the AADT if seasonal variation is negligible. Solution: Average of the four counts = (9500 + 8200 + 8600 + 8900)/4 = 35200/4 = 8800 vehicles. ADT = 8800 x 1.20 = 10,560 vehicles. With negligible seasonal variation, AADT is taken equal to the ADT of 10,560 vehicles per day.

Solved Problem 2: During a peak hour the total volume is 2400 vehicles and the highest fifteen-minute volume is 700 vehicles. Find the peak hour factor. Solution: PHF = 2400 / (4 x 700) = 2400/2800 = 0.857.

3. Speed Studies and Speed and Delay Studies

The speed of vehicles is a key indicator of the level of service of a road, and speed studies are conducted to establish the design speed, to check the adequacy of speed limits, to locate the points of congestion and to study the speed trends over time. The spot speed study measures the speeds of individual vehicles at a selected point of the road, either by the enoscope or by the radar speed meter, and the data are plotted as a frequency distribution or a cumulative speed distribution curve. The speed at which 85 percent of the vehicles travel at or below, called the 85th percentile speed, is used to set the speed limit, because it represents the speed adopted by the majority of drivers in free-flowing conditions.

The time mean speed is the arithmetic mean of the spot speeds of all the vehicles passing a point, while the space mean speed is the harmonic mean of the spot speeds, and it is the space mean speed that is used in the fundamental traffic flow relationship q = k x v. For the same set of spot speeds, the time mean speed is always greater than the space mean speed, and the difference increases with the spread of the speeds. The speed and delay study measures the running time, the journey time and the delays along a route, using the moving car observation method, in which a test car travels with the traffic stream in both directions and the observer records the journey times and the number of overtaken and overtaking vehicles.

Solved Problem 3: Spot speeds of three vehicles at a point are 40, 50 and 60 km/h. Find the time mean speed and the space mean speed. Solution: Time mean speed = (40 + 50 + 60)/3 = 50 km/h. Space mean speed = 3 / (1/40 + 1/50 + 1/60) = 3 / (0.0250 + 0.0200 + 0.01667) = 3/0.06167 = 48.65 km/h. The time mean speed of 50 km/h is higher than the space mean speed of 48.65 km/h.

4. Origin and Destination, Parking and Accident Studies

The origin and destination study determines the travel pattern of the traffic, namely where the trips begin and where they end, and it is used for planning new roads, designing the road network, deciding the location of terminals and for the projection of future traffic. The common methods are the roadside interview method, in which vehicles are stopped and the drivers are interviewed, the license plate method, in which the number plates are recorded at different points and matched, the tag or postcard method, in which the drivers are given tags to be returned, and the home interview method, in which a sample of households is interviewed about their daily trips. The results are presented in the form of desire lines, which show the flow between the zones on a map.

The parking study measures the demand for parking and the parking characteristics of an area, such as the parking accumulation, the parking load, the parking turnover, the average duration of parking and the parking index. The parking accumulation is the number of vehicles parked at a given time, the parking load is the total parking space-hours used, and the turnover is the number of vehicles using a space in a given period. The accident study collects the data of the number, the location, the time and the causes of accidents, and computes the accident rate in terms of accidents per million vehicle-kilometres, using the formula R = (number of accidents x 10 to the power 6) / (vehicle-kilometres of travel). The accident black spots are identified from the collision diagrams and are given priority for improvement.

Solved Problem 4: A stretch of road carries a total travel of 5 million vehicle-kilometres in a year and has 40 reported accidents. Find the accident rate. Solution: R = 40 x 10 to the power 6 / 5 x 10 to the power 6 = 8 accidents per million vehicle-kilometres.

5. Quick Revision Tables

Table 1: Traffic Studies and Their Objectives

Study Purpose Common method
Volume study Count vehicles, design capacity Manual and automatic counters
Spot speed study Set speed limits, design speed Enoscope, radar meter
Speed and delay study Measure journey time and delays Moving car observation
Origin and destination Find trip pattern Roadside interview
Parking study Assess parking demand Accumulation survey
Accident study Find causes and black spots Collision diagrams

Table 2: Computed Quantities in Traffic Studies

Quantity Formula / definition Typical use
AADT Total annual volume / 365 Pavement design
Peak hour factor Peak hour volume / (4 x peak 15-min volume) Capacity analysis
85th percentile speed Speed below which 85 percent travel Speed limit setting
Time mean speed Arithmetic mean of spot speeds Speed comparison
Space mean speed Harmonic mean of spot speeds q = k x v relationship
Accident rate Accidents x 10^6 / vehicle-km Safety ranking

6. Mind Map

flowchart TD
    A[Traffic Studies and Surveys] --> B[Volume studies]
    A --> C[Speed studies]
    A --> D[Speed and delay studies]
    A --> E[Origin and destination studies]
    A --> F[Parking studies]
    A --> G[Accident studies]
    B --> B1[AADT and ADT]
    B --> B2[Peak hour factor]
    B --> B3[Design hourly volume]
    C --> C1[Spot speed]
    C --> C2[85th percentile speed]
    C --> C3[Time mean and space mean speed]
    E --> E1[Roadside interview]
    E --> E2[License plate method]
    E --> E3[Desire lines]
    G --> G1[Accident rate per million vehicle-km]
    G --> G2[Black spots]
    B1 --> H[Used for pavement design]
    C3 --> I[Space mean speed used in q = k x v]

7. Important Diagrams (SVG)

The following diagrams show the cumulative speed distribution curve used for fixing speed limits and the desire line diagram used in origin and destination studies.

Cumulative Speed Distribution Curve Speed (km/h) Cumulative percent 85th percentile speed 85% Speed limit set near the 85th percentile speed Median and 15th percentile speeds also read from this curve Time mean speed > space mean speed for same data Golden Rule The 85th percentile speed from the cumulative curve is used to fix the speed limit.

Desire Line Diagram from O-D Study Zone A (Origin) Zone B (Dest) Zone C (Origin) Zone D (Dest) 4000 trips 1500 trips 800 trips Width of desire line is proportional to trips Golden Rule Desire lines show the trip demand between zones, with width proportional to the volume.

8. Common Mistakes

  1. Many students use the peak hour volume directly as the design volume without applying the peak hour factor or the directional distribution.
  2. A frequent error is to treat the time mean speed and the space mean speed as equal; the time mean speed is always greater for the same data.
  3. Some candidates compute the space mean speed as the arithmetic mean instead of the harmonic mean of the spot speeds.
  4. Students often forget that the AADT is the annual total divided by 365 and use only the average of a few daily counts.
  5. A common mistake is to state that the 50th percentile speed fixes the speed limit; it is the 85th percentile speed that is used.
  6. Many candidates multiply the accident rate formula incorrectly and give the result without the unit of per million vehicle-kilometres.
  7. Some students confuse the roadside interview method with the home interview method; the roadside interview stops vehicles on the road while the home interview visits households.
  8. Another recurring error is to omit the expansion factor when converting a short-period count to the average daily traffic.

9. Exam Tips

  1. Memorise PHF = peak hour volume / (4 x peak 15-minute volume).
  2. Remember that AADT = total annual volume / 365 and is used for pavement design.
  3. The 85th percentile speed is used to set the speed limit.
  4. Use the harmonic mean, not the arithmetic mean, for the space mean speed used in q = k x v.
  5. Note the accident rate formula R = accidents x 10^6 / vehicle-kilometres.
  6. Associate each O-D method with its technique: roadside interview, license plate, tag and home interview.
  7. Remember that the moving car observation method measures journey time and delay.
  8. In every numerical, state the unit of the final answer, such as vehicles per day or accidents per million vehicle-kilometres.

10. Conclusion

Traffic studies and surveys convert the raw reality of the road into the numbers on which all planning and design decisions rest. In this chapter we have studied the volume studies that count the traffic, the speed studies that measure how fast it moves, the speed and delay studies that measure congestion, the origin and destination studies that reveal the trip pattern, and the parking and accident studies that address the parking demand and the safety of the road. The computations that turn the raw data into useful quantities, including the average annual daily traffic, the peak hour factor, the 85th percentile speed, the time mean and space mean speeds and the accident rate, have been explained through worked examples. Since every traffic signal, every pavement thickness and every road improvement is justified by the data collected in these studies, the ability to design and interpret these surveys is indispensable. The knowledge of the traffic demand gained here, combined with the material on traffic control from the previous chapter, prepares the candidate for the pavement design chapters that follow.