Time and Work is one of the most important and frequently tested chapters in RRB JE CBT-1 Mathematics. RRB asks 2 to 3 questions every year. The chapter tests the rate-of-work concept, where work is measured as a fraction of the total completed per unit time. Questions involve single workers, groups, alternations, wages distribution, and combined efficiency. The chapter also connects with Pipes and Cisterns, which is mathematically identical. The LCM method is the most powerful shortcut for solving these problems quickly.
If a person completes a work in D days, then in one day the person does 1/D of the work. The rate of work is 1/D. If two persons A and B working alone take a and b days respectively, their one-day work is 1/a and 1/b. Working together, their combined one-day work = 1/a + 1/b, and the total time = 1 / (1/a + 1/b) = (a x b)/(a + b). Example: A does work in 10 days, B in 15 days. Together: (10 x 15)/(10 + 15) = 150/25 = 6 days.
Take the LCM of all given time values as the total work. Then each worker's one-day work is LCM/days. Add the daily works of the workers who work together, and divide the total work by the combined daily work to get the time. Example: A in 12 days, B in 18 days. LCM = 36 units. A does 3 units/day, B does 2 units/day. Together 5 units/day. Time = 36/5 = 7.2 days. This method avoids fractions and is the standard RRB approach.
If A and B work on alternate days starting with A, in 2 days they together complete 1/a + 1/b of the work. The full work is completed in pairs of days until the remainder is finished by the person whose turn it is. Example: A takes 6 days, B takes 12 days. In 2 days A + B do 1/6 + 1/12 = 1/4 of work. In 8 days (4 pairs) they do 1 whole work? 4 x 1/4 = 1, so 8 days total.
When a worker joins or leaves during the work, solve in stages: compute the fraction of work done by the working set in each stage, and continue until the total equals 1. Example: A can do a work in 20 days. A works alone for 5 days doing 1/4 of the work. Remaining 3/4 is completed by A and B together at a combined rate; if B alone takes 30 days, combined rate = 1/20 + 1/30 = 1/12, so time for remaining = (3/4)/(1/12) = 9 days.
Wages are distributed in the ratio of the work done, which equals the ratio of the rates of working when time worked is the same. If A does a work in a days and B in b days, wages split in the ratio b : a (inverse of days). Example: A completes in 6 days, B in 12 days; if they work together and earn Rs 600, A : B = 12 : 6 = 2 : 1, so A gets Rs 400 and B gets Rs 200. If the total work period differs, wages follow the ratio of (days worked)/(total days needed).
Efficiency is the amount of work done per unit time. If A is twice as efficient as B, then A does work in half the time B takes. If A's efficiency is x percent more than B's, then A's time = B's time/(1 + x/100). Example: A is 50% more efficient than B, B takes 9 days; A takes 9/1.5 = 6 days.
If M1 men working H1 hours per day take D1 days and M2 men working H2 hours take D2 days for the same work, then M1 x D1 x H1 = M2 x D2 x H2. This is the universal work formula. Example: 6 men working 8 hours a day take 10 days; how many men needed to finish in 6 days working 10 hours a day? 6 x 8 x 10 = M2 x 10 x 6, so M2 = 8 men.
If A and B together take x days, B and C take y days, and C and A take z days, then: 2(1/a + 1/b + 1/c) = 1/x + 1/y + 1/z. From this, individual times can be extracted. Example: A+B = 6 days, B+C = 8 days, C+A = 12 days. Sum of pair rates = 1/6 + 1/8 + 1/12 = 9/24 = 3/8. Twice combined rate = 3/8, so combined rate = 3/16, all three together take 16/3 days.
flowchart TD
A[Time and Work problem] --> B{Type}
B -->|Single group works together| C[LCM method for total time]
B -->|Alternate days| D[Add daily rates in pairs]
B -->|Join or leave midway| E[Stage-wise fraction addition]
B -->|Wages distribution| F[Split in inverse ratio of days]
B -->|Efficiency comparison| G[Convert to time ratio]
B -->|Men-days-hours| H[Apply M1 D1 H1 = M2 D2 H2]
C --> I[Answer]
D --> I
E --> I
F --> I
G --> I
H --> I
flowchart LR
A[Assume total work = LCM of days] --> B[One-day work of each worker]
B --> C[Add rates of simultaneous workers]
C --> D[Total work / combined rate]
D --> E[Time in days]
| Quantity | Formula |
|---|---|
| One-day work of D-day worker | 1/D |
| A and B together | ab/(a + b) days |
| Combined daily rate | 1/a + 1/b |
| Men-days-hours constant | M1 x D1 x H1 = M2 x D2 x H2 |
| Wages ratio (A in a days, B in b days) | b : a |
| A x% more efficient than B | A time = B time/(1 + x/100) |
| All three from pair times | 2 x combined rate = 1/x + 1/y + 1/z |
| Fraction of work in t days | t/D |
Example 1: A can finish a work in 12 days and B in 18 days. In how many days will they finish it together? Combined = 1/12 + 1/18 = 5/36. Time = 36/5 = 7.2 days.
Example 2: A and B together can complete a work in 6 days, and A alone in 10 days. Find B alone. B's rate = 1/6 - 1/10 = 1/15. B takes 15 days.
Example 3: 12 men can do a work in 15 days. How many men are needed to do the same work in 9 days? 12 x 15 = M2 x 9, so M2 = 180/9 = 20 men.
Example 4: A, B, C alone take 20, 30, 60 days respectively. All work together; in how many days is the work done? LCM(20,30,60) = 60 units. Rates: 3, 2, 1 per day; total 6/day. Time = 60/6 = 10 days.
Example 5: A and B can do a work in 8 days; A alone in 12 days. A works for 4 days, then B joins. Total time? A's 4-day work = 4/12 = 1/3. Remaining 2/3. B alone = 1/(1/8 - 1/12) = 24 days. Combined rate = 1/12 + 1/24 = 1/8. Time = (2/3)/(1/8) = 16/3 days. Total = 4 + 5.33 = 9.33 days.
Example 6: A and B together earn Rs 450 for a job done in 6 days. A alone takes 10 days, B alone takes 15 days. Wages ratio = 15 : 10 = 3 : 2. A gets Rs 270, B gets Rs 180.
Example 7: A is twice as efficient as B. Together they take 12 days. Find B alone. Let B's days = x, A's days = x/2. Together: 1/x + 2/x = 3/x = 1/12, so x = 36. B takes 36 days.
Example 8: A does a work in 10 days. B is 25% more efficient than A. Find B's time. B's time = 10/1.25 = 8 days.
| Q No | Question | Answer |
|---|---|---|
| 1 | A in 20 days, B in 30 days; together? | 12 days |
| 2 | A+B in 12 days, A alone 18; B alone? | 36 days |
| 3 | 8 men in 12 days; days for 6 men? | 16 days |
| 4 | A,B,C at 10,15,20 days; together? | 60/13 = 4.62 days |
| 5 | 5 men x 8 hours x 20 days = ? men x 8 hours x 10 days | 10 men |
| 6 | A twice efficient, together 9 days; A alone? | 13.5 days |
| 7 | A works alternate days with B (A:6, B:12); total? | 8 days |
| 8 | Wages 300, A:9 days, B:6 days; A gets? | 120 |
| 9 | A in 15 days, B in 10 days; work together, B leaves after 4 days; A finishes rest in? | 5 more days |
| 10 | 1 man does 1/5 work in 2 days; total days for man? | 10 days |
| 11 | A+B=6, B+C=8, C+A=12; all three together? | 16/3 days |
| 12 | 6 pipes fill a tank in... (skip); A in 24 days, B in 12 days; together? | 8 days |
Time and Work is a top-weightage chapter in RRB JE CBT-1, with 2 to 3 questions that are almost never skipped by serious aspirants. RRB's favourite patterns are: LCM-based combined time, men-days-hours proportion, alternation of workers, wages distribution, and efficiency comparisons phrased as percentages. The LCM method alone solves the majority of questions without fractions, saving considerable time. Since the chapter is logically identical to Pipes and Cisterns, mastering one gives command over the other. Expect questions of moderate difficulty; practice daily with timed sets to keep calculation speed high.
Time and Work rewards systematic method over guesswork. By converting days into one-day rates, adopting the LCM total-work shortcut, and applying the men-days-hours relation, every standard question in this chapter becomes a quick, safe calculation. Strong command of this chapter also transfers directly to Pipes and Cisterns, making it one of the most productive investments in RRB JE CBT-1 Mathematics preparation.